Kim v. Truck Corp.

Appellate Division of the Supreme Court of New York, Second Department
Feb 1, 2011
81 A.D.3d 586 (N.Y. App. Div. 2011)

Opinion

No. 2010-00611.

February 1, 2011.

In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals from so much of a judgment of the Supreme Court, Queens County (Kitzes, J.), entered December 18, 2009, as, upon the granting of the defendants' motion pursuant to CPLR 4401 for a judgment as a matter of law, made at the close of the plaintiffs case, is in favor of the defendants and against him dismissing the complaint.

Meyer, Suozzi, English Klein, P.C., Garden City, N.Y. (Robert N. Zausmer of counsel), for appellant.

Richard Yoon (Malvina Nathanson, New York, N.Y., of counsel), for respondents.

Before: Florio, J.P., Dickerson, Chambers and Lott, JJ.


Ordered that the judgment is affirmed insofar as appealed from, with costs.

Contrary to the plaintiffs contention, the Supreme Court properly dismissed his cause of action alleging breach of contract. The parol evidence rule precluded the plaintiff from introducing evidence of an alleged oral agreement, which allegedly contradicted and varied the terms of the parties' subsequent written contract ( see Harris v Hallberg, 36 AD3d 857).

The plaintiff's remaining contentions are without merit.


Summaries of

Kim v. Truck Corp.

Appellate Division of the Supreme Court of New York, Second Department
Feb 1, 2011
81 A.D.3d 586 (N.Y. App. Div. 2011)
Case details for

Kim v. Truck Corp.

Case Details

Full title:DONG WON KIM, Appellant, v. FRANK H. TRUCK CORPORATION et al., Respondents

Court:Appellate Division of the Supreme Court of New York, Second Department

Date published: Feb 1, 2011

Citations

81 A.D.3d 586 (N.Y. App. Div. 2011)
2011 N.Y. Slip Op. 640
917 N.Y.S.2d 869

Citing Cases

NRT New York, LLC v. Laffey

In opposition, the appellants failed to raise a triable issue of fact as to whether the plaintiff breached…

Lopez v. Volkswagen

“It is well settled that a contract is to be construed in accordance with the parties' intent, which is…