From Casetext: Smarter Legal Research

McPhail v. Johnson

Supreme Court of North Carolina
Sep 1, 1891
13 S.E. 799 (N.C. 1891)

Opinion

(September Term, 1891.)

Action, Splitting — Jurisdiction — Contract.

Under a contract which stipulated that the defendant was to receive "the entire output" of a mill, and pay the plaintiff a certain price per thousand for all lumber sawed, "as it was taken from the saw," the plaintiff made successive deliveries of lumber, the value of each delivery being less than $200, but the aggregate value was greater than that amount: Held, that while the plaintiff might have maintained an action before a justice of the peace for the value of each delivery as it was made, having postponed his suit until the whole sum became due, he could not split the cause of action and thereby confer jurisdiction on the justice of the peace.

ACTION, tried at May Term, 1891, of CUMBERLAND, before (572) Armfield, J.

T.H. Sutton for plaintiffs.

G. M. Rose for defendant.


The facts necessary to an understanding of the opinion are as follows:

This was one of three civil actions commenced and tried at the same time in the court of a justice of the peace of Cumberland County, in all of which plaintiffs recovered judgment, and the defendant appealed to the Superior Court.

The actions were founded upon a written contract between the defendant and the firm of H. Wade Co., the latter firm having assigned their interest to plaintiffs.

Plaintiffs alleged that the whole of said contract had been performed before the bringing of the said three actions, and that there was then due to plaintiffs on said contract, or for work done thereunder, a sum largely in excess of two hundred dollars, but as the contract had been performed by several deliveries of lumber at different times, which several deliveries were respectively under $200, that they had a right to split up their account and bring their several actions for sums respectively less than $200, though aggregating more than $200, in the court of a justice of the peace.

The following is a copy of the part of the contract material here:

"4. The said James H. Johnson is to receive the entire output of said mill, and pay the said H. Wade Co. the sum of two dollars and fifty cents per thousand feet for any and all lumber so sawed, as it is taken from the saw, and sawed according to bills furnished, in a workman-like manner."

His Honor intimated that, as the whole amount claimed by plaintiff was due when these three actions were commenced, that the plaintiffs could not split up their cause of action as they had attempted to do, so as to give jurisdiction to the justice.

In deference to this opinion of his Honor, plaintiffs took a (573) nonsuit, and appealed to the Supreme Court.


The alleged indebtedness of the defendant to the plaintiffs accrued from time to time, and at divers times, under and by virtue of a single contract, whereby H. Wade Co. agreed to supply the defendant with "the entire output" of a lumber mill, and they completely performed their part of such contract. The sum of money demanded by the plaintiffs was much more than two hundred dollars, and to facilitate the collection of their debt they subdivided their claim, so as to bring each part of it within the jurisdiction of a justice of the peace. They contend that they had the right to do so, because they supplied the lumber from the mill at divers times and on various accounts. This contention is not well founded. The indebtedness having accrued, was single — a whole — one debt, arising out of a single contract that possessed a single purpose — the supply of lumber. This case clearly comes within what is said and decided in Jarrett v. Self, 90 N.C. 478; Moore v. Nowell, 94 N.C. 265; Kearns v. Heitman, 104 N.C. 332.

If, however, the delivery under the contract was made by distinct installments, an action would lie for the amount due for the same at once. But when more than one such installment has been delivered, but one action lies for the whole amount due on account of same.

Affirmed.

Cited: Simpson v. Elwood, 114 N.C. 529; Smith v. Lumber Co., 140 N.C. 377; S. c., 142 N.C. 30.


Summaries of

McPhail v. Johnson

Supreme Court of North Carolina
Sep 1, 1891
13 S.E. 799 (N.C. 1891)
Case details for

McPhail v. Johnson

Case Details

Full title:McPHAIL BROS. v. J.H. JOHNSON

Court:Supreme Court of North Carolina

Date published: Sep 1, 1891

Citations

13 S.E. 799 (N.C. 1891)
109 N.C. 571

Citing Cases

Smith v. Lumber Company

The position, whether intrinsically correct or not, seems to be sustained by high authority. Jarrett v. Self,…

Smith v. Lumber Co.

The defendant relied upon the judgment recovered before the justice of the peace for the second month's…