From Casetext: Smarter Legal Research

Matter of Energy Control Systems of the Midwest, Inc.

United States Bankruptcy Court, W.D. Wisconsin.
Oct 14, 1982
23 B.R. 696 (Bankr. W.D. Wis. 1982)

Opinion


        Stephen J. Meyer, Van Metre, Hanson, Clarke, Schnitzler & Meyer, Madison, Wis., for plaintiff.

        Joseph J. Mihalek, Fryberger, Buchanan, Smith & Frederick, P.A., Duluth, Minn., for defendants.

        DECISION

        ROBERT D. MARTIN, Bankruptcy Judge.

        On July 8, 1981, Energy Control Systems of the Midwest began this adversary proceeding by filing a complaint which named Com/Energy Products Co., Inc. (Com/Energy) and New England Gas and Electrical Association (NEGEA) as defendants. The complaint contained causes of action for fraud and breach of contract. No request for a jury trial was made in the complaint, but plaintiff's attorney did mark a box on the bankruptcy cover sheet indicating that a jury trial was requested. This cover sheet is retained in the bankruptcy court file and is not served on the parties. On August 11 defendants filed an answer and counterclaim, and on August 19 the reply to the counterclaim was filed. In none of these documents was reference made to a jury trial.

        The defendants moved to dismiss the suit against Commonwealth Energy System, formerly known as New England Gas and Electric, for failure to state a claim on which relief could be granted. The motion, supporting affidavit and memorandum claimed the complaint did not allege any basis for Commonwealth Energy System's liability for Com/Energy's actions. The motion to dismiss was granted on December 7, 1981, with leave to amend. The amended complaint was filed on January 28, 1982. This complaint added a cause of action which alleged the basis for Commonwealth Energy System's liability for Com/Energy's actions. No answer to the amended complaint has ever been filed.

        On March 8 a motion for more definite statement was filed. The motion alleged that the cause of action added by plaintiff's amended complaint was so vague that a responsive pleading could not be framed. The motion for more definite statement was denied on April 6, 1982.

        On April 9, 1982, plaintiff filed a demand for a jury trial, "pursuant to Rule 38(b)" on all issues in the adversary proceeding. On April 14, 1982, defendants objected to the request for a jury trial as not timely. No response was filed to this objection.

        Requests for a jury trial in bankruptcy cases are governed by Interim Rule 9001, which is identical to Rule 38(b) of the Federal Rules of Civil Procedure. Rule 9001 provides:

It should be noted that neither the Rules of Bankruptcy procedure nor the Interim Rules adopt Rule 38(b) of the Federal Rules which permits the court to grant an untimely jury demand in its discretion.

         Because Interim Rule 9001 and Rule 38(b) are identical, it is appropriate to use cases construing Rule 38(b) to help interpret Rule 9001, particularly as there appear to be no cases on point construing Rule 9001. See In Re Patterson, 6 B.R. 149, 6 B.C.D. 969 (Bkrtcy.S.D.Ohio 1980).

         The first issue to address is whether plaintiff's act in checking the box marked "jury trial requested" on the bankruptcy case cover sheet constitutes a demand for jury trial which meets the requirements of Rule 9001. Rule 9001 requires that the party requesting the jury trial serve his demand for a jury trial on the other parties. As noted earlier, the bankruptcy cover sheet is not served on the parties, but is retained by the court. Thus, the requirement of notice of the jury demand is not met. The court in Omawale v. WBZ, 610 F.2d 20 (1st Cir. 1979) used this reasoning to deny a request for a jury trial where the defendant had marked the civil cover sheet.

         On April 9, 1982, plaintiff did serve a written demand for a jury trial on the other parties. There appears to be no issue as to the sufficiency of this demand; the timeliness, however, is in dispute. Rule 9001 requires that the demand for a jury trial on any issue be made "not later than 10 days after the service of the last pleading directed to such issue." In the instant case, the last pleading directed at any issue was the amended complaint, filed on January 28, 1982. As the demand for the jury trial was not made in the required form until April 9, 1982, it appears that the jury demand was not timely.

         The jury demand in the instant case, however, was made within the time that an answer to the amended complaint could have been filed, although defendants chose not to file such an answer. This is because the motion for more definite statement filed by defendants had the effect under Bankruptcy Rule 712(a) of extending the time for filing an answer until five days after the motion was denied and notice given of the court's action. The court denied the motion for more definite statement on April 6, and the defendant's answer could have been filed until April 11. Thus, plaintiff's April 9 jury trial demand fell within the time an answer could have been filed and, had an answer been filed, would have been timely as to the issues raised in the amended complaint. The key question then is, must an answer actually have been filed for the demand to have been timely, or is it enough that the jury demand was filed during the time an answer could have been filed? The language of the Rule indicates that the former approach is correct. The Rule speaks of service of the last pleading as the date from which the ten-day period runs. If the drafters of the Rule had wished the period to run from the last day that a pleading could have been served, it would have been a simple matter to have done so.

        However, the Tenth Circuit chose the other alternative in U.S. v. Anderson, 584 F.2d 369 (10th Cir. 1978). In Anderson, the defendant requested a jury trial more than ten days after the service of the last pleading, but before the Government had filed a reply to his counterclaim. The counterclaim was later dismissed. The court found that the jury demand had been timely made. The court reasoned:

        The court did not seem to consider it important that no reply to counterclaim was ever filed nor could have been filed as the counterclaim was dismissed. In all of the cases cited by the Tenth Circuit, the demand for a jury trial was made within the ten-day period after a pleading had actually been served, not merely within the time that a pleading could have been made. The Tenth Circuit apparently considered the crucial factor to be that a reply could have been made to the counterclaim, whether one was made or not.

        The one Seventh Circuit Case construing Rule 38(b), while not precisely on point, does shed some light. In Dasho v. Susquehanna Corp., 461 F.2d 11 (7th Cir. 1972), cert. denied, 408 U.S. 925, 92 S.Ct. 2496, 33 L.Ed.2d 336 (1972) plaintiff's demand for a jury trial was filed several months after all defendants had answered and was incorporated in a reply which itself was not filed within the time specified by the court. The court found that the jury demand was timely made:

        In Dasho, unlike Anderson and unlike the instant case, the jury demand was made within ten days of a pleading which had actually been filed. In that sense it is a very different case. The rationale presumed by the Court of Appeals for Rule 38(b) is illuminating, however. The court suggests that this rule was designed to enable a party to make his decision about a jury trial based on the very last pleading, apparently because this pleading could change the issues in some way which would make a jury trial more attractive. In cases

Page 700.

like the instant case, however, where an allowed pleading has not been made, there has been no change in the issues so as to justify allowing plaintiff to demand a jury. Thus, on the basis of the language of the Rule, its underlying rationale, and the one case in our Circuit construing it, I am satisfied that I must strike the jury demand as untimely.

        Even if it were decided to follow the reasoning in Anderson, it is clear that the jury demand would be timely as to only those issues newly raised by the amended complaint. As the court in First Wisconsin National Bank of Rice Lake v. Klapmeier, 526 F.2d 77 (8th Cir. 1975) stated:

        See also Britt v. Knight Publishing Co., 42 F.R.D. 593, 594 (D.S.C.1967). ("Under Rule 38 amendments or supplemental pleadings do not extend the time for making demand for jury trial except as to new issues raised by the new pleading,"); 5 Moore's Federal Practice, P 38.41 (2d ed. 1982). In the instant case the only new issues raised in the amended complaint are those issues which allege the particular acts and circumstances which would make NEGEA liable for Com/Energy's alleged breach of contract and fraud. Only a very limited part of the case could be heard before the jury. District courts in similar situations have exercised their discretion under Rule 39 and permitted the entire case to be decided by the jury. See Butterfield v. Crist, 52 F.R.D. 489 (E.D.Wis.1971). ("(G)iven the need for judicial efficiency ... in the exercise of discretion under Rule 39(b) their belated request should be granted.") However, there is no provision similar to Rule 39 in the Bankruptcy Rules, so this does not appear to be an option available to the bankruptcy court.

        Upon the foregoing, the jury trial demand is denied.


Summaries of

Matter of Energy Control Systems of the Midwest, Inc.

United States Bankruptcy Court, W.D. Wisconsin.
Oct 14, 1982
23 B.R. 696 (Bankr. W.D. Wis. 1982)
Case details for

Matter of Energy Control Systems of the Midwest, Inc.

Case Details

Full title:In the Matter of ENERGY CONTROL SYSTEMS OF THE MIDWEST, INC., Debtor…

Court:United States Bankruptcy Court, W.D. Wisconsin.

Date published: Oct 14, 1982

Citations

23 B.R. 696 (Bankr. W.D. Wis. 1982)
35 Fed. R. Serv. 2d 991