From Casetext: Smarter Legal Research

Lackawanna Mills v. Weil

Appellate Division of the Supreme Court of New York, First Department
Oct 1, 1897
21 App. Div. 492 (N.Y. App. Div. 1897)

Opinion

October Term, 1897.

B.F. Einstein, for the appellants.

A.A. Spear, for the respondent.



One ground relied upon by the appellants for the reversal of the judgment is that the learned trial judge erred in denying the motion to dismiss the complaint at the close of the plaintiff's case. The merits of this position necessarily involve an examination of the facts as to whether or not, as contended by the defendants, the plaintiff defaulted in the performance of its contract on June 1, 1891, and failed to give notice to the defendants of readiness to perform within a reasonable time after August 5, 1891.

It appeared upon the trial that on May 12, 1891, the plaintiff sent to the defendants an invoice of the 1,800 dozen, amounting to $16,200, and thereafter delivered to the defendants eight cases, the last two on August 19, 1891; that on July 2, 1891, the plaintiff wrote the defendants that they had packed and stored at the mill, subject to their order, the fifty-seven cases which were then undelivered. A controversy arose between the parties as to whether or not the goods which had been delivered corresponded to the terms of sale. The defendants claimed that the shirts and drawers were sold by sample and upon the agreement that they should correspond to similar goods manufactured by the plaintiff for the defendants and delivered in 1890 under No. 423, and that the goods did not correspond to the sample or to No. 423 in the respect, among others, that the shirts and drawers of No. 423 had four-hole pearl buttons, and that those of No. 424, which are the goods in controversy, had two-hole buttons. On August 5, 1891, the parties had a conference, the result of which was that the plaintiff allowed the defendants sixty dollars in settlement of the claim for wrong buttons on four cases which had been delivered between June 22 and August 1, 1891; and it was agreed that the 840 dozen of shirts then undelivered should be altered so as to have four-hole instead of two-hole buttons.

The question whether this was a gratuitous engagement on the part of the plaintiff, or was undertaken as the result of reasonable objections of the defendants, based upon the fact that there was a difference between the goods sought to be delivered and those required by the contract, was, among others, referred by the learned trial court to the jury. Upon the plaintiff's evidence, however, as it stood at the close of the case when the motion to dismiss was made, it was not so favorable to the defendants that the judge would have been justified in granting the motion; because, in addition to what appeared, as already cited, it was also shown that the goods were all manufactured, packed and ready for delivery in February, 1891; that they were invoiced to the defendants May 12, 1891; that the contract required that they should be ready for delivery June 1, 1891, and should be actually delivered in small lots as ordered by the defendants after that date, and should be paid for June tenth. On July second, as already stated, notice was given to the defendants that the goods were stored subject to their order. The defendants seemed to recognize the correctness of this procedure by repeatedly ordering those goods shipped, and in the Lampman order of August nineteenth they direct the plaintiff to ship "cases that you are holding, `subject to our order' as under noted."

On August fifth the difference had been settled, and the only change made in the original contract was that in regard to the change of buttons; and that for the moment may be considered as a modification of the contract. All the goods shipped after August fifth had changed buttons, and all the goods ordered by the defendants had either been actually delivered or tendered, and none were returned. Finally, although they had received goods on August fourteenth and nineteenth, and had not returned them, they refused to receive or admit into their store goods ordered on the nineteenth which were tendered to them on August twenty-fifth. There is evidence tending to show that, at the time of this tender and refusal to receive, the buttons had all been changed, the testimony being that within one or two days after Lampman's visit to the mills on August nineteenth, all the changes as to buttons had been made. However this may be, the rejection of these goods without examination was at the defendants' risk. If such goods corresponded with the requirements of the contract, such refusal to receive constituted a breach on the defendants' part, which made it unnecessary for the plaintiff to make any further tender. It was not required to ship all the remaining cases from Scranton to New York for the purpose of offering them to the defendants so that they might reject them. It was sufficient that the goods were ready for delivery and stored subject to the defendants' orders.

In Van Sickle v. Nester (34 Hun, 64) the rule is well stated in the following language: "If the plaintiff drew to the defendant a load of barley and tendered it upon the contract, and the barley in all respects corresponded with that required by the terms of the contract, and the defendant refused to accept it, it cannot be that the rule is that the plaintiff must continue day after day to draw other loads to the defendant and have them refused until he has drawn and tendered the whole amount required by the contract. Such a rule would be a hardship and unjust. The defendant, by refusing to accept, was guilty of a breach of the contract, and this breach dispensed with the necessity of the plaintiff's offering to deliver the rest. If there had been no breach of the contract on the part of the defendant, if the barley was not of the quality required by the contract, then he had a right to refuse to accept, and it would then have been the duty of the plaintiff to have purchased and delivered other barley. But upon this question the evidence is conflicting. It was submitted to the jury, and the jury have found in favor of the plaintiff." (See, also, Canda v. Wick, 100 N.Y. 127; Howe v. Moore, 37 N.Y. St. Repr. 736.)

Upon the question of the plaintiff's ability or willingness to perform, there was in the case, at the time the motion was made, evidence from which the jury might infer, as they subsequently did, that the plaintiff delivered or offered all goods ordered by the defendants, by having the balance called for by the contract in storage subject to the defendants' orders, the stored goods being, as the jury have determined, up to the requirements of the contract. Had the defendants changed their minds subsequent to August twenty-fifth and become willing to accept goods, they should have communicated that change of mind to the plaintiff by at least sending an order for more goods.

The question of law of course arises, not as to the right of the plaintiff to recover at all, not as to the right to go to the jury upon the question of the amount of damages, but as to when the payment became due, so as to set the interest running; and this is to be determined by the consideration of whether the plaintiff is entitled to recover upon the original contract, or such contract as modified by the agreement of August fifth; or, as held by the learned trial judge, whether the recovery should be for the balance due upon the entire contract, with interest from July 1, 1891, the date of the last payment. The date of payment, however, is not controlling upon the motion to dismiss, this latter requiring us to review the evidence with a view to determining whether there was sufficient testimony from which the jury could properly infer that the plaintiff was entitled to recover. We think, as did the learned trial judge, that there was ample evidence, and that it would have been error to grant the motion to dismiss. And upon the question of the plaintiff's right to recover upon the whole case, it could not have been stated in any fuller or clearer way than in the charge of the learned trial judge, wherein he told the jury: "Now, if you find that the goods which the plaintiff had ready for delivery on June 1, 1891, did, in fact, correspond to goods No. 423 of 1890, both with regard to the buttons and general workmanship, this question of subsequent alteration would not be material, since the plaintiff's offer to alter them would have been merely gratuitous; but if the original contract required four-hole buttons on both the shirts and drawers, and after the defendants had given the plaintiff an opportunity to correct the defect in the goods, it did correct the defect only in the shirts, there would then have been a breach of contract upon the plaintiff's part, and it could not recover. But, again, if the contract only called for four-hole buttons on the shirts, and the plaintiff did remedy the defect in this regard, under an agreement with the defendants, which called for no further alteration, and tendered the goods so altered within the time allowed by this modification of the contract, then there would have been a fulfillment by the plaintiff, and, if the goods were otherwise correct, the defendants could not claim a breach of contract because the buttons were not satisfactory on June 1st, the original date for delivery."

The trial judge thus clearly distinguished the different aspects of the case, depending upon the view which the jury might take of the evidence, and left it for them to determine, upon the conflicting evidence, the question as to when the payment became due. If the plaintiff was not in fault and had in all respects complied with the contract, and if the goods which it had completed and held subject to the defendants' order were, in respect to the buttons and general workmanship, in accordance with the contract, and if the plaintiff then subsequently agreed, with a view of avoiding any dispute and of buying its peace, to comply with the defendants' demand in reference to changing the buttons, and after that, the defendants without right and unreasonably refused to accept, the jury might well infer that their position was not one of good faith, and that they were seeking an excuse to recede from their contract, and in that event, there being no failure of the plaintiff to perform, it was entitled to receive payment according to the terms of the contract, so that in that aspect fixing July first as the date did not injure the defendants.

Under the terms of the contract the goods were to be ready for delivery on June 1, 1891, and, if required by the defendants, were to be actually delivered to them in the city of New York within a few days thereafter. The date of payment for the goods was fixed by the contract for June 10, 1891. It follows that if the goods had been ready for delivery on June first, payment would have become due and enforcible on June tenth. If, however, we conclude that an honest difference of opinion arose as to whether the goods were equal in quality of workmanship to those ordered, and that this difference was adjusted by the modified agreement of August fifth, it would follow that, as the goods were to be changed with respect to the buttons, and as such change was not made until some days after August nineteenth, the date of payment would be fixed by the time when the plaintiff was ready to deliver the goods as provided in the modified agreement. Assuming, therefore, as the jury had a right to do, that the goods tendered and refused on August twenty-fifth were in all respects up to the terms of the contract, and that on that date all the changes had been made in the balance of the goods, that, it seems to us, should be the date when payment for the goods became due. For, in the language of the opinion upon the former appeal (78 Hun, 348), "under its contract with the defendants, full performance on its part was to precede payment by the defendants."

It will thus be seen that we do not agree in the view taken by the appellants, that the learned trial judge erred in charging the jury as follows: "Now, if you find that these goods as offered on August 25th were actually in accordance with the requirements of the contract as originally made, or as subsequently modified, both in regard to the general workmanship and the form of the buttons, then there was a proper offer of delivery by the plaintiff, and the defendants' refusal to accept these ten cases constituted a breach of contract upon their part such as excused the plaintiff from making any further offer of the goods." In view of this charge, which we think was right, it is difficult to understand how the learned judge fell into the error of fixing the date when payment was due as of July first, which, as he says, was the time the last payment was made by the defendants to the plaintiff. Concluding, as we do, therefore, that the date when payment for the goods became due was not July first, but August twenty-fifth, it will make a difference in interest, and to that extent the judgment should be modified.

It is true that, by their answer and in support of their counterclaims, the defendants sought to show that the words "Delivery June 1st, 1891," meant absolute delivery on that date, and that the failure so to deliver to the defendants in New York is fatal to any recovery as of such date. Upon the trial, however, it was testified by one of the plaintiff's witnesses, without objection or exception, that the words "Delivery June 1st, 1891," meant that the goods were to be baled up and ready for delivery on the first of June, at the option of the buyer; and this testimony is enforced by the interpretation given to the contract by the parties themselves with respect to the delivery of the goods, because none were actually delivered until the latter part of June, and all deliveries were made as ordered from time to time up to August 19, 1891. The question, however, as to the meaning of these words was submitted to the jury, and their verdict sustained the plaintiff's contention that actual delivery of the goods on June first was not contemplated.

The appellants insist that notice of the completion of the contract and the readiness of the plaintiff to perform should have been given within a reasonable time after August 5, 1891. While we may assent to this as a proposition of law, we cannot, for the reasons already stated, agree with the view taken by the appellants of the evidence, that the only notice that the plaintiff gave was on June 28, 1894, nearly three years after the contract was modified, because the failure of the defendants to receive the goods on August 26, 1891, absolved the plaintiff from the necessity of making any further tender. Of course there was a conflict as to whether defendants were justified in refusing to accept, but this has been resolved by the jury adversely to them.

It would unnecessarily extend this opinion to refer to the numerous exceptions taken by the defendants to the rulings upon evidence and to the charge of the judge, it being sufficient to say that we have examined them and find them wanting in that force which requires this court to set aside a judgment entered upon a verdict which was rendered by the jury after a protracted trial, and after every question was fully and fairly presented by the judge in his charge, and in a manner as favorable to the defendants as they had a legal right to demand.

We think that, with the modification suggested (allowing interest from August 25, 1891, instead of from the date allowed in the computation by the jury), the judgment should be affirmed, without costs.

VAN BRUNT, P.J., WILLIAMS, PATTERSON and INGRAHAM, JJ., concurred.

Judgment modified as directed in opinion, and affirmed as modified, without costs.


Summaries of

Lackawanna Mills v. Weil

Appellate Division of the Supreme Court of New York, First Department
Oct 1, 1897
21 App. Div. 492 (N.Y. App. Div. 1897)
Case details for

Lackawanna Mills v. Weil

Case Details

Full title:THE LACKAWANNA MILLS, Respondent, v . SAMUEL WEIL and Others, Composing…

Court:Appellate Division of the Supreme Court of New York, First Department

Date published: Oct 1, 1897

Citations

21 App. Div. 492 (N.Y. App. Div. 1897)
47 N.Y.S. 585