Opinion
Submitted May 7, 1940 —
Decided July 29, 1940.
1. Suit by building contractor's assignee against owner to recover balance of contract price, held properly sent to a referee under R.S. 2:27-178.
2. Parol testimony as to time of payments under building contract held immaterial variance where suit was for alleged unpaid balance on completion.
3. Misjoinder of a defendant held not fatal to cause of action, and amendable at any time by virtue of R.S. 2:27-36.
On appeal from the Essex Circuit Court.
Before BROGAN, CHIEF JUSTICE, and Justices PARKER and PERSKIE.
For the appellant, Harry Kay.
For the respondent,
The plaintiff sued as assignee of the claim of one Zweigard under a contract for furnishing and installing the plumbing, heating and tinning equipment for a certain house that was under construction. The complaint alleged that the contract was made by both defendants, Epstein and the "Century Construction Co." — so reads the name of the corporation in the record. The answer of Epstein set up a number of defenses, and added a counter-claim for alleged defective work, c., alleging a written contract between Epstein and Zweigard dated October 2d 1936, annexing a copy. An amended answer by Epstein set up another similar but not identical contract of the same date. No answer was filed by the Century Corporation at any time, but no default judgment was taken against it. Both counter-claims set up breach by Zweigard, and claimed damages against him, and he answered traversing their allegations and setting up acceptance by Epstein. In this situation of the record, with the corporate defendant in default but with no default judgment against it, the Circuit Court ordered a reference pursuant to section 155 of the Practice act of 1903. N.J.S.A. 2:27-178. The referee reported that neither instrument set up in the counter-claims was the real contract, but that the actual contract consisted of a written estimate dated September 28th, 1936, signed by Zweigard, and orally accepted, not by Epstein, but by the Century corporation; and found an unpaid balance against which he charged certain items of defective or omitted work and materials, and struck a balance of $1,416.96 including interest, against the Century corporation, the present appellant, giving to it full privilege of defending at the reference, notwithstanding the default. He found Epstein not liable. The Century Construction Co. excepted to the report, the exceptions were overruled, and judgment entered upon the report. Century Construction Co. appeals, and three points are argued.
The first is that the case is not one in which "matters of account are in controversy," in the language of the statute. We hold to the contrary. In suits to recover a contract price, or balance thereof, under a building contract, reference of such cases is in our experience a fairly common practice, and peculiarly suitable for patient examination by a referee. Indeed, our court of last resort expressly so held in New York Metal Ceiling Co. v. Kiernan, 73 N.J.L. 763, a case on all fours with the present one but with the added element of a mechanics lien.
The second point is that the referee allowed parol testimony to vary the terms of the accepted estimate, which he held to be the contract. The variance was this: the estimate was for doing the work, c., "for the sum of $2,550." The testimony received was that the money was to be paid in installments, $900 when rough work was finished, $1,000 when fixtures delivered; $650 balance on completion. Conceding for the sake of argument that this amounted to a variance, we are unable to see what possible harm could have resulted. The total was the same, the contractor claimed completion and his rights were adjudged on that basis. The question was not whether some installment had not become due, but whether there should be a deduction from the total for defects.
The third and last point is that the complaint charges Epstein and Century jointly, that Epstein went without day; and that Century only was held; and that this judgment is not supported by the record. Before the Practice act of 1912 this point might have had some importance; but section 9 of that act ( Pamph. L. 1912 (at p. 379)) provides that "No action shall be defeated by the non-joinder or misjoinder of parties. New parties may be added and parties misjoined may be dropped, by order of the court, at any stage of the cause, as the ends of justice may require." See N.J.S.A. 2:27-31. The record may be appropriately amended by the elimination of Epstein as an alleged party to the contract; and assuming such amendment as made, the judgment under review will be affirmed.
This result makes it unnecessary to deal with a motion to dismiss the present appeal.