Summary

measuring damages by diminution in value where restoration would require construction of entirely new home

Summary of this case from Royal Capital Development, LLC v. Maryland Casualty Co.

Opinion

38688.

DECIDED FEBRUARY 9, 1961.

Action for damages. Sumter Superior Court. Before Judge Rees.

R. R. Jones, for plaintiff in error.

Smith Undercofler, Hiram K. Undercofler, contra.


1. Since the defendant would have had the right to contest the amount of unliquidated damages, and the amount of damages was the only issue submitted to the jury, it was not harmful error, even if it was error, for the court to overrule motions to strike the defendant's answer because it was not filed in time and the alleged default was not properly opened.

2. Under the pleadings and evidence in this case it was not error for the court to refuse to charge the jury as requested that the measure of damages to a house, which had to be completely rebuilt in order to be restored, was the cost of repair or restoration.

3. The request to charge was a single, entire request, and since part of it was defective, as shown in the preceding headnote, the court did not err in refusing the entire request.

DECIDED FEBRUARY 9, 1961.


W. G. Mercer sued J. M. Transportation Co., Inc., to recover damages which the plaintiff allegedly sustained when a residence which he owned in Dawson, Georgia, was struck by the defendant's truck when, due to the negligence of its driver, it swerved from the street and ran into the side of the residence, striking it with such force as to render it worthless as a residence. The original petition alleged that the market value of the house was $16,000 immediately before it was damaged and that after it was damaged it had no market value. By amendment the petition was made to allege also that the cost of restoring said dwelling house to the condition in which it was before being damaged was $16,000. The defendant denied the allegations of the petition. The jury found for the plaintiff in the sum of $6,312. The plaintiff excepts to the overruling of his motion to strike the defendant's answer on the grounds that it was filed too late and that it was filed when the case was in default without a legal opening of the default. He also excepts to the overruling of a second motion to dismiss the answer the basis of which, as ruled by the court, was that the plaintiff had waived the alleged illegal filing of the answer. By agreement liability of the defendant was admitted and it was agreed that the amount of liability was the only issue to be submitted to the jury. The plaintiff's motion for a new trial was overruled and he also excepts to that judgment.


1. Assuming for the sake of argument that the court erred in not dismissing the defendant's answer, which we do not consider or decide, no harm is shown since only the question of ascertaining the damages which were unliquidated at the time of trial was submitted to and decided by the jury, and the defendant had a right to introduce evidence on this question and to move for a new trial and to except as in other cases. Ben Hyman Co. v. Solow, 101 Ga. App. 249 ( 113 S.E.2d 489).

2. The special ground of the amended motion for a new trial complains that the court erred in refusing to give in charge a proper request that the measure of damages would be whatever amount it would take to put the house in the condition it was in before the damage. This part of the ground is without merit. "Damages are given as compensation for the injury done. . . " Code § 105-2001. "As a general rule the measure of damages in actions for injuries to real property is the difference in value before and after the injury to the premises." Georgia R. Bkg. Co. v. Flynt, 93 Ga. App. 514, 524 ( 92 S.E.2d 330). The only exception is when there is a more definite, equitable and accurate way by which the damage may be determined. Regardless of the effect of the plaintiff's pleading two measures of damage, the cost of restoration to the same condition as before the injury and the difference between the market value before the damage and after, the circumstances of this case and the reason, law and logic applicable, required that the court charge, as he did, that the measure of damage was the difference between the market value of the house before and after the damage. It is doubtful whether the assignment should be considered for the reason that the request that replacement cost be charged would have resulted in a duplicitous and conflicting charge. There is no exception to the charge actually given. Pretermitting this question we think that the replacement method should not be applied in a case like this. There are several reasons for this conclusion. The rationale of damages, as in this case, is to compensate the plaintiff and not to unreasonably burden the defendant beyond the point of compensating the plaintiff. The house destroyed was an old house. It could not be repaired. It had to be completely restored. Half of the life of the roof was gone. It was a house 25 or 30 years old. Originally it did not have plumbing or wiring. There were originally no subfloors, bath rooms, no modern heating or other features. To restore such a house to the condition it was in just before being damaged would be an absurd undertaking. The house rented, at most, for $50 per month. It is not reasonable to believe that it would rent for much more, if any, after being restored to its former condition. To require the defendant to replace the house at a cost of up to $17,000, the top figure in the evidence, when it would not be worth much more than half of such sum to the plaintiff, to our minds would be ridiculous. The evidence authorized the verdict rendered. The basis on which the verdict was rendered under the facts was the only reasonable basis upon which the amount of damages could be found. The court did not err in not charging as requested in the first part of the request.

3. The second part of the assignment of error in special ground 1 is without merit. The second part of the request is that the court charge that "in a suit for damages that interest is not recoverable but that the jury may consider the length of time damages had been withheld, the character of the tort, the conduct of the defendant, and all circumstances of the transaction, and may in their discretion increase the amount of damages accordingly." This request was a part and parcel of the one request made and since the first part of the request was defective the court did not err in refusing the entire single request. Clarke County School Dist. v. Madden, 99 Ga. App. 670 (5) ( 110 S.E.2d 47).

The court did not err in overruling the motions to dismiss the answer and did not err in overruling the motion for a new trial.

Judgments affirmed. Nichols and Bell, JJ., concur.


Summaries of

Mercer v. J. M. Transportation Co.

Court of Appeals of Georgia
Feb 9, 1961
118 S.E.2d 716 (Ga. Ct. App. 1961)

measuring damages by diminution in value where restoration would require construction of entirely new home

Summary of this case from Royal Capital Development, LLC v. Maryland Casualty Co.

measuring diminution in value where restoration of home would have required construction of entirely new home

Summary of this case from 325 Goodrich Avenue, LLC v. Southwest Water Co.

measuring damages by diminution in value where restoration would require construction of entirely new home

Summary of this case from Royal Capital Development, LLC v. Maryland Casualty Co.

measuring damages by diminution in value where restoration would have required construction of entirely new home

Summary of this case from John Thurmond Associates v. Kennedy

In Mercer v. J. M. Transportation Co., 103 Ga. App. 141 (2) (118 S.E.2d 716) where a similar charge was given and a similar objection made, the court, considering the differences between before and after value and cost of restoration of a building which could not be repaired because of the extent of destruction, held that to set the damages at replacement cost would "to our minds be ridiculous" as demanding an inflated measure of damages.

Summary of this case from Cornett v. Agee
Case details for

Mercer v. J. M. Transportation Co.

Case Details

Full title:MERCER v. J. M. TRANSPORTATION CO., INC

Court:Court of Appeals of Georgia

Date published: Feb 9, 1961

Citations

118 S.E.2d 716 (Ga. Ct. App. 1961)
118 S.E.2d 716

Citing Cases

John Thurmond Associates v. Kennedy

Where demanded by the facts of a case, courts also have determined damages in such cases by measuring the…

Atlanta c. Co. v. Tri-Cities c. Co.

See Woodward v. City Council of Augusta, 117 Ga. App. 857, 858 ( 162 S.E.2d 304). 3. The next enumeration of…