From Casetext: Smarter Legal Research

Linarello v. City University of New York

Appellate Division of the Supreme Court of New York, First Department
Apr 6, 2004
6 A.D.3d 192 (N.Y. App. Div. 2004)

Summary

finding that even if construction manager were third-party beneficiary of contracts requiring that it be named as additional insured on subcontractors' insurance policy, "that would simply mean that [construction manager] has standing to sue" subcontractors for failing to procure insurance as promised

Summary of this case from Nautilus Ins. Co. v. Jirsa Contruction Co.

Opinion

3312.

Decided April 6, 2004.

Order, Supreme Court, New York County (Marilyn Shafer, J.), entered April 2, 2003, which, in an action by an injured laborer against, inter alia, the construction site's construction manager, defendant/third-party plaintiff-appellant Morse Diesel, inter alia, (1) granted the motions of third-party defendants general liability insurers USFG and AEI for summary judgment declaring that their respective policies with third-party defendants subcontractors Westmont and Jagler, the latter plaintiff's employer, do not cover Morse Diesel as an additional insured, (2) denied in part Morse Diesel's cross motion for sanctions against Jagler for spoliation, and (3) denied Morse Diesel's cross motion for partial summary judgment on its cause of action against Jagler for contractual indemnification, unanimously modified, on the law and the facts, to preclude Jagler from denying receipt of Morse Diesel's June 1, 1998 memorandum, and to clarify that the indemnification provision in Jagler's contract with the Dormitory Authority may be enforceable depending on the outcome of the main action, and otherwise affirmed, without costs.

Lisa M. Comeau, for Plaintiffs.

Steven Z. Rosenzweig, for Defendant.

Kenneth Paganini, for Defendant/Third-Party Plaintiff-Appellant.

Joseph K. Molloy, for Third-Party Defendants-Respondents.

Dylan C. Braverman, for Third-Party Defendant.

Before: Tom, J.P., Saxe, Ellerin, Lerner, Gonzalez, JJ.


The indemnification clause in Jagler's contract with the site's owner, the State Dormitory Authority, invoked by Morse Diesel, provides that Jagler is to indemnify the owner and construction manager for any and all losses they sustain as a result of any or all injuries to any and all persons arising out of or occurring in connection with Jagler's work, excepting only injuries that arise out of faulty designs or the affirmative acts of the owner or construction manager committed with the intent to cause injury. Such clause indemnifies the owner and construction manager for their own negligence and therefore runs afoul of General Obligations Law § 5-322.1(1). We reject Morse Diesel's argument that the indemnification clause, at least to the extent it does not require Jagler to indemnify Morse Diesel for its own negligence, is saved by another clause providing that "[e]ach and every provision of law and clause required by law to be inserted in the Contract shall be deemed to be inserted therein." Such language is not equivalent to language in the indemnification clause itself limiting a subcontractor's indemnification obligation "to the extent permitted by law" ( see Itri Brick Concrete Corp. v. Aetna Cas. Sur. Co., 89 N.Y.2d 786, 795; Dutton v. Pankow Bldrs., 296 A.D.2d 321, lv denied 99 N.Y.2d 511).

An indemnification clause that runs afoul of General Obligations Law § 5-322.1(1) is enforceable in the event the indemnitee is found not negligent but nevertheless held vicariously liable to the plaintiff ( see Itri, 89 N.Y.2d at 795, n 5; Masciotta v. Morse Diesel Intl., 303 A.D.2d 309, 312). There being no finding that Morse Diesel was not negligent, the motion court should not have said, in denying Morse Diesel's motion for a conditional judgment of indemnification against Jagler, that the indemnification clause is unenforceable. Accordingly, we modify to clarify that the indemnification may be enforceable depending on the outcome of the main action.

Morse Diesel's motion for a conditional judgment of indemnification against Jagler ( see Masciotta, 303 A.D.2d at 310) was properly denied on the ground that Morse Diesel failed to demonstrate its freedom from negligence ( see Zeigler-Bonds v. Structure Tone, 245 A.D.2d 80, 81; Potter v. M.A. Bongiovanni, Inc., 271 A.D.2d 918, 919). As the motion court found, it appears that Morse Diesel had more than mere general supervisory authority, at least with respect to its subcontractor W. Property Resources, who was responsible for cleaning up debris and providing temporary protection around openings, and whose negligence in those respects may have contributed to the accident. In particular, there is evidence that Morse Diesel directed W. Property's work and supplied its equipment ( compare Masciotta, 303 A.D.2d at 312; Buccini v. 1568 Broadway Assoc., 250 A.D.2d 466, 468-469).

While Jagler's egregious destruction of its records pertaining to the project, including those that the court order had directed to be produced, hinders Morse Diesel's defense and third-party claims against Jagler, and therefore warrants a sanction, Morse Diesel is "not entirely bereft of evidence tending to establish [its] position" ( Cohen Bros. Realty v. Rosenberg Elec. Contrs., 265 A.D.2d 242, 244, lv dismissed 95 N.Y.2d 791), and the motion court therefore properly refused to strike Jagler's answer as too drastic a remedy. Jagler's destruction of its personnel records certainly makes it more difficult for Morse Diesel to locate two former Jagler employees who may have relevant knowledge, but Morse Diesel has not shown that it is unable to locate them. While it was a proper exercise of discretion to preclude Jagler from denying receipt of the Dormitory Authority's April 28, 1998 letter advising that Morse Diesel was the new construction manager, we modify so as to further preclude Jagler from denying receipt of Morse Diesel's June 1, 1998 memorandum confirming discussions that all certificates of insurance were to be revised so as to include Morse Diesel as an additional insured. The motion court's decision to postpone "the imposition of other appropriate sanctions" for Jagler's destruction of records was properly deferred until the trial.

By the plain terms of the policies issued by USFG and AEI to Westmont and Jagler, Morse Diesel is not an additional insured because it had no written contracts with Westmont and Jagler. Moreover, even if Morse Diesel were found to be a third-party beneficiary of Jagler's and Westmont's contracts with the Dormitory Authority ( but see Stainless, Inc. v. Employers Fire Ins. Co., 69 A.D.2d 27, 33-34 , affd 49 N.Y.2d 924), that would simply mean that Morse Diesel has standing to sue Jagler and Westmont for breach of the provisions in those contracts requiring that they procure insurance covering Morse Diesel as an additional insured. It would not mean that the policies should be rewritten to name Morse Diesel as an additional insured. Nor should USFG and AEI be estopped from denying that Morse Diesel is an additional insured on the basis of certificates of insurance naming Morse Diesel's predecessor construction manager as an additional insured. Assuming that such certificates are evidence of the existence of insurance ( but see American Ref-Fuel Co. v. Resource Recycling, 248 A.D.2d 420, 424 ), to be estopped USFG and AEI must have issued the certificates listing the predecessor with the intent of influencing Morse Diesel, and Morse Diesel must have relied on the certificates to its detriment ( see Bucon, Inc. v. Pennsylvania Mfg. Assn. Ins. Co., 151 A.D.2d 207, 210-211; see generally Werking v. Amity Estates, 2 N.Y.2d 43, 53; Waldman v. Cohen, 125 A.D.2d 116, 122). Morse Diesel makes no such showing. Accordingly, USFG and AEI were properly granted summary judgment declaring that they are not obligated to defend or indemnify Morse Diesel.

Morse Diesel's appellate request for summary judgment against Westmont and Jagler on the issue of their failure to procure insurance is improper. Morse Diesel sought no relief against Westmont before the motion court, and its motion against Jagler was based on grounds other than failure to procure insurance ( see Trokie v. York Preparatory School, 284 A.D.2d 129). Since the issue of Westmont's failure to procure insurance was not the subject of a motion before the motion court, Westmont's appellate request for summary judgment on that issue is also improper ( see Dunham v. Hilco Constr. Co., 89 N.Y.2d 425, 429-430).

THIS CONSTITUTES THE DECISION AND ORDER OF THE SUPREME COURT, APPELLATE DIVISION, FIRST DEPARTMENT.


Summaries of

Linarello v. City University of New York

Appellate Division of the Supreme Court of New York, First Department
Apr 6, 2004
6 A.D.3d 192 (N.Y. App. Div. 2004)

finding that even if construction manager were third-party beneficiary of contracts requiring that it be named as additional insured on subcontractors' insurance policy, "that would simply mean that [construction manager] has standing to sue" subcontractors for failing to procure insurance as promised

Summary of this case from Nautilus Ins. Co. v. Jirsa Contruction Co.

finding that even if construction manager were third-party beneficiary of contracts requiring that it be named as additional insured on subcontractors' insurance policy, "that would simply mean that [construction manager] ha[d] standing to sue" subcontractors for failing to procure insurance as promised

Summary of this case from Muss Dev., LLC v. Nationwide Ins. Co.

affirming the denial of the construction manager's motion for conditional judgment because it failed to show its freedom from negligence

Summary of this case from Lachs v. Best Buy Stores, Co., Inc.

In Linarello, 6 A.D.3d 192, 774 N.Y.S.2d 517, we affirmed an award of summary judgment declaring that two insurance carriers were not obligated to defend or indemnify a construction manager where their insureds had written contracts only with the site owner.

Summary of this case from Gilbane Bldg. Co. v. St. Paul Fire & Marine Ins. Co.

In Linarello, the First Department held that a construction.manager was not an additional insured under the additional insured endorsement because it did not enter into written contracts with the named insured subcontractors.

Summary of this case from Atl. Dev. Grp., LLC v. Interstate Fire & Cas. Co.

In Linarello, parties were denied additional insured status where the policy, as here, required written contracts, and those parties seeking additional insured status had no independent contracts with the policy-holding subcontractor (id. at 195).

Summary of this case from Doe Fund, Inc. v. Interstate Fire & Cas. Co.

In Linarello, the Appellate Division, First Department, addressing language identical to that in issue here, declined to extend coverage to parties with no written contracts with the insured, reasoning it would constitute an improper rewrite of the policy.

Summary of this case from Time Warner N.Y. Cable LLC v. Nova Cas. Co.

In Linarello, the appellate court considered language in a policy endorsement which is identical to that set forth above in Zurich's Form CG 20 33 07 04 herein.

Summary of this case from Murnane Bldg. Contractors, Inc. v. Zurich American Ins. Co.

In Linarello, the appellate court considered language in a policy endorsement which is identical to that set forth above in Zurich's Form CG 20 33 07 04 herein.

Summary of this case from Murnane Bldg. Contrs. v. Zurich Am. Ins. Co.
Case details for

Linarello v. City University of New York

Case Details

Full title:JOSEPH LINARELLO, ET AL., Plaintiffs, v. CITY UNIVERSITY OF NEW YORK…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Apr 6, 2004

Citations

6 A.D.3d 192 (N.Y. App. Div. 2004)
774 N.Y.S.2d 517

Citing Cases

Gilbane Bldg. Co. v. St. Paul Fire & Marine Ins. Co.

In this case, the “Additional Insured–By Written Contract” clause of the CGL policy provides additional…

Sicilia v. City of New York

However, a clause requiring a subcontractor to indemnify a general contractor or owner for injury to a worker…