{ΒΆ 22} Sterling seeks to distinguish its situation from the general prohibition against restitution because Main Event retained nearly $2 million between the retainage and the value of the unpaid contract price at the time Omni breached, without consideration of subsequent events. Sterling claims that Main Event's payments to release the mechanic's liens to the numerous other unpaid subcontractors and expenditures to finalize the project should not impact Sterling's claim for unjust enrichment, citing Wickford Metal Prods. v. Tri-Village Church of Christ, 5th Dist. Licking No. 98CA47, 1998 Ohio App. LEXIS 6499, 1 (Dec. 1, 1998). In Wickford, even though the property owner paid more to third parties to complete the project after the general contractor breached its contracts with the owner and a subcontractor