People v. Wayne Elec. Motor Co.

Supreme Court of Michigan
Dec 10, 1934
257 N.W. 877 (Mich. 1934)

Opinion

Docket No. 78, Calendar No. 38,039.

Submitted October 4, 1934.

Decided December 10, 1934.

Appeal from Wayne; Webster (Clyde I.), J. Submitted October 4, 1934. (Docket No. 78, Calendar No. 38,039.) Decided December 10, 1934.

Assumpsit by People of the State of Michigan, for the use of Belson Manufacturing Company, an Illinois corporation, against Wayne Electric Motor Company, a Michigan corporation, and Fidelity Deposit Company of Maryland, a Maryland corporation, for sums allegedly due for material and equipment furnished in construction of school. Judgment for defendants. Plaintiff appeals. Affirmed.

Welsh, Bebout, Hill Lee, for plaintiff.

Mark L. Rowley, for defendants.


On October 2, 1930, the board of education of the city of Detroit entered into a contract with the defendant Wayne Electric Motor Company, wherein the motor company agreed to furnish and install certain electric light and radio equipment for the Chadsey High School building and power plant in accordance with the plans and specifications therefor, for the sum of $51,460. On the same day, the motor company executed a bond to the people of the State of Michigan in the sum of $51,460 for the faithful performance of said contract by it, with the defendant Fidelity Deposit Company of Maryland as surety.

The Belson Manufacturing Company, of Chicago, had a local sales agent in Detroit, Thomas W. Butler. He examined the specifications for the lighting equipment and secured an order from the motor company to the Belson company for a part thereof, which it declined to accept "because of a matter of credit situation, their credit wasn't approved." The H. M. Hopkins Electric Company at that time was a "jobber" in Detroit, handling electric equipment. It appears that an arrangement was made between this company and the Belson company whereby the Hopkins company ordered certain electric equipment from the Belson company, and it was shipped to it and turned over to the motor company and installed by it in the building. The total purchase price thereof was $1,521.13, of which amount the Hopkins company was entitled to a 10 per cent. commission. Plaintiff here seeks to recover on the bond of the motor company the balance thereof, $1,369.02, and interest, under the provision in Act No. 187, Pub. Acts 1905, as amended by Act No. 167, Pub. Acts 1927, the same being 3 Comp. Laws 1929, § 13132 et seq. On trial before the court without a jury, the defendants had judgment, from which the plaintiff has taken this appeal.

Section 13132 reads as follows:

"When public buildings or other public works are about to be built, repaired or ornamented under contract at the expense of the State, or of any county, city, village, township or school district thereof, it shall be the duty of the board of officers or agents, contracting on behalf of the State, county, city, village, township or school district, to require sufficient security by bond for the payment by the contractor of all subcontractors and for the payment for all labor performed and materials and certain supplies furnished and used in the erection, repairing or ornamenting of such public buildings or works."

Section 13134 provides for the form of the bond to be given by the contractor, and section 13135 for recovery under it.

Plaintiff contends that (1) he is entitled to recover as a subcontractor, but, if not, (2) then for materials furnished and used in the construction of the building.

1. There was no allegation in the declaration to support the claim here made that the material and equipment were furnished by plaintiff as a subcontractor. The trial court so found, and in his opinion stated that "if the plaintiff could recover under this theory, I think it would not be too late perhaps to amend but I am satisfied that plaintiff cannot recover on that theory either." He, however, then discussed its claim as a subcontractor, and reached the conclusion stated. No amendment was asked for, or permitted to be made, and plaintiff's rights in this respect need not be further considered.

2. The material for which the plaintiff seeks to recover consisted of electric lights. One of the orders for them sent by the Hopkins company to the plaintiff stated that they were "to be furnished as per architect's specifications for Chadsey High School." It instructed plaintiff to "ship to us" and "charge to us." The other order contained the same direction as to shipping and charging. The shipments were so made and the lights delivered by the Hopkins company to the motor company. The record is barren of any information as to the dealings between the Hopkins company and the motor company under which these deliveries were made. It does appear that the lights were installed by the motor company. The only inference which may fairly be drawn is that the motor company purchased them from the Hopkins company and paid it therefor.

Surely, a contractor who purchases certain equipment from a jobber is not required to protect himself against liability by investigation as to whether the jobber has paid for it to the person from whom he purchased it.

Our mechanics' lien law (3 Comp. Laws 1929, § 13101 et seq.) provides in the first section thereof for a lien upon the building for materials furnished in the erection thereof.

"The word 'material-man' as used in this act, shall be construed to include all persons by whom any materials are furnished in or for building, altering, improving, repairing, erecting or ornamenting, or putting in any house, building, machinery, wharf or other structure or walk or walks." 3 Comp. Laws 1929, § 13129.

In Hart v. Reid, 243 Mich. 175, it was held that this act "does not extend beyond its express terms, and cover a material-man who furnishes materials in pursuance of a contract with another material-man who furnishes materials in pursuance of a contract with a subcontractor under the original contractor."

The judgment is affirmed.

POTTER, NORTH, FEAD, WIEST, BUTZEL, BUSHNELL, and EDWARD M. SHARPE, JJ., concurred.


Summaries of

People v. Wayne Elec. Motor Co.

Supreme Court of Michigan
Dec 10, 1934
257 N.W. 877 (Mich. 1934)
Case details for

People v. Wayne Elec. Motor Co.

Case Details

Full title:PEOPLE, for use of BELSON MANFG. CO., v. WAYNE ELECTRIC MOTOR CO

Court:Supreme Court of Michigan

Date published: Dec 10, 1934

Citations

257 N.W. 877 (Mich. 1934)
257 N.W. 877

Citing Cases

Kinney Electrical Mfg. Co. v. Modern Electric Co.

Midway was to perform no part of the contract which Modern had entered into with the Board of Education.…

Hub Electric Company v. Aetna Casualty Surety Co.

Defendant's claim is that plaintiff falls within the class of materialmen who are excluded from the Statute's…