The parties' stipulation to continue the briefing dates on the claim construction and claim construction hearing [Docket No. 24] is DENIED. Contrary to the parties' representation that the requested continuance will have no material effect on the schedule for this case, the proposed continuation would impact the motion cut-off date of January 15, 2008, the pre-trial conference set for February 26, 2008, and the trial date of March 24, 2008. See Docket No. 14.