From Casetext: Smarter Legal Research

Tri-Messine Construction Co. v. Telesector Resources Group, Inc.

Appellate Division of the Supreme Court of New York, Second Department
May 30, 2000
272 A.D.2d 609 (N.Y. App. Div. 2000)

Opinion

May 30, 2000

In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Nassau County (Winslow, J.), dated June 30, 1999, which granted the defendants' motion, in effect, to vacate a judgment of the same court, dated May 28, 1999, entered upon the defendants' default in answering the complaint, for an extension of time to serve an answer, and to compel the plaintiff to accept service thereof.

Before: O'Brien, J.P., Altman, Friedmann, McGinity and Smith, JJ.


Ordered that the order is affirmed, with costs.

The Supreme Court providently exercised its discretion in granting the defendants' motion, in effect, to vacate the judgment entered upon the defendants' default in answering the complaint, for an extension of time to serve an answer, and to compel the plaintiff to accept service thereof ( see, CPLR 2004, 2005, 3012[d]; De Benedictis v. Rahbar, 269 A.D.2d 134; Shure v. Village of Westhampton Beach, 121 A.D.2d 887).


Summaries of

Tri-Messine Construction Co. v. Telesector Resources Group, Inc.

Appellate Division of the Supreme Court of New York, Second Department
May 30, 2000
272 A.D.2d 609 (N.Y. App. Div. 2000)
Case details for

Tri-Messine Construction Co. v. Telesector Resources Group, Inc.

Case Details

Full title:TRI-MESSINE CONSTRUCTION CO., INC., APPELLANT, v. TELESECTOR RESOURCES…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: May 30, 2000

Citations

272 A.D.2d 609 (N.Y. App. Div. 2000)
708 N.Y.S.2d 630