William v. Fradkoff

Appellate Division of the Supreme Court of New York, First Department
Mar 1, 2007
38 A.D.3d 208 (N.Y. App. Div. 2007)

Opinion

No. 374.

March 1, 2007.

Order, Supreme Court, New York County (Marcy Friedman, J.), entered July 22, 2005, which denied defendants-appellants' motion to dismiss the complaint and defendant-respondent's cross claim for indemnification or contribution, unanimously affirmed, with costs.

Thelen Reid Brown Raysman Steiner LLP, New York (Brian J. Markowitz of counsel), for appellants.

Zetlin De Chiara LLP, New York (Alexander D. Tuttle of counsel), for William C. Samuels, respondent. Herbert Adler, White Plains, for Alex R. Fradkoff, respondent.

Before: Tom, J.P., Mazzarelli, Williams, McGuire and Kavanagh, JJ.


Plaintiff's allegations that appellants were aware that the purpose of their architectural services was for plaintiffs renovation project and that their drawings, plans and recommendations would be used by plaintiff for the project suffice to show the functional equivalent of privity and state a cause of action for negligence ( see Ossining Union Free School Dist. v Anderson LaRocca Anderson, 73 NY2d 417, 419). A cause of action for negligent misrepresentation is stated by plaintiffs allegations that appellants submitted inaccurate work permits bearing plaintiff's forged signature ( see Hudson Riv. Club v Consolidated Edison Co. of N.Y., 275 AD2d 218, 220). A cause of action for fraud is stated by plaintiffs allegations that appellants concealed that violations existed throughout the duration of the project, that construction proceeded without the proper permits, that numerous design and construction deficiencies plagued the project, and that appellants were retained to perform certain design services that could only be performed by a licensed architect ( see John Blair Communications v Reliance Capital Group, 157 AD2d 490, 492; Swersky v Dreyer Traub, 219 AD2d 321, 327). Defendant-respondent's cross claim, which effectively alleges that appellants were delegated the former's responsibilities under his contract with plaintiff, states a cause of action for indemnification ( see 17 Vista Fee Assoc. v Teachers Ins. Annuity Assn. of Am., 259 AD2d 75, 80). The cross claim is not defeated by the fact that it arises out of defendant-respondent's written agreement with appellants, where it also claims tort liability based on appellants' negligent performance of architectural services. We have considered appellants' remaining arguments and find them unavailing.


Summaries of

William v. Fradkoff

Appellate Division of the Supreme Court of New York, First Department
Mar 1, 2007
38 A.D.3d 208 (N.Y. App. Div. 2007)
Case details for

William v. Fradkoff

Case Details

Full title:WILLIAM C. SAMUELS, Respondent, v. ALEX R. FRADKOFF, Respondent, and…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Mar 1, 2007

Citations

38 A.D.3d 208 (N.Y. App. Div. 2007)
832 N.Y.S.2d 499

Citing Cases

XPO Logistics, Inc. v. Malcomb

Even assuming arguendo that the relationship between Pavarini and WM and/or Cerami were sufficient to impose…

Travelers Casualty Surety v. Dormitory Authority

y [the defendant]," did not constitute the functional equivalent of privity); Marcellus, 755 N.Y.S.2d at 476…