From Casetext: Smarter Legal Research

United States Fidelity G. Co. v. Md. Cas. Co.

Supreme Court of Mississippi, In Banc
Feb 10, 1941
191 Miss. 103 (Miss. 1941)

Opinion

No. 34228.

December 23, 1940. Suggestion of Error Overruled February 10, 1941.

1. MECHANICS' LIENS.

Where contractor under contract with federal government for construction of levee earthwork sublet a portion of contract and subcontractor after performing part of subcontract assigned it to another, and assignee of subcontract executed a bond for payment of all debts incurred for labor and materials, assignee's contract and bond provided by it clearly indicated that parties did not intend that assignee was to assume liabilities incurred by subcontractor, and, under doctrine of "expressio unius est exclusio alterius," assignee's contract and bond would not be construed "retroactively," so as to impose liability upon assignee and its surety for liabilities incurred by subcontractor (Code 1930, sec. 2276; 40 U.S.C.A., sec. 270).

2. MECHANICS' LIENS.

Under statute providing that, where an owner of a building lets a private contract for construction and takes a bond, bond inures to benefit of laborers and materialmen, a retroactive or retrospective bond is not required (Code 1930, sec. 2276).

3. STATUTES.

Statutes are usually construed to be prospective and operate only in the future.

The statute providing that, where an owner of a building lets a private contract for construction and takes a bond, bond inures to benefit of laborers and materialmen, does not cover labor and materials furnished to a subcontractor (Code 1930, sec. 2276).

5. MECHANICS' LIENS.

Where subcontractor of a part of contract with federal government for construction of levee earthwork assigned subcontract to another, and assignee executed a bond for payment of all debts incurred for labor and materials, and assignee thereafter sublet contract back to assignor, assignor became subcontractor of assignee, under statute providing that, where an owner of a building lets a private contract for construction and takes a bond, bond inures to benefit of laborers and materialmen, and hence assignee's bond would not secure payment of debts incurred for labor and materials by assignor (Code 1930, sec. 2276).

ON SUGGESTION OF ERROR. (In Banc. Feb. 10, 1941.) [199 So. 278. No. 34228.]

APPEAL AND ERROR.

Suggestion of error based on mere irregularities of expression in opinion and making gratuitous comments on minor aspects of the litigation must be overruled.

APPEAL from the chancery court of Washington county, HON. J.L. WILLIAMS, Chancellor.

Butler Snow, of Jackson, for appellant.

Elkas and surety were liable to remote materialmen.

U.S. for use of Hill v. Am. Surety Co., 200 U.S. 197, 50 L.Ed. 437; Mankin v. U.S., use, etc., 215 U.S. 535, 54 L.Ed. 315.

Parties to whose rights subrogation is sought are not necessary parties.

Taylor v. Webb, 54 Miss. 36; Griffith's Chan. Practice, secs. 107-110; Hill v. Ritchie, 90 Vt. 318, L.R.A. 1917A, 731; Fridenburg v. Wilkinson, 20 Fla. 359; U.S.F. G. Co. v. Singleton, 206 Ala. 437, 90 So. 296; Singleton v. U.S.F. G. Co., 109 Ala. 506, 70 So. 169; Swain v. Stockton Savings, etc., Soc., 78 Calif. 600, 12 Am. S.R. 114; 60 C.J. 831; Prestridge v. Lazar, 132 Miss. 168, 95 So. 837; Robinson v. Sullivan, 102 Miss. 581, 159 So. 846; Doty v. Timber Co., 114 Miss. 872, 75 So. 602.

Judgment paid by surety is transferred by operation of law.

Secs. 2959, 2961, Code of 1930; Quinn v. Alexander, 125 Miss. 690, 88 So. 170.

When the Council Lewy Company accepted the assignment, in law it became bound to perform all the terms and obligations of the contract of January 3, 1933, and became obligated to pay all claims against Elkas on account of the performance of that part of the work covered by the contract of January 3, and to completely indemnify Elkas against any loss on account of that part of the contract assigned to them, and became liable to all laborers and materialmen, to which Elkas was liable under his original contract and bond with the government.

5 C.J. 977; Atlantic, etc., R. Co. v. Atlantic, etc., Co., 147 N.C. 368, 23 L.R.A. (N.S.) 223; Jenkins v. City Ice Fuel Co., 160 So. 215; Rockwell v. Edgcomb, 72 Wn. 694, 131 P. 191, 45 L.R.A. (N.S.) 661; Page on Contracts, p. 4006, sec. 2263; 4 Am. Jur. 234, 310, 311; A.L.I., Restatement of Contracts, sec. 164.

The bond and contract must be treated as one instrument.

Hall-Miller Decorating Co. v. Nat. Surety Co., 104 Miss. 626, 61 So. 700; Standard Oil Co. v. Nat. Surety Co., 143 Miss. 841, 107 So. 559; U.S.F. G. Co. v. Marathon Lbr. Co., 119 Miss. 802, 81 So. 492; Note, 77 A.L.R. 46, 47, 62.

Contract to indemnify owner obligates contractor to pay for material.

Pacific States Electric Co. v. U.S.F. G. Co. (Cal.), 293 P. 812; Callan v. Empire State Surety Co., 20 Calif. App. 483; Smith v. Fid. Dep. Co. (Tex.), 280 S.W. 767; Stoddard v. Hibler, 156 Mich. 335; Hiewit v. Carter 25 Neb. 460; Friend v. Ralston, 35 Wn. 422; Lichtentage v. Feital, 133 La. 931, 37 So. 880; Sailling v. Morrell, 97 Neb. 454, 150 N.W. 195; Nye-Schneider-Fowler Co. v. Rosser, 103 Neb. 614, 173 N.W. 605; Amer. Bonding Co. v. Pueblo Inv. Co., 150 Fed. 17; Classon v. Bailey, 161 Ind. 611; Brown H. Co. v. Ligon, 92 Fed. 851.

It is true that the bond given by The Council Lewy Company and the Maryland Casualty Company, on its face, does not purport to bind the appellees to pay laborers and materialmen's claims, but under the contract, The Council Lewy Company assumed the obligations of Elkas under the original contract; that the bond guaranteed the faithful performance of that contract and, as a consequence, appellees became jointly and severally liable to Elkas and appellant, as subrogee, for all claims paid. And this is so, whether the claims arose prior or subsequent to January 3, 1933, or prior or subsequent to the 14th day of January, 1933.

The contract of January 3, 1933, and the bond of appellees are governed by the private contractor's statute (sec. 2276, Code 1930) under such cases as Davis Company, Inc., v. D'Lo Guaranty Bank, 162 Miss. 829, 138 So. 802; U.S. for use, etc., v. Md. Cas. Co., 10 F. Supp. 982; Landis Young v. Gossett Winn, 169 So. 178.

Section 2276, Code of 1930, has the effect to write into the bond given by The Council Lewy Company, as principal, and the Maryland Casualty Company, as surety, the obligation to pay all persons furnishing labor and material under that contract. Indeed, had such obligation been expressly excluded, the bond, nevertheless, would have inured to the benefit of such materialmen.

Hartford Acc. Ind. Co. v. Natchez Inv. Co., 161 Miss. 198, 132 So. 535; Hartford Acc. Ind. Co. v. Nelson, 291 U.S. 352, 78 L.Ed. 840; Union Ind. Co. v. Acme Blow Pipe Sheet Metal Works et al., 150 Miss. 332, 117 So. 251; Commercial Bank of Magee v. Evans, 145 Miss. 643, 112 So. 482; U.S.F. G. Co. v. Parsons, 147 Miss. 335, 112 So. 469, 53 A.L.R. 88.

The instrument executed by Martin Carrithers Bros. to The Council Lewy Company under date of January 14, 1933, was an assignment of the contract of January 3, 1933. But even if it be said that this contract was a mere sub-letting, it does not affect the case because The Council Lewy Company agreed to indemnify and save harmless Elkas from all liability. And it follows that when appellant discharged the original primary obligation of Elkas, which appellees had assumed, it stood in Elkas' shoes and became entitled to enforce the contract of indemnity just as Elkas might have done.

Wynn, Hafter Lake, of Greenville, and Watkins Eager, of Jackson, for appellee.

The bond executed by the Maryland Casualty Company, as surety for Council Lewy Company, was prospective and not retroactive, and, therefore, the appellant was only liable for the completion of the unfinished portion of the project and for the payment of claims for labor and material thereafter furnished to Council Lewy.

Council Lewy, as assignees of Elkas and Martin Carrithers Bros., did not become personally liable to the assignors by reason of such assignment.

Atlantic North Carolina R.R. Co. v. Atlantic North Carolina Co., 147 N.C. 368, 61 S.E. 184, 23 L.R.A. (N.S.) 223; 4 Am. Jur. 234, 310; Rockwell v. Edgcomb (Wash.), 72 Wn. 694, 131 P. 191, 45 L.R.A. (N.S.) 661; Grant v. Harner (Ariz.), 239 P. 296; Jenkins v. Ice Fuel Co. (Fla.), 160 So. 215; Lunt v. Lorscheider (Ill.), 121 N.E. 237; Page on Contracts; Restatement of the Law, Contracts, par. 164.

Regardless of the liability of Council Lewy under the contract of assignment of January 14, 1939, the bond executed by the Maryland Casualty Company is prospective and covered liability for the completion of the work and for the payment of claims for labor and material furnished thereunder to Council Lewy, principal in the bond.

The bond sued upon will be construed just as any other contract; the appellee had the right to limit its coverage.

Am. Life Acc. Ins. Co. v. Nidlinger, 73 So. 875, 113 Miss. 84, 4 A.L.R. 871; Berry v. Lamar Life Ins. Co., 165 Miss. 405, 142 So. 445, 145 So. 887; Brotherhood of Railroad Trainmen v. Bridges, 144 So. 554, 164 Miss. 356; Continental Cas. Co. v. Hall, 80 So. 605, 118 Miss. 871; Ferguson v. Provident Life Acc. Ins. Co., 155 So. 168, 170 Miss. 504; Ga. Cas. Co. v. Cotton Mills Product Co., 132 So. 73, 159 Miss. 396; Lavender v. Volunteer State Life Ins. Co., 157 So. 101, 171 Miss. 169, 182; Locomotive Engineers' Mut. Life Acc. Ins. Co. v. Meeks, 127 So. 699, 157 Miss. 97; New Amsterdam Cas. Co. v. Perryman, 140 So. 342, 162 Miss. 864; Southern Home Ins. Co. v. Wall, 127 So. 398, 156 Miss. 865; U.S.F. G. Co. v. Citizens' State Bank of Moorhead, 116 So. 605, 150 Miss. 386.

Surety bonds are ordinarily construed as operating prospectively unless a retroactive construction is required.

Chicora Bank v. U.S.F. . G. Co. (S.C.), 77 A.L.R. 857; Fid. Dep. Co. v. Bank of Pascagoula, 151 So. 373, 169 Miss. 755; Johnson v. Bobbitt, 81 Miss. 339; Nunnery v. Baker, 195 So. 314, 188 Miss. 596; Royal Ind. Co. v. Am. Vitrified Products Co. (Ohio), 62 A.L.R. 407, 410; Salley v. Globe Ind. Co., 43 A.L.R. 92.

The bond sued upon was conditioned only upon the completion of the unfinished work and the payment for labor and material furnished Council Lewy therein.

13 C.J. 537.

The expression in a contract of one or more things of a class implies the exclusion of all not expressed, although all would have been implied had none been expressed.

13 C.J. 537.

The rule is applicable here. The express mention of such claims for labor and material as were to be covered by the bond necessarily excludes any other claims for labor and material.

Where a contractor enters into a contract to construct an improvement and agrees therein to pay all claims for labor and material arising out of the contract and gives a bond with a surety providing merely for the faithful performance of the contract, the surety is liable directly to persons furnishing labor and material in the prosecution of the work. The cases announce such a proposition and go no further. In each and every case, however, the bonds are held to be prospective in liability and in no case is liability imposed on a surety for labor or material previously furnished.

Alpena, Use of Zess, v. Title Guaranty S. Co., 138 Mich. 678, 123 N.W. 536; Am. Bonding Co. v. Pueblo Inv. Co., 150 Fed. 17; Am. Surety Co. v. James A. Dick Co., 23 F.2d 464, certiorari denied 278 U.S. 624, 73 L.Ed. 545; Brown Heyward v. Ligon (Mo.), 92 Fed. 851; E.I. Dupont De Nemours Powder Co. v. Culgin-Pace Contracting Co., 206 Mass. 585, 92 N.E. 1023; Fogarty v. Davis, 305 Mo. 288, 264 S.W. 879; Lichtentage v. Feital, 113 La. 93, 37 So. 880; Morton v. Harvey, 57 Neb. 304, 77 N.W. 808; Ney-Schneider-Fowler Co. v. Roeser, 103 Neb. 614, 173 N.W. 605; Pacific States Electric Co. v. U.S.F. G. Co. (Cal.), 293 P. 812; Pickle Marble Granite Co. v. McClay, 54 Neb. 661, 74 N.W. 1062; Sailling v. Morrell, 97 Neb. 454, 150 N.W. 195; Smith v. Fid. Dep. Co. (Tex.), 280 S.W. 767; Standard Oil Co. v. Nat. Surety Co., 143 Miss. 841, 107 So. 559; U.S.F. G. Co. v. Marathon Lbr. Co., 119 Miss. 802, 81 So. 492.

Section 2276, Miss., 1930 Code, is prospective, not retroactive. It contemplates the giving of a bond for the performance of future covenants. The statute does not contemplate the giving of a bond for previously incurred obligations.

Hester, Sheriff, v. Copiah County, 191 So. 496, 186 Miss. 716; Nunnery v. Baker, 188 Miss. 596, 195 So. 314; Hartford Acc. Ind. Co. v. Natchez Inv. Co., 161 Miss. 198, 132 So. 535, 291 U.S. 352, 78 L.Ed. 840; Union Indemnity Co. v. Acme Bros. Pipe Metal Works, 150 Miss. 332, 117 So. 251; Commercial Bank of Magee v. Evans, 145 Miss. 643, 112 So. 482; U.S.F. G. Co. v. Parsons, 147 Miss. 325, 112 So. 469, 53 A.L.R. 88.

Since the bond sued on is a private contract under Section 2276, Miss. Code of 1930, the same would not cover labor and material furnished to any sub-contractor other than to Council Lewy. None of the labor and material going into the contract was furnished to Council Lewy.

Ala. Marble Co. v. U.S.F. G. Co., 146 Miss. 414, 111 So. 573.

Argued orally by Geo. Butler, for appellant, and by W.H. Watkins, Sr., for appellee.


The appellant, United States Fidelity and Guaranty Company, filed its bill in the chancery court seeking to recover from the appellees, Council Lewy Company and the surety on its bond, the amount of a judgment which had been recovered against it in the federal court by materialmen, also court costs and attorneys' fees.

Nothwithstanding that the court below sustained demurrers to the original bill, there was an amendment of the bill and the case was tried upon a stipulation of facts which admitted practically all of the allegations of the bill, but denied the legal conclusions of the pleader; and upon a full final hearing, the court below dismissed the bill.

Since the court below disposed of the case upon a full final hearing, we think it unnecessary to discuss the demurrer. The facts necessary to state are set forth, as follows:

On October 14, 1932, Dave Elkas entered into a written contract with the United States Government, whereby he agreed, for a stipulated price, to furnish all labor and material required in the construction of levee earthwork, according to Government specifications. Included as a part of that construction work was an item described as "L-290-B," which item alone is involved in this controversy.

Pursuant to this contract, Elkas executed a bond for $102,000 with the appellant, United States Fidelity Guaranty Company, as surety, for the faithful performance of the contract and for the prompt payment of all debts incurred for labor and materials furnished to Elkas for the prosecution and completion of that construction job.

After Elkas executed the above-mentioned contract and bond, he entered into an oral contract with Jack Martin and J.E. Pryor for the construction of the levee item, L-290-B, in which oral contract Martin Pryor agreed to furnish all labor and material and perform the necessary work to complete that item in accordance with Elkas' original contract with the Government.

On November 28, 1932, Pryor sold his interest in the firm of Martin Pryor to P.P. and T.M. Carrithers, and thereupon the firm of Martin Carrithers Brothers agreed to perform the contract with Elkas as to L-290-B, and the latter firm entered upon a performance of that contract until January 3, 1933, on which date Elkas and Martin Carrithers Brothers entered into a written contract, by which the latter was to perform Elkas' contract with the Government in accordance with the specifications, as to the item in controversy. Martin Carrithers Brothers agreed therein to perform and complete all of Elkas' obligations so far as that item was concerned, and they further agreed to execute a bond in Elkas' favor for $33,000, which bond "shall completely indemnify Elkas from any failure of Martin Carrithers Brothers to perform each and all of the obligations of this contract." The bond was to be a part of the contract and was to contain the same provisions and conditions as the bond executed by Elkas to the Government, limited to the item in controversy.

Martin Carrithers Brothers failed to execute a bond, but entered upon the construction work between January 3, 1933, and January 14, 1933, and on the latter date assigned in writing their contract to Council Lewy Company, being all of their right, title, interest and benefits in their contract with Elkas. This assignment included money previously earned by Martin Carrithers Brothers, and stated that Elkas should pay same to Council Lewy Company. This assignment was executed by Martin Carrithers, Dave Elkas and Council Lewy Company, on January 14, 1933.

On January 31, 1933, Council Lewy Company, as principal, executed a bond with the Maryland Casualty Company, as surety, in the sum of $33,000 in favor of Elkas, as obligee, conditioned that Council Lewy Company had entered into a contract with Elkas on January 14, 1933, for constructing the levee item in controversy. On January 14, 1933, Council Lewy Company sublet their contract to Martin Carrithers Brothers as to said item, reserving to itself the option to construct 200,000 cubic yards of said work on the north end of said project. Elkas was to pay Council Lewy Company 14 cents per cubic yard, and the latter was to pay Martin Carrithers Brothers 13 1/2 cents per cubic yard. Subsequent to January 14, 1933, Martin Carrithers Brothers performed in part this contract, but Council Lewy Company completed it later.

Prior to January 3, 1933, Martin Carrithers Brothers earned on their contract $3,702.60. Between January 3rd and 14th, 1933, they earned $960.34. Prior to January 14th, Martin Carrithers Brothers incurred debts for labor and material on this project in the total sum of $3,847.26, of which $2,476.16 was incurred by Martin Carrithers Brothers prior to January 3, 1933. $1,043.81 was incurred by Martin Carrithers Brothers between January 3rd and 14th, 1933, and $327.29 was incurred by Martin Carrithers Brothers after January 14, 1933.

The federal court at Clarksdale rendered a judgment against Elkas and the United States Fidelity Guaranty for the above-mentioned sums, with interest thereon. Prior to this federal court judgment, the United States Fidelity Guaranty Company demanded in writing that the Maryland Casualty Company, as surety of the Council Lewy Company, defend the suit. This, the casualty company declined to do. The judgment in the federal court dismissed the suit as to these appellees and others, without adjudicating their rights inter sese. The appellant, the United States Fidelity Guaranty Company, paid all of the judgment and costs in March, 1936, including fees allowed an auditor and stenographer.

The basis of the liability contended for by the appellant is the contract or assignment dated January 14, 1933, and the bond of Council Lewy Company payable to Elkas dated January 31, 1933. Referring to the written contract by Martin Carrithers Brothers and Elkas, the obligation of that contract was that Martin Carrithers Brothers "hereby agree to furnish all labor and materials and perform all work required for the construction of said earth work known as Item L-290-B in strict accordance with the plans, specifications, schedules and drawings which are attached and made a part of the original contract . . . just as if fully copied herein.

"It is further agreed that the parties of the second part (Martin Carrithers Brothers) shall complete and perform all the obligations imposed on the party of the first part by said contract in respect to said Item L-290-B; and the parties of the second part shall, in all details, strictly comply with the aforesaid original contract; . . .

"It is further understood and agreed and made a condition of this contract that the parties of the second part shall furnish to the party of the first part (Elkas) a bond in some Surety Company, to be approved by the party of the first part, which bond shall completely indemnify the party of the first part from any failure of the parties of the second part to perform each and all obligations of this contract . . ."

The bond referred to was never furnished by Martin Carrithers Brothers to Elkas.

Coming now to the pertinent part of the contract entered into and executed by Council Lewy Company, Dave Elkas and Martin Carrithers Brothers on January 14, 1933, we find recited therein that "the parties of the first part do hereby set over and assign all of their right, title, interest and benefits under the conditions of the contract dated the 3rd day of January, 1933" (naming the parties to the contract). This contract was assigned to Council Lewy Company. Elkas agreed therein to deliver all of the money to Council Lewy Company which he was to pay under the original contract to Martin Carrithers Brothers; Martin Carrithers Brothers assented to that arrangement; and "the same (levee contract) to be performed in accordance with the terms and specifications on file in the office of the United States Government Engineer, in Memphis, Tennessee." Now, as to the bond executed by the Maryland Casualty Company as surety of the Council Lewy Company. The stipulation in the bond was: "Now, therefore, if the principal shall well and truly perform and fulfill all the undertakings, covenants, terms, conditions and agreements of said contract during the original term of said contract and any extensions thereof that may be granted by the Obligee with or without notice to the Surety, and during the life of any guaranty required under the contract, and shall also well and truly perform and fulfill all the undertakings, covenants, terms, conditions, and agreements of any and all duly authorized modifications of said contract that may hereafter be made, notice of which modifications to the surety being hereby waived, and if said contract is for the constructions or repair of a public building or a public work within the meaning of the act of August 13, 1934, as amended by act of February 25, 1905, shall promptly make payment to all persons supplying the principal with labor and materials in the prosecution of the work provided for in said contract, and any such authorized extension or modification thereof, then this obligation to be void; otherwise to remain in full force and virtue."

It will be observed from this statement of facts, and the recitals in Council Lewy Company's contract and bond that this was in the assignment referred to in the textbooks signed only by the assignor, but the rights and duties of all parties were set forth and delimited by them in the contract. There is no ambiguity in the contract and bond here sued on. There is nothing left to be construed. The parties set forth their mutual obligations.

The obligation assumed by Council Lewy Company as to the levee work, which Elkas was bound to complete by his original contract and bond with the Government, is in these words: "the same to be performed in accordance with the terms and specifications on file in the office of the United States Government Engineer, in Memphis, Tennessee." The bond limited its liability so far as payment for materials and labor to that which was furnished to Council Lewy Company. There was no effort on the part of the parties then, by the contract or the bond, to have Council Lewy Company and their surety assume Elkas' debt for labor and materials, nor Martin Carrithers Brothers' debt for labor and materials. The appellees here assumed a prospective obligation. That is clear and unequivocal. At the time the contract was entered into on January 14, 1933, Elkas was liable for labor and materials incurred up to that date under his original contract and bond. He owed the debt by his bond to the Government. See 40 U.S.C.A., sec. 270. Likewise, Martin Carrithers Brothers owed these debts, but the language which we have quoted demonstrates that Council Lewy Company did not assume the payment of the debts which had accrued against the assignor, Martin Carrithers Brothers, for which Dave Elkas was primarily liable under the Act of Congress to which we have referred. It is also demonstrated by the judgment rendered by the federal District Court at Clarksdale. The bond is to be construed in conjunction with the contract. The bond of the Maryland Casualty Company is to be construed with the contract assigned to the Council Lewy Company, and it is clear from the bond that the surety only agreed to become responsible for material and labor furnished to its principal to-wit: The Council Lewy Company. There is no room to imply a contract to pay past-due debts on the part of the assignee. The record indicates that Elkas and the assignor, Martin Carrithers Brothers, knew or should have known of these debts; and the language of the contract is so plain as to exclude all implication. In other words, the doctrine of expressio unius must be applied to this contract and bond. See 13 C.J. 537, Paragraph 12, 17 C.J.S., Contracts, sec. 312.

The record shows that the monies earned by the assignor were promptly paid over to Council Lewy Company; and it is agreed in this record that sums of money were seasonably paid over to the assignor. However, the record does not show what became of the ten per cent retainage which Elkas had a right to retain under the contract made on January 3, 1933; nor does it show whether or not the assignors, Martin Carrithers Brothers, expended this money for labor and materials on this item — L-290-B. It is not even contended that it was not so paid out. It was imperative that Elkas perform his contract with the Government. He evidently realized that he could not complete his contract as he assigned same and required bond therefor. He is bound by the terms of that contract and the bond. No obligation was assumed by Council Lewy Company to pay his debts. Elkas was primarily liable for the debts incurred by him for labor and materials prior to the assignment of the contract to Council Lewy Company. He was liable under his bond and the Act of Congress cited above. The United States Fidelity Guaranty Company, as Elkas' surety, could not acquire any right by that assignment other than Elkas had against Council Lewy Company and its surety. But, it is said that a vast sum of money, considering the size of the contract, was paid over by Elkas under the assignment contract of January 14, 1933, to Council Lewy Company; and that therefore, by the assignment, Elkas, materialmen and laborers acquired the right to look to this fund so paid over as a trust fund by subrogation, and that the United States Fidelity Guaranty Company having paid the claims are now subrogated to the rights of the laborers and materialmen for labor and materials furnished to Elkas and Martin Carrithers Brothers. Council Lewy Company and their surety did not assume any obligation to the laborers and materialmen who had claims against Elkas and Martin Carrithers Brothers. Their claim was against Elkas and his surety primarily, or the laborers and materialmen who contracted with them. They did not have a claim against Council Lewy Company as none was created by its contract in the so-called bi-lateral assignment and bond. Such an idea was excluded by the terms of the contract and bond.

It is insisted that Section 2276, Code of 1930, is applied here and read into the bond of the Maryland Casualty Company. That statute, in substance, requires that, where an owner of a building lets a private contract for construction and takes a bond, the bond inure to the benefit of the laborers and materialmen. We have already held that the contract and bond in this case was not retroactive, but, on the contrary, shows on its face that the parties clearly made a contract to be performed in the future, and was not a contract or bond to assume any liabilities incurred in the past. There is nothing in Section 2276 that indicates an intention on the part of the Legislature, as expressed in that statute, to require a retroactive or retrospective bond. A retroactive or retrospective enactment must be clearly expressed as such. Statutes are usually construed by the courts to be prospective and operate only in the future. See Hester, Sheriff, v. Copiah County, 186 Miss. 716, 191 So. 496; Nunnery v. Baker, 188 Miss. 596, 195 So. 314; and Fidelity Deposit Company v. Merchants' Marine Bank of Pascagoula, 169 Miss. 755, 151 So. 373, 154 So. 260.

It is now settled in this State that Section 2276 does not cover labor and materials furnished to a subcontractor. See Alabama Marble Company v. United States Fidelity Guaranty Company et al., 146 Miss. 414, 111 So. 573. In so far as this statute is concerned, Council Lewy Company would be treated as a principal contractor, and there is no contention here that any item of labor or material was furnished to Council Lewy Company. Martin Carrithers Brothers, under that statute, would become subcontractors of Council Lewy Company after January 14, 1933.

The final decree of the chancellor coincides with the conclusions reached by this court. We do not know, and it is not disclosed by the record, by what process of reasoning the court below reached the result, but can only conclude that the decree of the court below is manifestly correct.

Affirmed.


ON SUGGESTION OF ERROR.


The suggestion of error here attacks not only the substantive findings of the original opinion, but seeks to point out what are, at most, irregularities of expression or gratuitous comments upon minor aspects of the litigation. Although conceding the possibility that such inadvertencies may be found, we adhere to the conclusions reached, as well as to the bases therefor.

Suggestion of error overruled.


Summaries of

United States Fidelity G. Co. v. Md. Cas. Co.

Supreme Court of Mississippi, In Banc
Feb 10, 1941
191 Miss. 103 (Miss. 1941)
Case details for

United States Fidelity G. Co. v. Md. Cas. Co.

Case Details

Full title:UNITED STATES FIDELITY GUARANTY CO. v. MARYLAND CASUALTY CO. et al

Court:Supreme Court of Mississippi, In Banc

Date published: Feb 10, 1941

Citations

191 Miss. 103 (Miss. 1941)
199 So. 278

Citing Cases

Stone v. McKay Plumbing Co.

No retrospective effect should be given to the statute. Hester v. Copiah County, 186 Miss. 716, 191 So. 496;…

Reed v. Maryland Casualty Company

This is the implication of Metropolitan Casualty Ins. Co. of N.Y. v. Koelling, Miss., 57 So.2d 562, in which…