Summary
In Wong v. New York Times Co., 297 A.D.2d 544, 549 (1st Dep't 2002), the First Department, following Russin, considered whether one general contractor would be liable under § 241(6) for injuries sustained by an individual who was supervised by a different general contractor.
Summary of this case from Barbosa v. 1 World Trade Ctr. L.L.C.Opinion
753
September 19, 2002.
Order, Supreme Court, New York County (Alice Schlesinger, J.), entered February 7, 2001, which, insofar as appealed from as limited by the briefs, granted that branch of plaintiffs' cross motion for partial summary judgment on liability on plaintiffs' Labor Law § 240(1) claim, denied Lehrer McGovern Bovis, Inc.'s (LMB) cross motion for summary judgment dismissing the complaint in its entirety and all cross claims asserted against it, and granted the motion of third party plaintiff George R. Hall, Inc. d/b/a George R. Hall Contracting (Hall) for summary judgment on the fifth cause of action in the third-party complaint (breach of contract to procure insurance) and granted judgment against Budco for indemnity for the full amount of liability including attorneys' fees and costs, unanimously modified, on the law, to 1) deny that branch of plaintiffs' motion for partial summary judgment against LMB on the Labor Law § 240(1) claim; 2) grant LMB's cross motion for summary judgment dismissing the complaint in its entirety and any cross claims and counterclaims for common law indemnification and contribution insofar as asserted against it; and 3) direct that Budco's indemnification of Hall is limited to costs and expenses for which Hall is not otherwise covered by its own policy of insurance; and otherwise affirmed, without costs. The Clerk is directed to enter judgment in favor of Lehrer McGovern Bovis, Inc. dismissing the complaint in its entirety and any cross claims and counterclaims for common law indemnification and contribution insofar as asserted against it.
SCOTT N. SINGER, for plaintiffs-respondents.
ERIC A. PORTUGESE, for defendants-respondents.
ERIC A. PORTUGESE, for third-party plaintiffs-respondents.
ROBERT L. BOYDSTUN, for third-party defendant-appellant.
Before: Andrias, J.P., Rosenberger, Lerner, Friedman, Marlow, JJ.
Defendant New York Times (hereinafter the Times) entered into a written contract with LMB to construct a 540,000-square-foot, three-story printing plant in Flushing, Queens. Construction of the plant involved two separate projects: the construction of the building and the installation of five huge printing presses. Pursuant to a construction agreement with the Times, defendant-appellant LMB was retained as construction manager to construct the building facility which would house the printing press machinery. LMB hired Vergara-Nastasi Industries, Inc. (Vergara), a carpentry subcontractor; Interstate, a steel subcontractor; and Century Maxim, a concrete subcontractor.
Defendants Rockwell International Corporation and Goss Graphic Systems, Inc., f/k/a Rockwell Graphic Systems, Inc., the Goss Division (collectively Goss) manufactured the printing presses. Goss entered into a sales agreement with the Times for the purchase and installation of the printing press equipment. Under the agreement, Goss had sole responsibility for the installation of the presses.
By purchase order, Goss retained the services of defendant George R. Hall, Inc., d/b/a George R. Hall, for the delivery, rigging and installation of the printing presses. The purchase order provided in relevant part that:
Subcontractor [Budco] agrees, at its expense, to procure and maintain such comprehensive general liability, worker's compensation and other insurance as is reasonable under the circumstances to protect Contractor [Hall] against damages, claims, obligations, liabilities, losses, costs and expense that may arise out of the work to be performed by Subcontractor, and except with respect to such worker's compensation insurance, such insurance will name Contractor as an additional insured with respect to such work.
Budco obtained liability insurance for itself and named Hall as an additional insured for excess coverage.
Hall in turn contracted with third-party defendant-appellant Budco Enterprises, Inc. (hereinafter Budco) to supply iron workers to perform the actual installation of the presses. Budco hired plaintiff Kwoksze Wong (hereinafter plaintiff) as an ironworker.
As part of the construction, concrete was poured as the floor where the printing presses would be installed. When the concrete was poured, a large space — called a press bay — was left open for each printing press. When each printing press was placed, the concrete subcontractor poured the rest of the concrete around it. However, during the time in which the space around the press had not yet been filled in, Vergara (the carpentry subcontractor) placed plywood boards over the open space. The bay was then roped off by perimeter cables. LMB was in charge of removing the plywood before the subcontractor finished pouring the concrete.
On September 30, 1996, plaintiff and another Budco crewman were working in the area of the press bay, dismantling a crane-like structure known as a gantry, which had been used to load the presses into the building. Plaintiff was standing on the plywood planking over the press bay, removing cross bracing from the gantry. He was not protected by a safety device other than a hard hat provided by his supervisor. The perimeter cables had been removed to facilitate the dismantling. Plaintiff lost his footing while attempting to control a guide rope by which he and his co-worker were to haul out the cross brace. Plaintiff fell, dropping approximately 13 feet.
Plaintiff and his wife commenced an action against, inter alia, LMB pursuant to Labor Law § 200, § 240, and § 241. Hall and Goss brought a third-party action against Budco which alleged, inter alia, that Budco had failed to procure insurance for Hall pursuant to the terms of the purchase order. Hall claimed that if any judgment were recovered by plaintiffs against Hall, Budco was responsible for all the "resulting damages" of Hall, including Hall's liability for plaintiffs' damages and for Hall's own legal fees and expenses.
Hall moved for summary judgment on the failure to procure insurance cause of action set forth in the third-party complaint, claiming that it was "entitled to indemnity from and for judgment over and against [Budco]." The Supreme Court granted Hall's motion finding that Budco was required to obtain for Hall the same kind of insurance it got for itself and provide Hall the same kind of protection.
Plaintiffs cross-moved for partial summary judgment against, inter alia, LMB on the issue of liability. LMB cross-moved for summary judgment dismissing the complaint in its entirety and for dismissal of any cross claims asserted against it. As relates to this appeal, the Supreme Court granted plaintiffs summary judgment against LMB on the Labor Law § 240(1) claim, denied summary judgment on the Labor Law § 241(6) claim, and granted summary judgment in LMB's favor dismissing the Labor Law § 200 claim. However, the court did not specifically state that any cross claims were dismissed.
Budco argues that it complied with the letter of the purchase order by obtaining "reasonable" insurance coverage for Hall, and that the court erred in finding that the excess insurance obtained did not satisfy that obligation. More specifically, Budco maintains that the purchase order did not specify that Budco had to obtain primary coverage, and that therefore it did not breach the agreement to procure insurance. However, Budco's argument has been squarely rejected by Pecker Iron Works of New York, Inc. v. Traveler's Insurance Company ( 290 A.D.2d 426, lv granted 98 N.Y.2d 605, 2002 N.Y. Lexis 1534). In any event, a contract should be construed in accordance with the parties' purpose (see Elmsmere Assoc. v. Gladstone, 153 A.D.2d 501, 506, as clarified upon reargument by 153 A.D.2d 821). Furthermore, "[a] fair and reasonable interpretation, consistent with that purpose, must guide the courts in enforcing the agreement" (Matter of Cromwell Towers Redevelopment Co. v. City of Yonkers, 41 N.Y.2d 1, 6). Budco claims that it was only required to provide "reasonable" coverage. However, as the Supreme Court found, only primary insurance would be reasonable under the circumstances of this case. Indeed, "additional insured" has "a well-understood meaning in the insurance industry as an `entity enjoying the same protection as the named insured'" (Del Bello v. General Accid. Ins. Co., 185 A.D.2d 691, quoting Rubin, Dictionary of Insurance Terms [Barron's 1987]).
Budco argues, in the alternative, that its damages are limited to out-of-pocket costs for insurance. Hall maintains that a construction contract is distinguishable from other contracts and, as a matter of public policy, Budco should make Hall whole regardless of the existence of its own insurance. In Kinney v. G.W. Lisk Co. ( 76 N.Y.2d 215), the Court of Appeals held that where a subcontractor breached its agreement to provide insurance for a general contractor, the subcontractor was liable for the resulting damages, including the general contractor's liability to plaintiff. However, in Inchaustegui v. 666 5th Avenue ( 96 N.Y.2d 111), the Court found that damages recoverable by a landlord for a tenant's breach of an agreement to obtain liability insurance for the landlord's benefit were limited to the landlord's out-of-pocket damages caused by the breach. Thus, where a landlord procured its own insurance, it may not look to the tenant for the full amount of the settlement and defense costs it incurred in an underlying personal injury action against the landlord and tenant by an employee of the tenant. Having procured its own insurance, the landlord sustained no loss beyond its out-of-pocket costs. The Court distinguished Kinney because the question whether resulting damages could be minimized by any insurance the general contractor had obtained was not raised by the parties or considered by the Court.
Hall's attempt to limit Inchaustegui to landlord/tenant cases is unavailing as this Court has calculated damages in construction cases in accordance with Inchaustegui. For example, in Sheppard v. Blitman/Atlas Building Corp. ( 288 A.D.2d 33), we held that the proper measure of damages is the full cost of insurance, i.e., the premiums it paid for its own insurance, any out-of-pocket costs that may have been incurred incidental to the policy and any increase in future insurance premiums resulting from the present liability claim (accord Trokie v. York Preparatory School 284 A.D.2d 129; cf. McDonald v. Tishman Interiors Corp. ( 290 A.D.2d 266) [any limitation of the damages to which a subcontractor and his employee may be entitled pursuant to Inchaustegui would be premature inasmuch as court is unable to determine which insurance policies will cover the claimed injuries, and to what extent]).
Accordingly, the Supreme Court properly granted Hall summary judgment on the fifth cause of action of the third-party complaint for breach of the agreement to procure insurance.
However, the court erred in allowing Hall to recover the full amount of its liability to plaintiffs.
LMB maintains that it played no role in the work for which plaintiff was hired. Indeed, the record reveals that the Times hired LMB solely for the construction of the building. The contract between the Times and Goss for installation of the printing presses was separate. Under that contract, Goss had sole responsibility for installing the presses. Moreover, plaintiff was hired mid-job by Budco, a subcontractor of Hall, which was a subcontractor of Goss. Plaintiff had nothing to do with the construction of the building, and LMB, in turn, had nothing to do with dismantling of the gantry, which was the activity plaintiff was engaged in when he fell.
The Supreme Court nevertheless granted summary judgment to plaintiff against LMB on Labor Law § 240(1) because LMB, as overseer of the concrete and carpentry subcontractors, was responsible for the plywood-covered gaps in the pressroom floor, on which plaintiff lost his footing. The court also found that plaintiff had a valid § 241(6) claim based on Industrial Code 12-1.7 and that "all [defendants] are arguably responsible under this statute." Accordingly, the court denied both plaintiffs' and LMB's cross motions for judgment on that claim.
The court should have granted summary judgment to LMB on the Labor Law § 240(1), and § 241(6) claims. The court improperly focused on the cause of the injury, instead of the nature of LMB's relationship to the work in which plaintiff was engaged at the time of the injury (see Campanella v. St. Luke's Roosevelt Hosp., 247 A.D.2d 294, 296). Indeed, in Russin v. Louis N. Picciano Son ( 54 N.Y.2d 311, 317), the Court of Appeals held that the current provisions of Labor Law § 240, and § 241 "were intended to shift responsibility for construction site injuries from those parties without control of the injury producing activity to the general contractor and owner [emphasis added]." Here, although LMB was a general contractor, it was so only with respect to the building construction. There was a separate prime contractor for the installation of the printing presses. Thus, LMB cannot be held liable because it was "never delegated the general construction work in which plaintiff was engaged at the time of his injury and therefore [was] in no way responsible for the work giving rise to the duties referred to in and imposed by sections 240 and 241 of the Labor Law" (id. at 318). Moreover, if liability is to be premised on supervisory control, it must be control over the work in which plaintiff was engaged at the time of his injury (see Chae v. Lee Nat'l Corp., 282 A.D.2d 317, 318, lv denied 97 N.Y.2d 602; see also Maggi v. Innovax Methods Group Co., Inc., 250 A.D.2d 576, lv denied 92 N.Y.2d 819).
Finally, the Supreme Court should have dismissed any common-law contribution and indemnification cross claims and counter claims asserted against LMB when it granted summary judgment dismissing plaintiff's Labor Law § 200 claim (see Taylor v. VAW of America, 276 A.D.2d 621, 622).
We need not reach plaintiffs' other contentions raised under Labor Law § 240(1)in light of our determination.
THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.