Rabey Elec. c. v. Housing Auth. of Savannah

Court of Appeals of Georgia
Jan 30, 1989
190 Ga. App. 89 (Ga. Ct. App. 1989)

Summary

holding 120–day statute of limitations period was reasonable

Summary of this case from Cobra Tactical, Inc. v. Payment Alliance Int'l Inc.

Opinion

77698.

DECIDED JANUARY 30, 1989.

Action on contract. Chatham Superior Court. Before Judge Head.

John G. Hunter, for appellant.

Malberry Smith, Jr., for appellee.


Rabey Electric Company, Inc., brought suit against the Housing Authority of Savannah to recover the difference between the price set for work performed by Rabey pursuant to a contract between the parties for the electrical modernization of certain public housing projects and the payment actually made to Rabey by the Housing Authority, which penalized Rabey for failing to complete the work on time and for using materials which did not conform to contract specifications. Ruling on the Housing Authority's motion for directed verdict was reserved by the trial court, and after the jury returned a verdict in favor of Rabey, the trial court granted the Housing Authority's motion, setting aside the jury's verdict. Rabey appeals.

The record reveals that the contract contained a provision which required, inter alia, that appellee's contracting officer be notified in writing of all disputes within ten days of their commencement, and that if the contractor has properly given that notice and properly excepted any decision of the contracting officer with which it disagrees from the final release, it must bring suit "within 120 days after receipt of final payment under this contract or within six months of a written request by the [Housing Authority] that he submit a final voucher and release, whichever time is the lesser." The contract also provided that "the [c]ontractor hereby agrees that his noncompliance with the conditions precedent constitutes a waiver of his right to assert [his] claim."

Appellant does not claim to have complied with the conditions precedent, but in several enumerations of error contends that the trial court erred by granting appellee's motion for a directed verdict either because appellee waived its right to insist on the conditions precedent, or because the contract limitations are void.

1. The record does not support appellant's contention that appellee waived its right to insist on the conditions precedent by not including this defense in the consolidated pretrial order. In fact, the pretrial order states clearly that one issue for determination by the jury is "[w]hether [appellant] waived its right to bring this action by failing to comply with the conditions precedent specified in the contract." Accordingly, there is no merit in this enumeration.

2. Appellant contends the contractual conditions are unreasonable and therefore void. We do not agree. While the statute of limitation for actions on simple contracts in writing is six years, OCGA § 9-3-24, "[t]he Georgia courts have permitted parties to contract as to a lesser time limit within which an action may be brought so long as `"the period fixed be not so unreasonable as to raise a presumption of imposition or undue advantage in some way." [Cit.]' [Cit.] If not reasonable . . . , then it is not permitted regardless of the parties' freedom to contract. [Cit.]" General Elec. c. Corp. v. Home Indem. Co., 168 Ga. App. 344, 348 ( 309 S.E.2d 152) (1983). Appellant concedes in its brief that Georgia courts have many times upheld much shorter contractual limitation periods. See, e.g., Turner v. Nat. Union Fire Ins. Co., 167 Ga. App. 762 ( 307 S.E.2d 290) (1983); Beck v. Ga. Farm c. Ins. Co., 146 Ga. App. 878 ( 247 S.E.2d 548) (1978); Livaditis v. American Cas. Co., 117 Ga. App. 297 (2) ( 160 S.E.2d 449) (1968).

Appellant argues that the intermediate time limitations in the contract, such as the requirement of notice to the contracting officer, result in an effective ten-day statute of limitation, which is patently unreasonable. However, appellant expressly directed that no transcript of the trial proceedings be included in the record, and the order of the trial court granting appellee's motion for a directed verdict recites that it is based on appellant's failure to file this action within the time prescribed by the contract. Consequently, "[w]e find no evidence in the record that the trial court was asked to consider [the issue of the reasonableness of those prior limitations], and so there is nothing for us to consider. `Grounds which may be considered on appeal are limited to those which were urged before the trial court. [Cits.]' [Cit.]" Chafin v. Wesley Homes, 186 Ga. App. 403, 405 ( 367 S.E.2d 236) (1988). the only relevant question of reasonableness presented is that of the contract language which provides that the action itself must be brought either 120 days after final payment, or 6 months after a request to submit a final voucher and release. Bearing in mind the fact that appellant complied with neither alternative limitation on the time for filing suit, and that a contractual limitation period of 6 months was upheld by the Georgia Supreme Court in Brown v. Savannah Mut. Ins. Co., 24 Ga. 97, 101 (2) (1858), we do not find the contractual limitation is "so unreasonable as to raise a presumption of imposition or undue advantage." General Elec. c. Corp., supra at 348. Accordingly, the trial court did not err by granting appellee's motion for a directed verdict on that basis. See generally Dependable Equip. c. Co. v. Nursecare of Atlanta, 184 Ga. App. 136, 137 (1) ( 361 S.E.2d 23) (1987).

3. Although appellant also asserts the contractual limitation is void because it is against public policy, the Supreme Court declared in Brown, supra, that "[n]o principle of public policy is violated by a condition in a policy of insurance, that the injured party shall sue within six months from the time of the loss or lose his remedy," id., and we see no reason why such a limitation should be void as against public policy in this case.

Judgment affirmed. Carley, C. J., and Deen, P. J., concur.

DECIDED JANUARY 30, 1989.


Summaries of

Rabey Elec. c. v. Housing Auth. of Savannah

Court of Appeals of Georgia
Jan 30, 1989
190 Ga. App. 89 (Ga. Ct. App. 1989)

holding 120–day statute of limitations period was reasonable

Summary of this case from Cobra Tactical, Inc. v. Payment Alliance Int'l Inc.

Enforcing a contractual alteration to the statute of limitation for action on contracts and noting "Georgia courts have permitted parties to contract as to a lesser time limit within which an action may be brought so long as the period fixed be not so unreasonable as to raise a presumption of imposition or undue advantage in some way." (citations and punctuation omitted)

Summary of this case from Langley v. MP Spring Lake, LLC.
Case details for

Rabey Elec. c. v. Housing Auth. of Savannah

Case Details

Full title:RABEY ELECTRIC COMPANY, INC. v. HOUSING AUTHORITY OF SAVANNAH

Court:Court of Appeals of Georgia

Date published: Jan 30, 1989

Citations

190 Ga. App. 89 (Ga. Ct. App. 1989)
378 S.E.2d 169

Citing Cases

Wolf Creek Landfill, LLC v. Twiggs County

See Gen. Elec. Credit Corp. v. Home Indem. Co. , 168 Ga.App. 344, 346, 309 S.E.2d 152 (1983) (“Georgia has no…

Langley v. MP Spring Lake, LLC.

See, e.g., Brown v. Savannah Mut. Ins. Co. , 24 Ga. 97, 101 (1858) ("There is no reason why a party may not…