From Casetext: Smarter Legal Research

Lake Construction Dev. v. City of New York

Appellate Division of the Supreme Court of New York, First Department
Jan 19, 1995
211 A.D.2d 514 (N.Y. App. Div. 1995)

Summary

In Lake, the contractor was denied recovery for the "extra work" actually performed; here, for the same failure to inspect the proposed work site, plaintiff may not claim entitlement to perform "extra work" in the first place.

Summary of this case from Seville Constr., v. Nycha

Opinion

January 19, 1995

Appeal from the Supreme Court, New York County (Alice Schlesinger, J.).


We find that the IAS Court, in granting summary judgment dismissing plaintiff's complaint seeking payment for extra or additional work plaintiff allegedly performed in completing brickwork on a public works contract, properly determined that there was no ambiguity in the parties' contract with respect to the brickwork required to complete the project, and that the plaintiff was barred from seeking additional compensation. Additionally, the IAS Court properly determined that plaintiff had failed to preserve its claim under the contract, for alleged extra work, by plaintiff's conceded failure to carefully examine the project work site and to seek clarification of any contractual ambiguities prior to bidding, as specifically required by the unambiguous provisions of the parties' contract (Acme Bldrs. v. Facilities Dev. Corp., 51 N.Y.2d 833; Savin Bros. v. State of New York, 62 A.D.2d 511, affd 47 N.Y.2d 934).

It is well settled that, on a motion for summary judgment, the construction of an unambiguous contract is a question of law for the court to pass on, and that circumstances extrinsic to the agreement or varying interpretations of the contract provisions will not be considered, where, as here, the intention of the parties can be gathered from the instrument itself (Mallad Constr. Corp. v. County Fed. Sav. Loan Assn., 32 N.Y.2d 285, 291).

Plaintiff's unilateral interpretation of the parties' contract to support its contention that there were actually two walls required to complete the project, rather than one wall which measured 972 square feet, as was estimated by the City engineer's cost estimate for the project, upon which the plaintiff admittedly relied in submitting its bid, was properly rejected by the IAS Court since the parties' contract unambiguously provided that the quantity of brickwork to be paid for under the contract "shall be based on the number of square feet of free-standing brickwall installed in accordance with the plans and specifications and directions of the Engineer". The mere assertion by a party that contract language is ambiguous is not, in and of itself, enough to raise a triable issue of fact precluding summary judgment (Bethlehem Steel Co. v. Turner Constr. Co., 2 N.Y.2d 456, 460; Olson Enters. v. Agway, Inc., 55 N.Y.2d 659, 661).

By seeking to modify its original bid and negotiate a more favorable agreement for itself, after it had already secured the contract as the low bidder, the plaintiff is, in effect, improperly attempting to secure an unfair competitive advantage over other legitimate bidders and to conduct the type of post-bid negotiation deemed violative of the practice of competitive bidding by the courts of this State (Sinram-Marnis Oil Co. v City of New York, 74 N.Y.2d 13, affg 139 A.D.2d 360, 365-366). We have reviewed the plaintiff's remaining claims and find them to be without merit.

Concur — Ellerin, J.P., Ross, Williams and Tom, JJ.


Summaries of

Lake Construction Dev. v. City of New York

Appellate Division of the Supreme Court of New York, First Department
Jan 19, 1995
211 A.D.2d 514 (N.Y. App. Div. 1995)

In Lake, the contractor was denied recovery for the "extra work" actually performed; here, for the same failure to inspect the proposed work site, plaintiff may not claim entitlement to perform "extra work" in the first place.

Summary of this case from Seville Constr., v. Nycha
Case details for

Lake Construction Dev. v. City of New York

Case Details

Full title:LAKE CONSTRUCTION DEVELOPMENT CORPORATION, Appellant, v. CITY OF NEW YORK…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Jan 19, 1995

Citations

211 A.D.2d 514 (N.Y. App. Div. 1995)
621 N.Y.S.2d 337

Citing Cases

Woodlands Commercial Bank v. State

First Judicial District Court, Carson City; James E. Wilson, Judge. Having considered the parties' arguments…

Mayo v. Mktropolitan Opera Ass'n, Inc.

the intention of the parties can be gathered from the instrument itself.'" Maysek & Moran, Inc. v S.G.…