This action is brought against the defendant corporation upon the ground that the defendant failed to pay ten per cent. of the wages of one of its employees, after an execution against the salary of such employee had been served upon it. The action is brought under section 1391 of the Code of Civil Procedure. The plaintiff alleged and proved that one Grow was an employee of the defendant, and that, "pursuant to an order duly made and entered by a Justice of the Supreme Court, New York County, on the 12th day of March, 1910, an execution * * * was duly issued out of the Supreme Court, New York County, in favor of the plaintiffs * * * and * * * on the 21st day of March, 1910, said Sheriff duly presented said execution to the Harlem Construction Company, the defendant herein." The plaintiff also proved that the defendant failed to pay the prescribed percentage of the wages of its employee to the officer presenting said execution to it.

No proof was offered to show that a judgment had been recovered against the defendant's employee, or that an execution upon said judgment had been returned wholly or partly unsatisfied. The appellant contends that, in the absence of such proof, the plaintiff failed to establish a cause of action under the statute referred to above.

It was necessary, before such an execution as is contemplated by the statute could be "presented" to the defendant, that judgment against the employee should have been recovered and that execution thereon should have issued and been returned wholly or partly unsatisfied. That these steps are essential prerequisites to the making of an order providing that execution shall issue against the wages or salary, etc., of the judgment debtor is evident from the provision of section 1391 of the Code of Civil Procedure. The answer of the defendant admits the fact that, pursuant to an order duly made and entered, the execution against the wages of said Grow was "duly" issued out of the Supreme Court, and that the sheriff "duly" presented said execution to the defendant. The word "duly" has frequently been defined as meaning according to law: "That is, according to the statute governing the subject, and implies the existence of every fact essential to perfect regularity of procedure." Brownell v. Town of Greenwich, 114 N.Y. 518, 527. Interpreting the word "duly" in the sense in which it has been judicially defined, we think that the complaint stated a cause of action against the defendant and that the admissions by the defendant that the execution was "duly" issued and "duly" presented left it without any defense to this action, and that the learned court below properly granted judgment in favor of the plaintiffs.

Judgment affirmed with costs.

PAGE and BIJUR, JJ., concur.

Judgment affirmed, with costs.


Summaries of

Reynolds v. Harlem Construction Co.

Supreme Court, Appellate Term
Apr 1, 1911
71 Misc. 446 (N.Y. App. Term 1911)
Case details for

Reynolds v. Harlem Construction Co.

Case Details

Full title:FLORENCE B. REYNOLDS and ALICE M. DIKE, Respondents, v . HARLEM…

Court:Supreme Court, Appellate Term

Date published: Apr 1, 1911

Citations

71 Misc. 446 (N.Y. App. Term 1911)
128 N.Y.S. 642

Citing Cases

Curry v. Johnston

25 R.C.L. 778, § 24. The term "duly filed" as used in Acts 1935, p. 424, § 345.40, presupposes the existence…