From Casetext: Smarter Legal Research

Peck Ormsby Constr. Co. v. Rigby

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO
Aug 31, 2011
NO. CIV. 1:10-545 WBS (D. Idaho Aug. 31, 2011)

Opinion

NO. CIV. 1:10-545 WBS

08-31-2011

PECK ORMSBY CONSTRUCTION COMPANY, a Utah corporation, Plaintiff, v. CITY OF RIGBY, an Idaho municipal corporation; PARKSON CORPORATION, a Delaware corporation; and WESTERN SURETY COMPANY, a South Dakota corporation, Defendants.


MEMORANDUM AND ORDER RE:

MOTIONS TO DISMISS AND TO

COMPEL ARBITRATION


AND RELATED COUNTERCLAIMS AND CROSS-CLAIMS.

Plaintiff Peck Ormsby Construction Company ("Peck Ormsby") brought this action against defendants City of Rigby ("Rigby"), Parkson Corporation ("Parkson"), and Western Surety Company ("Western") arising from a construction project in Rigby for which Peck Ormsby is the general contractor and Parkson is a subcontractor. After the court granted Parkson's and Western's motions to dismiss with leave to amend, Peck Ormsby filed an amended complaint and then a Second Amended Complaint ("SAC"), alleging a claim for breach of contract against Rigby and a bond claim against Western. (Docket Nos. 44, 54, 64.) Rigby brought a counterclaim for breach of contract against Peck Ormsby and cross-claims against Parkson for breach of contract and indemnification and a bond claim against Western. (Docket No. 55.) Currently before the court are Parkson's and Western's motions to dismiss the claims against them and Parkson's motion to compel arbitration of Rigby's breach of contract claim.

I. Factual and Procedural Background

In January of 2008, Rigby and Peck Ormsby entered into an agreement ("Prime Contract") whereby Peck Ormsby agreed to construct a wastewater treatment plant in Rigby. (SAC ¶¶ 7, 11.) One of the components of the plant, a cloth filtration system, would be made by a subcontractor, who was required under the Prime Contract to provide a written guarantee to Rigby that the filtration system would meet particular specifications. (Rigby's Am. Answer, Crosscl. & Countercl. ¶ 15 (Docket No. 55).) On April 29, 2008, Peck Ormsby and Parkson entered into an agreement ("Purchase Order") whereby Parkson would supply the filtration system. (SAC ¶ 9, 13.) Pursuant to the requirement in the Prime Contract, Parkson provided Rigby a "Performance Guarantee" for its equipment in July of 2008. (Rigby's Am. Answer, Crosscl. & Countercl. ¶ 19.)

On August 15, 2008, Keller Associates ("Keller"), the engineer for the project, reviewed and approved Parkson's submittals for the filtration system. (SAC ¶ 14.) The filtration system was installed and operational by August 18, 2009. (Id. ¶ 15.)

On September 9, 2009, Peck Ormsby received a letter from Keller stating that the filtration system did not meet the specified performance criteria. (Id. ¶ 16.) Peck Ormsby sent the letter to Parkson. (Id. ¶ 17.)

On April 16, 2010, pursuant to a Change Order to the Prime Contract extending the time of final completion for the project, Parkson as principal and Western as surety executed a Maintenance Bond to guarantee the filtration system against defects in material or workmanship, naming Peck Ormsby and Rigby as dual obligees. (Id. ¶¶ 19-20.)

On July 20, 2010, Peck Ormsby received a "rejection letter" from Rigby and Keller formally rejecting the filtration system "based on five (5) reasons indicating that the Equipment is defective." (Id. ¶ 21.) Parkson acknowledged receipt of the letter, but has not repaired the alleged defects. (Id. ¶¶ 22-23.)

The parties have requested that the court consider certain documents in deciding the motions to dismiss. As a general rule, "a district court may not consider any material beyond the pleadings in ruling on a Rule 12(b)(6) motion." Hal Roach Studios, Inc. v. Richard Feiner & Co., 896 F.2d 1542, 1555 n.19 (9th Cir. 1989). However, the court may consider documents on which the complaint necessarily relies if their authenticity is not disputed. See Lee v. City of Los Angeles, 250 F.3d 668, 688 (9th Cir. 2001). On that ground and because the parties have so agreed, the court will consider documents related to the Peck Ormsby-Parkson agreement (Purchase Order Acknowledgment; Parkson's Quotation, including Standard Conditions of Sale, Quotation Addendum, and General Arrangement Drawing; and Addenda to Purchase Order cover letter and Supplier Purchase Order), and Western's Maintenance Bond. (Rothenberg Decl. Exs. A-C (Docket No. 13); Micheli Decl. Ex. A (Docket No. 16).)
In deciding the motion to compel arbitration, the court "may consider the pleadings, documents of uncontested validity, and affidavits submitted by either party." Macias v. Excel Bldg. Servs. LLC, 767 F. Supp. 2d 1002, 1007 (N.D. Cal. 2011) (quoting Ostroff v. Alterra Healthcare Corp., 433 F. Supp. 2d 538, 540 (E.D. Pa. 2006)). The parties request that the court consider the documents comprising the Prime Contract between Rigby and Peck Ormsby, the Purchase Order between Peck Ormsby and Parkson, and the Performance Guarantee. (Mastin Decl. Ex. A (Docket No. 60); Ritchie Aff. Exs. A-F (Docket No. 72).) Accordingly, the court will consider these documents in deciding the motion to compel arbitration.

II. Discussion

A. Motions to Dismiss

On a motion to dismiss, the court must accept the allegations in the complaint as true and draw all reasonable inferences in favor of the plaintiff. Scheuer v. Rhodes, 416 U.S. 232, 236 (1974), overruled on other grounds by Davis v. Scherer, 468 U.S. 183 (1984); Cruz v. Beto, 405 U.S. 319, 322 (1972). "To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to 'state a claim to relief that is plausible on its face.'" Ashcroft v. Iqbal, --- U.S. ----, ----, 129 S. Ct. 1937, 1949 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). This "plausibility standard," however, "asks for more than a sheer possibility that a defendant has acted unlawfully," and "[w]here a complaint pleads facts that are 'merely consistent with' a defendant's liability, it 'stops short of the line between possibility and plausibility of entitlement to relief.'" Iqbal, 129 S. Ct. at 1949 (quoting Twombly, 550 U.S. at 556-57).

1. Western's Motions to Dismiss Rigby's Maintenance Bond Cross-Claim and Peck Ormsby's Bond Claim

The bond pursuant to which Peck Ormsby and Rigby bring their claims against Western states that Parkson "is required to guarantee the work installed under [the Purchase Order] against defects in materials or workmanship, which may develop during the period of one year ending April 20, 2010." (Mitcheli Decl. Ex. A (Docket No. 16-3).) Peck Ormsby and Rigby sue Western for recovery pursuant to the bond on the ground that Parkson failed to repair the filtration system after being informed in the September 9, 2009, letter and the July 20, 2010, rejection letter that the filtration system did not meet the performance standards.

Both Peck Ormsby and Rigby fail to plead liability with the requisite specificity. There is no indication that either of the letters sent to Parkson informed it of "defects in materials or workmanship"; indeed, it appears from the allegations that the filtration system had no actual defects but simply failed to meet the performance standards set out in the Purchase Order and Prime Contract. Western's maintenance bond does not incorporate those performance standards. Even if the term "defect" could be construed to apply to performance issues, the parties have not provided any allegations regarding the type of defect that occurred. The bond claims simply do not cross the line from possibility to plausibility of entitlement to relief.

The court notes that it is unlikely Western would have acted as surety to a bond in April of 2010 if Parkson had already been informed of a defect in September of 2009.

Because Western cannot be held liable unless Parkson failed to meet its obligations under the bond, see Asociacion de Azucareros de Guatemala v. U.S. Nat'l Bank of Or., 423 F.2d 638, 641 (9th Cir. 1970), the court will dismiss Peck Ormsby's and Rigby's bond claims against Western. Peck Ormsby and Rigby have previously been given leave to amend in order to plead these claims with the requisite specificity, but have failed to do so; accordingly, the court will not give leave to amend a second time.

2. Parkson's Motion to Dismiss Rigby's Indemnification Claim

Rigby seeks indemnification from Parkson for any damages Peck Orsmby recovers on its breach of contract claim against Rigby. To state a claim for indemnification, a plaintiff must allege (1) an indemnity relationship, (2) actual liability of the indemnitee to a third party, and (3) a reasonable settlement amount. Chenery v. Agri-Lines Corp., 115 Idaho 281, 284 (1988). Even if Rigby has properly alleged an indemnity relationship, it has not alleged that it has been found liable to Peck Ormsby or that a settlement has been reached. Until that time, Rigby cannot bring a claim for indemnification against Parkson.

Rigby argues that it is required to assert the claim now, even though it admits no settlement has taken place. However, Rigby's claim against Parkson is permissive, not compulsory. See Fed. R. Civ. P. 13(a), (g); Peterson v. Watt, 666 F.2d 361, 363 (9th Cir. 1982). Because Rigby may bring a claim for indemnity against Parkson if and when judgment is entered against Rigby, the court will dismiss this claim.

B. Parkson's Motion to Compel Arbitration of Rigby's

Breach of Contract Claim

The Prime Contract between Rigby and Peck Ormsby provides that the subcontractor installing the filtration system would be required to "provide a written guarantee that the installed filter system will produce an effluent that meets the suspended solids requirements of this specification, based on the specified wastewater quality entering the filtration process." (Ritchie Aff. ¶ 5, Ex. D (Docket No. 70-5).) The Purchase Order between Peck Ormsby and Parkson states that Parkson "does hereby agree to be bound by the terms of the prime contract agreement, construction regulations, general conditions, plans and specifications, and any and all other contract documents in so far as they are applicable to this purchase order." (Id. ¶ 6, Ex. E.) Parkson also agreed "to execute to [Peck Ormsby] and/or [Rigby], a guarantee in writing for [Parkson's] work." (Id.)

Pursuant to these obligations, Parkson provided the Performance Guarantee to Rigby in July of 2008, stating that Parkson would provide a filtration system that would meet specific performance and design specification standards for effluent. (Id. ¶ 7, Ex. F.) The Performance Guarantee also contains an arbitration clause and Florida choice of law provision. (Id.) Rigby now sues Parkson under the Performance Guarantee for breach of contract, and Parkson moves to compel arbitration of the claim.

The Federal Arbitration Act ("FAA") provides that a party may seek an order to compel arbitration from a district court where another party fails, neglects, or refuses to arbitrate. 9 U.S.C. § 4. The Act "leaves no place for the exercise of discretion by a district court, but instead mandates that district courts shall direct the parties to proceed to arbitration on issues as to which an arbitration agreement has been signed." Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 218 (1985). "The court's role under the Act is therefore limited to determining (1) whether a valid agreement to arbitrate exists and, if it does, (2) whether the agreement encompasses the dispute at issue." Chiron Corp. v. Ortho Diagnostic Sys., Inc., 207 F.3d 1126, 1130 (9th Cir. 2000). Upon a showing that a party has failed to comply with a valid arbitration agreement, the district court must issue an order compelling arbitration. Cohen v. Wedbush, Noble, Cooke, Inc., 841 F.2d 282, 285 (9th Cir. 1988), overruled on other grounds by Ticknor v. Choice Hotels Int'l, Inc., 265 F.3d 931 (9th Cir. 2001).

Although the FAA sets forth a policy favoring arbitration, "a party cannot be required to submit to arbitration in any dispute which he has not agreed so to submit." United Steelworkers of Am. v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582 (1960); see also Three Valleys Mun. Water Dist. v. E.F. Hutton & Co., 925 F.2d 1136, 1139 (9th Cir. 1991). Thus, whether a party has submitted to arbitration is first and foremost a matter of contractual interpretation that must hinge on the intent of the parties. United Steelworkers, 363 U.S. at 582; Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473 U.S. 614, 626 (1985).

Rigby does not dispute Peck Ormsby's contention that the arbitration clause, if valid, encompasses the breach of contract claim; Rigby only argues that the arbitration clause in the Performance Guarantee did not constitute a valid agreement.

The commonly accepted meaning of "guarantee" is "[t]he assurance that a contract or legal act will be duly carried out." Black's Law Dictionary 772 (9th ed. 2009). The term "performance" is defined to mean "[t]he successful completion of a contractual duty." Id. at 1252. Thus, "the plain meaning of the term 'performance guarantee' is an assurance or promise that a contractual obligation will be fulfilled." In re Versant Props, LLC, Civil Nos. 1:10cv98, 1:10cv198, 2011 WL 1131057, at *7 (W.D.N.C. Mar. 25, 2011). Parkson was allegedly required by the Purchase Order, which incorporated portions of the Prime Contract, to give Rigby a Performance Guarantee. By giving Rigby the Performance Guarantee, Parkson was promising to fulfill a preexisting obligation.

In deciding this motion, the court makes no judgment regarding the merits of the underlying breach of contract claim. See United Computer Sys., Inc. v. AT & T Corp., 298 F.3d 756, 766 (9th Cir. 2002).

Under Idaho contract law, a party cannot unilaterally amend an agreement to add an arbitration clause unless the original contract expressly provided that party with the right to make such a modification. MBNA Am. Bank, N.A. v. Fouche, 146 Idaho 1, 3 (2008). Parkson unilaterally placed an arbitration clause in the Performance Guarantee it was contractually obligated to give Rigby without the right to do so. Because Rigby never agreed to arbitrate disputes with Parkson, the court will deny Parkson's motion to compel arbitration.

IT IS THEREFORE ORDERED that:

(1) Western's motion to dismiss Peck Ormsby's bond claim be, and the same hereby is, GRANTED;

(2) Western's motion to dismiss Rigby's maintenance bond claim be, and the same hereby is, GRANTED;

(3) Parkson's motion to dismiss Rigby's indemnification claim be, and the same hereby is, GRANTED;

(4) Parkson's motion to compel arbitration of Rigby's breach of contract claim be, and the same hereby is, DENIED; and

(5) The stay of discovery entered by the court on August 22, 2011, is hereby LIFTED.

WILLIAM B. SHUBB

UNITED STATES DISTRICT JUDGE


Summaries of

Peck Ormsby Constr. Co. v. Rigby

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO
Aug 31, 2011
NO. CIV. 1:10-545 WBS (D. Idaho Aug. 31, 2011)
Case details for

Peck Ormsby Constr. Co. v. Rigby

Case Details

Full title:PECK ORMSBY CONSTRUCTION COMPANY, a Utah corporation, Plaintiff, v. CITY…

Court:UNITED STATES DISTRICT COURT FOR THE DISTRICT OF IDAHO

Date published: Aug 31, 2011

Citations

NO. CIV. 1:10-545 WBS (D. Idaho Aug. 31, 2011)