From Casetext: Smarter Legal Research

State Rds. Comm'n v. Northampton

Court of Appeals of Maryland
Mar 30, 1970
263 A.2d 867 (Md. 1970)

Opinion

[No. 277, September Term, 1969.]

Decided March 30, 1970.

CONDEMNATION — STATE ROADS COMMISSION — Maryland Rule U27 g 1 Requires Party Dissatisfied With Award Of Board Of Property Review File Notice Within 30 Days After Filing Of Award With Clerk Of Court — Where Notice Of Dissatisfaction Filed More Than 30 Days After Filing Of Award It Was Proper For Trial Court To Dismiss Commission's Condemnation Petition. pp. 353-354

Appeal from the Circuit Court for Prince George's County (DIGGES, C.J.).

Condemnation proceedings by State Roads Commission of Maryland against Northampton Corporation and others. The Commission appeals from the order granting the property owners' motion to dismiss the Commission's notice of dissatisfaction.

Order affirmed. Costs to be paid by the appellant.

The cause was submitted on briefs to HAMMOND, C.J., and McWILLIAMS, FINAN, SINGLEY and SMITH, JJ.

Submitted by Francis B. Burch, Attorney General, Joseph D. Buscher, Special Assistant Attorney General, Joseph J. Bonner, Special Attorney, and Carl Harrison Lehmann for appellant.

Submitted by Welsh Lancaster for Northampton Corporation, part of appellees; no brief filed on behalf of other appellees.


In State Roads Commission v. Laurel Pines Country Club, Inc., 256 Md. 605 (1970), the Board of Property Review filed its award to the property owner on 5 April. The award was dated 20 March. The appellant (Commission), on 9 May, filed the notice of dissatisfaction provided by Maryland Rule U27 g 1. Since the rule requires such a notice to be filed "within thirty days after the filing of the award with the clerk of the court" we held that the property owner's motion to dismiss the Commission's notice of dissatisfaction was properly granted. In the case at bar (actually two cases, consolidated and treated as one case) the award, dated 5 April, was filed on 5 May. The Commission admits the receipt of a copy thereof on 8 May. Its notice of dissatisfaction was not filed until 10 June, clearly more than 30 days after the filing of the award. The trial judge, Digges, C.J. (now Digges, J., of this Court), upon motion of the appellee, dismissed the Commission's Condemnation Petition. We shall affirm the action of Judge Digges.

Order affirmed.

Costs to be paid by the appellant.


Summaries of

State Rds. Comm'n v. Northampton

Court of Appeals of Maryland
Mar 30, 1970
263 A.2d 867 (Md. 1970)
Case details for

State Rds. Comm'n v. Northampton

Case Details

Full title:STATE ROADS COMMISSION OF MARYLAND v . NORTHAMPTON CORPORATION, ET AL

Court:Court of Appeals of Maryland

Date published: Mar 30, 1970

Citations

263 A.2d 867 (Md. 1970)
263 A.2d 867