Opinion
1:08-cv-00759-MMB-BAM
01-31-2022
ORDER RESPECTING DEFENDANTS' MOTION IN LIMINE #1
M. MILLER BAKER, JUDGE
Defendants' first motion in limine (ECF 469) seeks an order “on the appropriate method for calculating and proving damages.” ECF 469, cover page. They raise two issues that are relevant for present purposes: (1) whether damages in a RESPA case are limited to the amounts individual class members paid themselves for improper “settlement services, ” as that term is used in the statute, or whether damages may include all amounts paid for the settlement services regardless of who paid those amounts (i.e., including amounts paid by someone else on behalf of a class member); and (2) whether any damages calculation should be reduced (“offset”) by any claims paid by Atrium. 1
Defendants also argue that damages should be limited to any overcharges paid by the plaintiffs. ECF 469, at 6-7. They candidly admit this argument runs directly counter to controlling circuit precedent and they seek to preserve it for en banc or Supreme Court review. See Id. at 8 (acknowledging that Edwards v. First Am. Corp., 610 F.3d 514, 517 (9th Cir. 2010), abrogation recognized on other grounds by Frank v. Gaos, 139 S.Ct. 1041, 1044, 1046 (2019), forecloses this argument).
I.
Defendants contend that “class members' damages should be limited to the amounts the class members paid in mortgage insurance premiums themselves, as opposed to any amounts their loan servicers or others paid on their behalf.” ECF 469, at 4. In support of this argument, they cite the RESPA statute, which authorizes damages “to the person or persons charged for the settlement service involved in the violation in an amount equal to three times the amount of any charge paid for such settlement service.” 12 U.S.C. § 2607(d)(2). Defendants focus on the words “to the person or persons charged.” ECF 469, at 4. They also cite the court's final pretrial order in this case, which summarized Plaintiffs' position as seeking “monetary recovery under RESPA, Section 8(d)(2), 12 U.S.C. § 2607(d)(2), in an amount equal to three times the amount of all private mortgage insurance payments made by class members in connection with loans originated/purchased by PHH during the class period.” ECF 456, at 8 (emphasis added). Defendants place particular significance on the words “made by class members” and argue that those words inherently require evidence of what amounts were paid by the plaintiffs themselves, as opposed to amounts paid by loan servicers. ECF 469, at 4-6.
In response, Plaintiffs accuse Defendants of trying to convince the court to reconsider prior rulings in violation of the law of the case doctrine. Plaintiffs contend the court has “ma[d]e clear that the proper measure of damages is the 2 entire settlement charge . . . for private mortgage insurance.” ECF 480, at 5. They assert that damages are not limited to the amounts individual class members paid. Like Defendants, they focus on the statutory language, but they emphasize the words “three times the amount of any charge paid, ” id. at 7 (emphasis in Plaintiffs' brief), to argue that “[t]here is no limiting language, which Defendants would have this Court read into the statute, restricting damages to the particular amount each Class Member actually paid or excluding payments possibly made on their behalf, ” id. They further argue that the court previously “determin[ed]” that “[i]f liability is proven, the damages for this violation are provided by statute, and call for three times the amounts paid for Defendants' settlement service.” Id. (quoting Munoz v. PHH Corp., No. 1:08-cv-0759-AWI-BAM, 2013 WL 2146925, at *25 (E.D. Cal. May 15, 2013) (ECF 230) (Magistrate Judge's findings and recommendation on class certification)). In reply, Defendants further emphasize the final pretrial order and refer to it as containing the court's “interpretation of the statute” as being that damages would be “three times the amount of all private mortgage insurance payments made by class members.” ECF 490, at 2 (quoting ECF 456, at 8) (emphasis Defendants'). They refer to the final pretrial order as “the last in time statement on this issue from the Court.” Id. at 3. Defendants also argue that “[t]he statute's own language makes clear that the language Plaintiffs like (that damages are ‘three times the amount of any charge paid') is plainly ‘limited' by the 3 statute's restriction of damages ‘to the person or persons charged.' ” ECF 490, at 2 (emphasis in original).
Defendants' argument prevails for two reasons. First, theirs is the better reading of the relevant statutory provision, which states:
Any person or persons who violate the prohibitions or limitations of this section shall be jointly and severally liable to the person or persons charged for the settlement service involved in the violation in an amount equal to three times the amount of any charge paid for such settlement service.12 U.S.C. § 2607(d)(2) (emphasis added).
“Statutory construction . . . is a holistic endeavor.” United Sav. Ass'n of Tex. v. Timbers of Inwood Forest Assocs., Ltd., 484 U.S. 365, 371 (1988). That means when a court “look[s] to the plain language of a statute in order to interpret its meaning, [it] do[es] more than view words or sub-sections in isolation. [The court] derive[s] meaning from context, and this requires reading the relevant statutory provisions as a whole.” In re Rufener Constr., Inc., 53 F.3d 1064, 1067 (9th Cir. 1995).
Taken in context of the entire provision, the words “any charge paid” must refer to any amounts paid by “the person or persons charged for the settlement service”-i.e., the borrower, which in this case means Plaintiffs and the class members. Thus, while Plaintiffs are correct that the statutory 4 language controls, their interpretation impermissibly reads the words “any charge paid” in isolation.
Freeman v. Quicken Loans, Inc., 566 U.S. 624, 627 (2012) (emphasis added; brackets in original) (quoting 12 U.S.C. § 2607(d)(2)). While Freeman did not address the precise issue present here, the Court's reading of the statute is nevertheless instructive. See also Alston v. Countrywide Fin. Corp., 585 F.3d 753, 760 (3d Cir. 2009) (“[D]amages are fixed at three times the total charge paid by the consumer in exchange for a settlement service, and not merely any overcharge.”) (emphasis added); In re Carter, 553 F.3d 979, 986 (6th Cir. 2009) (“[T]he court finds that a defendant is liable for the charges assessed the home buyer for settlement services as a whole, and not just for overcharges.”) (emphasis added, original emphasis removed); Valdez v. Downey Sav. & Loan, No. C 06-2541 JF (HRL), 2008 WL 4452116, at *2 (N.D. Cal. Oct. 3, 2008) (“For violations of RESPA, a plaintiff may recover three times the amount of the settlement services paid by the borrower, plus costs and reasonable attorneys' fees.”) (emphasis added). In the course of addressing a different issue, the Supreme Court noted that RESPA's substantive provisions are enforceable through, inter alia, actions for damages brought by consumers of settlement services against “[a]ny person or persons who violate the prohibitions or limitations” of § 2607, with recovery set at an amount equal to three times the charge paid by the plaintiff for the settlement service at issue.
Second, Plaintiffs' reliance on the law of the case doctrine is misplaced. That doctrine “simply does not impinge upon a district court's power to reconsider its own interlocutory order provided that the district court has not been divested of jurisdiction over the order.” City of Los Angeles, Harbor Div. v. Santa Monica Baykeeper, 254 F.3d 882, 888 (9th Cir. 2001). “The legal effect of the doctrine of the law of the case depends upon whether the earlier ruling was made by a trial court or an appellate court. All rulings of a trial court are subject to revision at any time before the entry of judgment.” Id. (emphasis in original) (quoting United States v. Houser, 804 F.2d 565, 567 (9th Cir. 1986), 5 abrogated on other grounds by Christianson v. Colt Indus. Operating Corp., 486 U.S. 800, 816-17 & n.5 (1988)). This principle is consistent with the rule that “as long as a district court has jurisdiction over the case, then it possesses the inherent procedural power to reconsider, rescind, or modify an interlocutory order for cause seen by it to be sufficient.” Id. at 889 (quoting Melancon v. Texaco, Inc., 659 F.2d 551, 553 (5th Cir. Unit A 1981), and citing Fed.R.Civ.P. 54(b)).
Judgment has not been entered in this case. Therefore, the court's various orders do not constitute law of the case. Moreover, even if they were binding under the law of the case doctrine, at no time did the court “determine” or “hold, ” as Plaintiffs contend, that damages are three times the amount paid for settlement services without regard to who paid those amounts. Indeed, the Magistrate Judge's findings and recommendation on class certification-on which Plaintiffs heavily rely-states, “Plaintiffs seek recovery of three times the amount class members paid for PHH's settlement services.” 2013 WL 2146925, at *2 (emphasis added); see also Id. at *22 (“If Defendants' conduct violated Section 8, Defendants would be liable to Mr. Munoz for damages in an 6 amount equal to three times the amount Mr. Munoz paid
for PHH's settlement service.”) (emphasis added).
The court's final pretrial order, meanwhile, merely summarizes the parties' positions in advance of trial and-contrary to Defendants' argument-in no way constitutes a “holding, ” “determination, ” or any other form of statement of the court's view as to the proper measure of damages. It further bears noting that the final pretrial order was consistent with Plaintiffs' own position on damages dating back to their first amended complaint, which seeks relief as follows: “Plaintiffs and the Class are entitled to recover from Defendants an amount equal to three times the amounts they have paid or will have paid for private mortgage insurance as of the date of judgment.” ECF 96, ¶ 97 (emphasis added).
Therefore, the court concludes that Defendants' interpretation is the correct one-statutory damages are limited to the amounts actually paid by the individual plaintiffs or class members and do not include other amounts paid on their behalf by PHH or some other entity.
II.
Defendants also contend that “[a]ny damages calculation should also necessarily be reduced, or offset, by any claims paid by Atrium.” ECF 469, at 6. Plaintiffs' response argues that the Magistrate Judge “specifically rejected” Defendants' contention on this issue by stating that “Section 8 does not suggest that statutory damages would be offset by any reinsurance payments made by Atrium…..there is no authority in Section 8, case law, or HUD guidance for ‘offset.' ” ECF 480, at 4 (five-dot ellipsis in original) (quoting 2013 WL 2146925, 7 at *25). Defendants simply reply that the Magistrate Judge did not actually decide the issue. ECF 490, at 8.
As an initial matter, for the reasons discussed above, any prior order in this case is neither determinative nor binding. With that said, Defendants are correct that the Magistrate Judge made the statement in question as part of a determination that “[d]iffering amounts of individual class members' damages does not defeat [class] certification, ” 2013 WL 2146925, at *25, rather than as a substantive ruling on the “offset” issue. Critically, however, her explanation was broader than what Defendants suggest. She explained as follows:
Defendants' argument that delinquent class members would require individual damage determinations is wrong for two reasons: First, Section 8 does not suggest that statutory damages would be offset by any reinsurance payments made by Atrium. Defendants suggest this is the only “fair” result, however, there is no authority in Section 8, case law, or HUD guidance for “offset.” Second, even if damage offset would be appropriate, such an analysis would be conducted on a classwide basis because Atrium's reinsurance agreement is not maintained on an individualized loan basis. Reinsurance payments are made from a cross-collateralized trust account covering all book years in the aggregate, and therefore, any offset would be on per-reinsurance-agreement basis; not by individual loan. Accordingly, the individual and classwide damage determinations involved in this case are properly certified under Rule 23.Id.
It is apparent from the context that the Magistrate Judge did reject Defendants' “offset” argument, as she clearly stated that “there is no authority in Section 8, case law, or HUD guidance for ‘offset.' ” 2013 WL 2146925, at *25 8 (emphasis added). Nothing in Defendants' motion in limine challenges that statement, which the court finds persuasive on its own merits. The court expects that a party disagreeing with a determination that there is “no authority” for a proposition would respond by citing some “authority” (be it the statute, case law, HUD guidance, or prior rulings in this case), but Defendants have failed to do so here. Accordingly, like the Magistrate Judge, the court concludes that there is no basis in law for Defendants' “offset” theory.
III.
Finally, Plaintiffs' opposition brief argues that because RESPA provides for automatic trebling of damages, “any Order addressing the appropriate method for calculating and proving damages [should] specifically provide that Defendants may not reference the trebling provision of RESPA in any argument or evidence presented to the jury.” ECF 480, at 9 n.5. That argument represents an affirmative request for relief that Plaintiffs should have raised (but did not) via a motion in limine. Defendants are also correct that it is inappropriate to raise a request for relief solely via a footnote. As the Ninth Circuit has explained, “a cursory mention of an issue in a footnote without citation to legal authority is insufficient . . . .” Momox-Caselis v. Donohue, 987 F.3d 835, 842 (9th Cir. 2021). Plaintiffs may instead address this issue via their proposed jury instructions. 9
Conclusion It is hereby ORDERED that Defendants' motion in limine #1 is
GRANTED IN PART and DENIED IN PART as follows:
1. Defendants' motion is GRANTED insofar as it requests an order stating that the statutory RESPA damages are limited to the amounts actually paid by the individual plaintiffs or class members and do not include other amounts paid on their behalf by PHH or some other entity.
2. Defendants' motion is DENIED insofar as it seeks an order stating that any damages calculation should be reduced, or offset, by any claims paid by Atrium.
3. Defendants' motion is also DENIED insofar as it seeks an order providing that damages should be limited to any overcharges paid by the plaintiffs, as any such order would be counter to controlling Ninth Circuit precedent.
Finally, it is further ORDERED that Plaintiffs' request that the court's order deciding Defendants' motion should preclude Defendants from referring to RESPA's treble damages provision in the presence of the jury is DENIED WITHOUT PREJUDICE to Plaintiffs' right to address that issue in their proposed jury instructions.
Judge of the United States Court of International Trade, sitting by designation.