U.S. v. Ohio Edison Company

United States District Court, S.D. Ohio, Eastern Division
Jan 30, 2009
CASE NO. C2-99-1181 (S.D. Ohio Jan. 30, 2009)

Opinion

CASE NO. C2-99-1181.

January 30, 2009


ORDER


The Defendant, Ohio Edison, has requested an extension of time in which to elect whether to install flue gas desulfurization ("FGD") technology, termed scrubbers, on Units 4 and 5 of the Burger Plant. Under the Consent Decree, the existing date for meeting such election was December 31, 2008.

The Court finds, in its discretion, that an extension of ninety (90) days is appropriate. Ohio Edison shall make an election on or before March 31, 2009 indicating whether it intends to install FGDs on the Burger Units.

Based upon representations made by the parties in legal memoranda, in the event Ohio Edison elects to install FGDs at the Burger Plant, all parties shall be bound by the terms and conditions of the Memorandum of Understanding reached on December 18, 2008.

Based upon the foregoing, the Motion to Extend the Deadline to Elect filed by Ohio Edison is DENIED with prejudice.

IT IS SO ORDERED.


Summaries of

U.S. v. Ohio Edison Company

United States District Court, S.D. Ohio, Eastern Division
Jan 30, 2009
CASE NO. C2-99-1181 (S.D. Ohio Jan. 30, 2009)
Case details for

U.S. v. Ohio Edison Company

Case Details

Full title:UNITED STATES OF AMERICA, et al., Plaintiffs, v. OHIO EDISON COMPANY, et…

Court:United States District Court, S.D. Ohio, Eastern Division

Date published: Jan 30, 2009

Citations

CASE NO. C2-99-1181 (S.D. Ohio Jan. 30, 2009)