From Casetext: Smarter Legal Research

Neuchatel Asphalte Co. v. Mayor

New York Common Pleas — General Term
Apr 1, 1895
12 Misc. 26 (N.Y. Misc. 1895)

Opinion

April, 1895.

Thomas M. North, for appellant.

C.J.G. Hall, for respondents.


The plaintiff, a foreign corporation, filed a notice of lien against the premises in question on October 25, 1893. It is objected that no lien was thereby effected, because the plaintiff's contract was not enforcible, owing to noncompliance with the provisions of the General Corporation Act of 1892, requiring foreign corporations to procure from the secretary of state a certificate that they have complied with all the requirements of law to authorize them to do business in this state. It is also contended that if a valid lien was originally acquired it was lost by failure to bring an action of foreclosure within ninety days after filing of the notice. Consol. Act, § 1827.

The General Corporation Act referred to prohibits a foreign stock corporation, other than a moneyed corporation, doing business in this state without having procured the certificate referred to; and the section concludes with the provision: "No foreign stock corporation doing business in this state without such certificate shall maintain any action in this state upon any contract made by it in this state until it shall have procured such certificate."

The plaintiff was doing business in this state when the act was passed, and made the contract and performed the work upon which defendant's claim is based, in this city, in the year 1893, but did not procure the certificate required by the act until December 4, 1893, which was after the filing of its lien, but before it attempted to commence an action of foreclosure. Although this contract when made was prohibited by the statute, it was nevertheless enforcible by action as soon as the certificate was procured. The clause quoted undoubtedly refers to prohibited contracts, i.e., contracts made while the corporation was doing business without a certificate, for by its terms it applies to corporations so doing business and no others. Were it intended to prohibit actions upon contracts untainted by illegality (such as contracts made before the statute) the qualification "without such certificate" would have been omitted, and the clause would have simply provided that "no foreign corporation doing business in this state shall maintain any action in this state upon any contract made by it in this state until it shall have procured such certificate." By qualifying the corporation as one "doing business in this state without a certificate" the provision applies only to corporations engaged in violations of the act, and its only purpose is to afford such corporations an opportunity to make their contracts, otherwise unenforcible, cognizable by the courts of this state.

By this construction effect is given to every part of the section of the act in question; for if the last clause were not intended to help contracts that were invalid, it would be mere surplusage; the general prohibition contained in the first part of the enactment would be sufficient to prevent recovery upon contracts made in violation of such prohibition. This construction also relieves the court from the necessity of considering the point suggested in Murphy Varnish Co. v. Connell, 10 Misc. 553, that the act in question may be in conflict with the Constitution of the United States reserving to congress the regulation of commerce between the states and with foreign nations; for we regard the statute as merely refusing, in certain cases, the use of the courts of this state to foreign corporations until they comply with its laws.

Having procured the certificate of the secretary of state on December 4, 1893, this plaintiff was enabled to maintain an action upon its contract and to foreclose its lien by action. An attempt to commence such an action was made in January, 1894, but the contractor, Matthias Theriault, under whom plaintiff claims as subcontractor, was not served with the summons in that action until February 7, 1894, which was more than ninety days after the filing of the lien. The Lien Act declares that no lien shall be binding upon the property unless an action be commenced within ninety days from the filing of the same and a notice of pendency of action be filed with the comptroller. Consol. Act, § 1827. The same act declares that any claimant who has filed a lien may enforce his claim by a civil action. § 1829. The party commencing such action must make all parties who have filed claims, the contractor and the city parties defendant. § 1830.

It is contended against the plaintiff that its failure to serve the summons upon the contractor within ninety days from the filing of its lien was a failure to commence an action within that period, as the contractor was a necessary party and the principal party to the litigation, and that the service upon the city within the prescribed time was not the commencement of the action. If this contention were fair then it would result that in any case where a lienor plaintiff commenced an action, but failed to serve his summons upon any other lienor within the ninety days, such plaintiff's lien would cease to be binding, for the statute makes every claimant a necessary party equally with the city and the contractor. It would seem a reasonable compliance with the statute to hold that an action is commenced if all the necessary parties are included in it, and service upon either the contractor or the owner or holder of the fund claimed is effected within the ninety days; but it is not necessary to rest a decision in favor of this plaintiff upon that construction, as his lien is saved by the fact that an action was commenced by another lienor, and the city and the contractor served therein, before the expiration of ninety days from the filing of this plaintiff's lien.

The statute does not prescribe that each lienor must commence a separate action to foreclose his lien, but that within ninety days from the filing of it "an action" shall be commenced, and as all the parties who have filed liens are necessary parties to any such action, and may set forth their claims by answer, and the court is to decide the extent, justice and priority of the claims of all parties therein (§ 1830), it would seem that any action so commenced is, in effect, an action on behalf of each party entitled when it is so commenced to maintain an action to enforce his own lien. Even were the plaintiff in such action to fail therein for want of a lien the action would not abate, but would be retained to afford the defendants the relief which they were entitled to among themselves. Morgan v. Taylor, 5 N.Y.S. 920.

One of the parties filing liens upon this fund under the contract with Theriault was Kuhnla, who filed his lien on October 20, 1893, and who commenced an action to foreclose it and served the city and the contractor within ninety days after that date, and of course within ninety days from the filing of the plaintiff's lien, which was on October 25, 1893. To that action the plaintiff was a necessary party, made so by statute, and if omitted would have to be brought in upon his own application, or that of any other party. He was made a party and answered. His lien was, therefore, enforcible by him in that action, which was commenced while his lien was binding upon the fund; and when that action was consolidated with his own, and with that of a third lienor, the consolidated action still remained Kuhnla's action, and plaintiff was entitled to all the benefits which he derived from its timely commencement.

The judgment should, therefore, be modified so as to provide for the payment out of the fund of the plaintiff's lien in the order of priority of its filing, and as so modified affirmed, with costs of this appeal to the appellant to be paid out of the fund. McAllister v. Case, 5 N.Y.S. 918.

BISCHOFF and PRYOR, JJ., concur.

Judgment modified so as to provide for the payment out of the fund of plaintiff's lien in the order of priority of its filing, and as so modified affirmed.


Summaries of

Neuchatel Asphalte Co. v. Mayor

New York Common Pleas — General Term
Apr 1, 1895
12 Misc. 26 (N.Y. Misc. 1895)
Case details for

Neuchatel Asphalte Co. v. Mayor

Case Details

Full title:THE NEUCHATEL ASPHALTE Co., LIMITED, Appellant, v . THE MAYOR, ETC., of…

Court:New York Common Pleas — General Term

Date published: Apr 1, 1895

Citations

12 Misc. 26 (N.Y. Misc. 1895)
33 N.Y.S. 64

Citing Cases

Newman Lumber Co. v. Wemple

Such action shall be deemed an action to enforce the lien of such defendant lienor," etc. The main object of…