From Casetext: Smarter Legal Research

Novak v. Dormitory Auth. of the State of N.Y

Appellate Division of the Supreme Court of New York, Second Department
Apr 15, 1991
172 A.D.2d 653 (N.Y. App. Div. 1991)

Opinion

April 15, 1991

Appeal from the Supreme Court, Rockland County (Kelly, J.).


Ordered that the order and judgment is modified, by deleting the fifth decretal paragraph thereof, and substituting therefor a provision denying that branch of the defendant's motion which was for partial summary judgment in its favor on its counterclaim for liquidated damages; as so modified, the order and judgment is affirmed insofar as appealed from, without costs or disbursements.

The plaintiff, a plumbing contractor, and one of several prime contractors, brought this action to recover damages arising out of its plumbing work on a project for the construction of a new hospital. The contract form used with each contractor included a broad no-damage-for-delay clause, prohibiting the contractors from recovering delay damages from the defendant for any delays from any cause whatsoever, a hold harmless clause from the action or inaction of any of the other contractors, and a liquidated damages clause fixing a daily rate of $400 per day for each day the contractor is in default after the stated completion date.

It is well established that no-damage-for-delay clauses commonly included in construction contracts are enforceable unless the claimed delays were not contemplated by the parties at the time they entered into the contract or the delay damages were the result of the contractee's intentional wrong-doing, gross negligence or willful misconduct (see, Corinno Civetta Constr. Corp. v. City of New York, 67 N.Y.2d 297; Kalisch-Jarcho, Inc. v. City of New York, 58 N.Y.2d 377; Davis Constr. Corp. v. County of Suffolk, 149 A.D.2d 404; Martin Mechanical Corp. v. Carlin Constr. Co., 132 A.D.2d 688). On this record, we find that the plaintiff has failed to raise any factual issue that the delays were not contemplated by the parties or that the defendant's conduct could be found willful, malicious, in bad faith or grossly negligent. Therefore, partial summary judgment dismissing the plaintiff's second cause of action was properly granted.

However, upon review of the clause relating to liquidated damages, we find that, as a matter of law, the court improperly determined this provision to be unqualified or unconditional. On the contrary, the contract expressly states that a contractor shall not be liable for liquidated damages if the delay in completion was due to, inter alia, acts of another contractor in the performance of a contract with the owner. Since the plaintiff's papers in opposition include correspondence notifying the defendant of delays caused by other contractors, we find that a question of fact is presented for trial, namely whether the delays in completion were caused by the delays of other contractors with whom the plaintiff was required by the defendant to coordinate its work (see, Kelly v. Board of Educ., 7 A.D.2d 856, 857, affd 8 N.Y.2d 764). Thus, partial summary judgment was not proper on this counterclaim in light of the provision which expressly states that the plaintiff shall not be liable for delays caused by other contractors. The fact that the plaintiff may not recover against the defendant for delay damages thus sustained does not mean that the defendant can penalize the plaintiff for delays.

We have examined the plaintiff's remaining contention with respect to its third cause of action and find it to be without merit. Kunzeman, J.P., Kooper, Lawrence and O'Brien, JJ., concur.


Summaries of

Novak v. Dormitory Auth. of the State of N.Y

Appellate Division of the Supreme Court of New York, Second Department
Apr 15, 1991
172 A.D.2d 653 (N.Y. App. Div. 1991)
Case details for

Novak v. Dormitory Auth. of the State of N.Y

Case Details

Full title:NOVAK CO., INC., Appellant, v. DORMITORY AUTHORITY OF THE STATE OF NEW…

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Apr 15, 1991

Citations

172 A.D.2d 653 (N.Y. App. Div. 1991)
568 N.Y.S.2d 453

Citing Cases

Richard H. List, Inc. v. Town of Halfmoon

We also note that the liquidated damages clause specifically stated that the damages were for delay and not…

Novak Co., Inc. v. Dormitory Auth. of State of N.Y

Decided February 25, 1992 Appeal from (2d Dept: 172 A.D.2d 653) FINALITY OF JUDGMENTS AND…