From Casetext: Smarter Legal Research

Sanguinetti v. United States

U.S.
Feb 18, 1924
264 U.S. 146 (1924)

Summary

holding that "the injury was in its nature indirect and consequential, for which no implied obligation on the part of the Government can arise" where flooding is neither permanent, nor is intermittent but inevitably recurring

Summary of this case from Cary v. U.S.

Opinion

APPEAL FROM THE COURT OF CLAIMS.

No. 130.

Argued January 3, 1924. Decided February 18, 1924.

A canal, constructed by the Government to improve navigation, overflowed intermittently, flooding the claimant's land but not ousting him from his customary user, except for brief periods, or inflicting permanent injury; and it did not appear either that the flooding was intended or anticipated by the Government or its officers, or that it was attributable directly, in whole or in part, to the improvement, rather than to natural conditions. Held, that no taking could be implied, and the United States was not liable ex contractu. P. 148. 55 Ct. Clms. 107, affirmed.

APPEAL from a judgment of the Court of Claims dismissing a petition.

Mr. Benjamin Carter, with whom Mr. F. Carter Pope was on the brief, for appellant.

Mr. Solicitor General Beck appeared for the United States.


The main portion of the City of Stockton, California, and the adjacent territory lie between the Calaveras river and the Mormon slough, both flowing in a general southwesterly direction. The streams are several miles apart and the intervening area, including appellant's land, has always been subject to inundation by overflow therefrom, as well as by reason of periodic heavy rainfall. During periods of high water sediment was deposited in large quantities in the navigable channel, interfering with navigation and entailing annual expenditures for dredging. In view of this condition, Congress, in 1902, authorized the construction above the city of a connecting canal, by means of which the waters of Mormon slough were diverted into the Calaveras river. Act of June 13, 1902, c. 1079, 32 Stat. 368. The canal was constructed in accordance with plans prepared by government engineers, after investigation, upon a right of way procured by the State of California and conveyed to the United States. A diversion dam was placed in the slough, immediately below the intake of the canal. The excavated material was put on the lower side of the canal, making a levee, of which the dam was practically a continuation; but that this was not done with a view of casting flood waters upon the upper lands is apparent, since the engineers believed the capacity of the canal would prove sufficient under all circumstances. It was evidently the most convenient method of disposing of the material and also it may have contributed to strengthen the lower bank against erosion. The canal was completed in 1910. In January, 1911, there was a flood of unprecedented severity, and there were recurrent floods of less magnitude in subsequent years, except in 1912 and 1913. The capacity of the canal proved insufficient to carry away the flood waters, which overflowed the lands of appellant, lying above the canal, damaging and destroying crops and trees and injuring to some extent the land itself. Appellant brought suit against the Government to recover damages upon the alleged theory of a taking of the property thus overflowed. The land would have been flooded if the canal had not been constructed but to what extent does not appear. None of the land of appellant was permanently flooded, nor was it overflowed for such a length of time in any year as to prevent its use for agricultural purposes. It was not shown, either directly or inferentially, that the Government or any of its officers, in the preparation of the plans or in the construction of the canal, had any intention to thereby flood any of the land here involved or had any reason to expect that such result would follow. That the carrying capacity of the canal was insufficient during periods of very heavy rains and extremely high water was due to lack of accurate information in respect of the conditions to be met at such times. The engineers who made the examination and recommended the plans, determined, upon the information which they had, that the canal would have a capacity considerably in excess of the requirements in this respect.

The Court of Claims concluded that none of the land here involved had been taken, within the meaning of the Fifth Amendment to the Constitution, and that, therefore, no recovery could be had upon the theory of an implied contract; but that the liability sought to be enforced was one sounding in tort, of which the court had no jurisdiction. Accordingly, the petition was dismissed.

Beginning with Pumpelly v. Green Bay Co., 13 Wall. 166, this Court has had frequent occasion to consider the question now presented. In that case, by authority of the State of Wisconsin, a dam was constructed across the Fox river, which had the effect of raising the ordinary water level and overflowing plaintiff's land continuously from the time of the completion of the dam in 1861 to the beginning of the action in 1867, resulting in an almost complete destruction of the value of the property. It was held that this constituted a taking in the constitutional sense, and the rule was laid down (p. 181) "that where real estate is actually invaded by superinduced additions of water, earth, sand, or other material, or by having any artificial structure placed on it, so as to effectually destroy or impair its usefulness, it is a taking."

In United States v. Lynah, 188 U.S. 445, a dam had been constructed by the United States in such manner as to hinder the natural flow of a stream and, as a necessary result, to raise the level of its waters and overflow the land of plaintiff to such an extent as to cause a total destruction of its value. It was impossible to remove this overflow of water and the property, in consequence, had become an irreclaimable bog, unfit for any agricultural use. It was held that the property had been taken and that the Government was liable for just compensation, upon payment of which the title and right of possession would pass.

In United States v. Cress, 243 U.S. 316, the Government by means of a lock and dam, had raised the water of the Cumberland river above its natural level, so that lands not normally invaded were subjected permanently to frequent overflows, impairing them to the extent of one-half their value. A like improvement had raised the waters of the Kentucky river in the same manner so as to end the usefulness of a mill by destroying the head of water necessary to run it. The findings made it plain that it was not a case of temporary overflow or of consequential injury but a condition of "permanent liability to intermittent but inevitably recurring overflows" and it was held that such overflowing was a direct invasion, amounting to a taking.

Under these decisions and those hereafter cited, in order to create an enforceable liability against the Government it is, at least, necessary that the overflow be the direct result of the structure, and constitute an actual, permanent invasion of the land, amounting to an appropriation of and not merely an injury to the property. These conditions are not met in the present case. Prior to the construction of the canal the land had been subject to the same periodical overflow. If the amount or severity thereof was increased by reason of the canal, the extent of the increase is purely conjectural. Appellant was not ousted nor was his customary use of the land prevented, unless for short periods of time. If there was any permanent impairment of value, the extent of it does not appear. It was not shown that the overflow was the direct or necessary result of the structure; nor that it was within the contemplation of or reasonably to be anticipated by the Government. If the case were one against a private individual, his liability, if any, would be in tort. There is no remedy in such case against the United States. Keokuk Bridge Co. v. United States, 260 U.S. 125.

The most that can be said is that there was probably some increased flooding due to the canal and that a greater injury may have resulted than otherwise would have been the case. But this and all other matters aside, the injury was in its nature indirect and consequential, for which no implied obligation on the part of the Government can arise. See Gibson v. United States, 166 U.S. 269; Bedford v. United States, 192 U.S. 217; Transportation Co. v. Chicago, 99 U.S. 635; Jackson v. United States, 230 U.S. 1; Horstmann Co. v. United States, 257 U.S. 138; Coleman v. United States, 181 F. 599.

The judgment of the Court of Claims is

Affirmed.


Summaries of

Sanguinetti v. United States

U.S.
Feb 18, 1924
264 U.S. 146 (1924)

holding that "the injury was in its nature indirect and consequential, for which no implied obligation on the part of the Government can arise" where flooding is neither permanent, nor is intermittent but inevitably recurring

Summary of this case from Cary v. U.S.

holding that no taking occurred where the claimant failed to show that increased flooding resulting from the governments construction of a canal was the direct or necessary result of the structure; [or] within the contemplation of or reasonably to be anticipated by the government

Summary of this case from Ridge Line, Inc. v. U.S.

holding no taking under Just Compensation Clause where landowner failed to provide any evidence that flooding was "direct or necessary result" of government action, and any amount of increased flooding caused by action was purely conjectural, where area had suffered from major natural flooding event and subsequent intermittent less severe flooding in later years

Summary of this case from Running v. City of Athens

finding no taking occurred despite periodic flooding of claimant's property because the land was subject to the same periodic overflows prior to the government's construction of a nearby canal and levee system and claimant produced no evidence that the amount or severity of flooding was increased by construction of the canal

Summary of this case from Columbia Venture, LLC v. Richland Cnty.

finding no taking occurred where there was no causal connection between the construction of a nearby government canal and the increased amount or severity of periodic flooding

Summary of this case from Columbia Venture, LLC v. Richland Cnty.

finding no taking occurred despite periodic flooding of claimant's property because the land was subject to the same periodic overflows prior to the government's construction of a nearby canal and levee system and claimant produced no evidence that the amount or severity of flooding was increased by construction of the canal

Summary of this case from Columbia Venture, LLC v. Richland County

finding no taking occurred where there was no causal connection between the construction of a nearby government canal and the increased amount or severity of periodic flooding

Summary of this case from Columbia Venture, LLC v. Richland County

concluding that government's construction of canal that caused flooding of neighboring property during periods of high rains was a tort, not a taking, where flooding occurred because engineers designing the canal relied on inaccurate information when determining the carrying capacity of the canal

Summary of this case from Yawn v. Dorchester Cnty.

concluding there was no remedy against the United States where carrying capacity of government-constructed canal was insufficient to avoid overflow during heavy rains

Summary of this case from Nicholson v. U.S.

characterizing the causal relationship asserted by the landowner as "purely conjectural"

Summary of this case from Ark. Game & Fish Comm'n v. United States

In Sanguinetti, plaintiffs brought a takings claim alleging that a canal built by the government caused flooding damage.

Summary of this case from St. Bernard Par. Gov't v. United States

involving a canal insufficient to carry away flood waters

Summary of this case from Arkansas Game Fish Com'n v. U.S.

In Sanguinetti v. United States, 264 U.S. 146, 44 S.Ct. 264, 68 L.Ed. 608 (1924), the Court held that the government was not liable for flooding caused by a canal because the land would have flooded in its natural state.

Summary of this case from Ballam v. United States

In Sanguinetti v. United States, supra [ 264 U.S. 146, 44 S.Ct. 265, 68 L.Ed. 608], the Supreme Court said that "in order to create an enforceable liability against the government, it is at least necessary that the overflow be the direct result of the structure, and constitute an actual, permanent invasion of the land, amounting to an appropriation of and not merely an injury to the property."

Summary of this case from Goodman v. United States

In Sanguinetti v. United States, 264 U.S. 146, 44 S.Ct. 264, 68 L.Ed. 608, liability of the United States ex contractu was denied where "it did not appear either that the flooding was intended or anticipated by the Government or its officers, or that it was attributable directly, in whole or in part, to the improvement, rather than to natural conditions".

Summary of this case from Sponenbarger v. United States

In Sanguinetti v. U.S., 264 U.S. 146, 44 S.Ct. 264, 68 L.Ed. 608, congress authorized the construction of a canal by means of which the waters of Mormon Slough were diverted into the Calaveras River. The canal was constructed in accordance with plans prepared by the government engineers.

Summary of this case from North v. United States

In Sanguinetti, the Court foreshadowed the emerging role of causation and implied contract (i.e., intent) takings analysis by applying both in the same discussion.

Summary of this case from Hansen v. U.S.

In Sanguinetti v. United States, 264 U.S. 146, 44 S.Ct. 264, 68 L.Ed. 608, the question was whether or not the erection of a canal which allegedly caused an overflow of plaintiff's property constituted a taking.

Summary of this case from Columbia Basin Orchard v. United States, (1955)

In Sanguinetti v. United States, 264 U.S. 146, 44 S.Ct. 264, 265, 68 L.Ed. 608, the Government had constructed a canal and when its capacity proved insufficient to carry away flood waters, plaintiff's' land along the canal was overflowed.

Summary of this case from Yazel v. United States, (1950)

distinguishing claim based on permanent consequential physical invasion of private property tantamount to a government appropriation from mere "consequential injury"

Summary of this case from Wittman v. City of Billings

In Sanguinetti v. United States, 264 U.S. 146, 44 S.Ct. 264, 68 L.Ed. 608 (1924), a canal constructed and operated by the government was insufficient to carry away flood waters.

Summary of this case from Farmers New World Life v. Bountiful City

In Sanguinetti v. United States, 264 U.S. 146, 149, 44 S. Ct. 264, 265, 68 L. Ed. 608, 610, liability was denied where it did not appear that the flooding was attributable directly, in whole or in part, to the improvement, rather than to natural conditions.

Summary of this case from Lage v. Pottawattamie County

In Sanquinetti, the Court stated that to effectuate a de facto taking the overflow must constitute an actual, permanent invasion of the land amounting to an appropriation thereof, and not merely an injury to the property.

Summary of this case from Oxford v. Commonwealth, Department of Transportation

taking must "constitute an actual, permanent invasion of the land, amounting to an appropriation of and not merely an injury to the property"

Summary of this case from Rohaly v. State
Case details for

Sanguinetti v. United States

Case Details

Full title:SANGUINETTI v . UNITED STATES

Court:U.S.

Date published: Feb 18, 1924

Citations

264 U.S. 146 (1924)
44 S. Ct. 264
68 L. Ed. 608

Citing Cases

Baker v. City of McKinney

Id. at 127, 43 S.Ct. 37. The Court also finds Sanguinetti v. United States , 264 U.S. 146, 44 S.Ct. 264, 68…

Ark. Game & Fish Comm'n v. United States

Id., at 1378. The Court of Appeals understood this conclusion to be dictated by this Court's decisions in…