Stengel v. Town of Poughkeepsie Planning Bd.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Dec 12, 2018
167 A.D.3d 752 (N.Y. App. Div. 2018)

Opinion

2017–08367 Index No. 103/16

12-12-2018

In the Matter of Roy A. STENGEL, et al., Appellants, v. TOWN OF POUGHKEEPSIE PLANNING BOARD, et al., Respondents.

McCabe & Mack, LLP, Poughkeepsie, N.Y. (Daniel C. Stafford of counsel), for appellants. Wallace & Wallace, LLP, Poughkeepsie, N.Y. (Lisa M. Cobb of counsel), for respondent Town of Poughkeepsie Planning Board. Stenger, Roberts, Davis & Diamond, LLP, Wappinger Falls, N.Y. (James P. Horan of counsel), for respondents Arlington Farms, Inc., and Malabar Realty, LLC.


McCabe & Mack, LLP, Poughkeepsie, N.Y. (Daniel C. Stafford of counsel), for appellants.

Wallace & Wallace, LLP, Poughkeepsie, N.Y. (Lisa M. Cobb of counsel), for respondent Town of Poughkeepsie Planning Board.

Stenger, Roberts, Davis & Diamond, LLP, Wappinger Falls, N.Y. (James P. Horan of counsel), for respondents Arlington Farms, Inc., and Malabar Realty, LLC.

ALAN D. SCHEINKMAN, P.J. MARK C. DILLON, JEFFREY A. COHEN, LINDA CHRISTOPHER, JJ.

DECISION & ORDER

In a proceeding pursuant to CPLR article 78, the petitioners appeal from a judgment of the Supreme Court, Dutchess County (James D. Pagones, J.), dated June 16, 2017. The judgment denied the petition and dismissed the proceeding to annul the determination of the respondent Town of Poughkeepsie Planning Board adopting a negative declaration under the State Environmental Quality Review Act (see ECL art 8) and granting conditional site plan approval to the respondent Malabar Realty, LLC, for construction of a motor vehicle service facility.

ORDERED that the judgment is affirmed, with one bill of costs to the respondents appearing separately and filing separate briefs.

The petitioners, the residential neighbors of a proposed motor vehicle service facility (hereinafter the facility), oppose its construction. The facility will consist of a 3,400 square-foot convenience store and gas station within close proximity to their homes. The respondent Malabar Realty, LLC (hereinafter Malabar Realty), is the owner of the lots where the facility will be constructed, and the respondent Arlington Farms, Inc., will run the business thereon. Upon merging two previously separate lots, Malabar Realty will construct the facility on a 0.81 acre triangular-shaped lot, which currently houses a dilapidated apartment building and a smaller motor vehicle service facility. After public meetings regarding the construction of the facility where opponents of the project were permitted to raise their objections, the respondent Town of Poughkeepsie Planning Board (hereinafter Planning Board) determined that the proposed project would not have a significant environmental impact and, thus, a Draft Environmental Impact Statement would not be needed. Subsequently, after review of Malabar Realty's application for site plan approval and the grant of several area variances and a special use permit by the Town of Poughkeepsie Zoning Board of Appeals, the Planning Board granted conditional site plan approval for the project. The petition seeks to nullify the Planning Board's determinations to adopt a negative declaration under the State Environmental Quality Review Act (see ECL art 8; hereinafter SEQRA) and to grant conditional site plan approval to Malabar Realty for construction of the facility.

To the extent that the petition alleges the Planning Board's noncompliance with SEQRA, the four-month statute of limitations applies (see CPLR 217[1] ; Matter of Young v. Board of Trustees of Vil. of Blasdell , 89 N.Y.2d 846, 848, 652 N.Y.S.2d 729, 675 N.E.2d 464 ). An action taken by an agency pursuant to SEQRA may be challenged only when such action is final (see CPLR 7801[1] ). An agency action is final when the decision-maker arrives at a " ‘definitive position on the issue that inflicts an actual, concrete injury’ " ( Stop–The–Barge v. Cahill , 1 N.Y.3d 218, 223, 771 N.Y.S.2d 40, 803 N.E.2d 361, quoting Matter of Essex County v. Zagata , 91 N.Y.2d 447, 453, 672 N.Y.S.2d 281, 695 N.E.2d 232 ). The position taken by an agency is not definitive and the injury is not actual or concrete if the injury purportedly inflicted by the agency could be prevented, significantly ameliorated, or rendered moot by further administrative action or by steps available to the complaining party (see Stop–The–Barge v. Cahill , 1 N.Y.3d at 223, 771 N.Y.S.2d 40, 803 N.E.2d 361 ; Matter of Essex County v. Zagata , 91 N.Y.2d at 453–454, 672 N.Y.S.2d 281, 695 N.E.2d 232 ; Matter of Patel v. Board of Trustees of Inc. Vil. of Muttontown , 115 A.D.3d 862, 864, 982 N.Y.S.2d 142 ). Here, the statute of limitations began to run with the issuance of the negative declaration for the project on February 19, 2015, as this constituted the Planning Board's final act under SEQRA and, accordingly, any challenge to the negative declaration had to be commenced within four months of that date (see generally Chase v. Board of Educ. of Roxbury Cent. School Dist. , 188 A.D.2d 192, 593 N.Y.S.2d 603 ; cf. Matter of Cathedral Church of St. John the Divine v. Dormitory Auth. of State of N.Y. , 224 A.D.2d 95, 645 N.Y.S.2d 637 ). The challenge to the negative declaration under SEQRA is, therefore, time-barred (see Matter of Wertheim v. Albertson Water Dist. , 207 A.D.2d 896, 616 N.Y.S.2d 778 ).

The petitioners' contention that the Planning Board's determination to grant conditional site plan approval violated the mandatory setback requirements of the Town of Poughkeepsie Code (hereinafter the Town Code) § 210–152(A)(2) is without merit. The Planning Board is vested with discretion in determining whether to issue a site plan approval pursuant to Town Code § 210–152(A). The record provides a rational basis for the Planning Board's determination (see generally Matter of In–Towne Shopping Ctrs., Co. v. Planning Bd. of the Town of Brookhaven , 73 A.D.3d 925, 901 N.Y.S.2d 331 ).

SCHEINKMAN, P.J., DILLON, COHEN and CHRISTOPHER, JJ., concur.


Summaries of

Stengel v. Town of Poughkeepsie Planning Bd.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Dec 12, 2018
167 A.D.3d 752 (N.Y. App. Div. 2018)
Case details for

Stengel v. Town of Poughkeepsie Planning Bd.

Case Details

Full title:In the Matter of Roy A. Stengel, et al., appellants, v. Town of…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department

Date published: Dec 12, 2018

Citations

167 A.D.3d 752 (N.Y. App. Div. 2018)
167 A.D.3d 752
2018 N.Y. Slip Op. 8488

Citing Cases

Velardi-Ward v. N.Y. State Dep't of Envtl. Conservation

To the extent that the amended petition alleges noncompliance with SEQRA, the four-month statute of…