From Casetext: Smarter Legal Research

Hong v. Renval Constr.

Supreme Court of New York, Second Department
Aug 9, 2023
219 A.D.3d 593 (N.Y. App. Div. 2023)

Opinion

2021–06581 Index No. 603634/19

08-09-2023

Jack HONG, appellant, v. RENVAL CONSTRUCTION, LLC, et al., defendants, Steven Cestaro, respondent.

Roseman, Beerman & Beerman, LLP (Sweetbaum & Sweetbaum, Lake Success, NY [Jackie L. Gross and Joel A. Sweetbaum ], of counsel), for appellant.


Roseman, Beerman & Beerman, LLP (Sweetbaum & Sweetbaum, Lake Success, NY [Jackie L. Gross and Joel A. Sweetbaum ], of counsel), for appellant.

HECTOR D. LASALLE, P.J., BETSY BARROS, VALERIE BRATHWAITE NELSON, ROBERT J. MILLER, JJ.

DECISION & ORDER In a stakeholder's interpleader action, in effect, pursuant to CPLR 1006, the plaintiff appeals from an order of the Supreme Court, Nassau County (Christopher G. Quinn, J.), dated August 11, 2021. The order denied the plaintiff's motion for summary judgment dismissing the counterclaim of the defendant Steven Cestaro to recover on a promissory note.

ORDERED that the order is affirmed, without costs or disbursements.

The plaintiff and the defendant Renval Construction, LLC (hereinafter Renval) entered into a joint venture agreement for the purchase, renovation, and sale of certain real property. Prior to completion of the project, Renval and its principal, the defendant Renato Busljeta, obtained a loan of $200,000 from the defendant Steven Cestaro and executed a promissory note. The note was secured by an "Assignment of Contract Proceeds" (hereinafter the Assignment), which was signed by the plaintiff, among others. The Assignment provided, inter alia, that the sums due pursuant to the note would be "immediately paid from the proceeds of [the] sale [of the subject property]."

Following a dispute regarding the sale price of the property, the plaintiff and Renval entered into arbitration, resulting in an award in favor of Renval in the amount of $85,876.84, which represented Renval's share of the proceeds of the sale of the subject property. The plaintiff then commenced this stakeholder's interpleader action, in effect, pursuant to CPLR 1006, alleging that he was subject to conflicting claims for the funds of the arbitration award. Cestaro counterclaimed for payment of the outstanding sums due under the note. The plaintiff moved for summary judgment dismissing Cestaro's counterclaim. In an order dated August 11, 2021, the Supreme Court denied the motion, finding the terms of the Assignment ambiguous as to whether the plaintiff may be liable to Cestaro for payment of the sums due under the note. The plaintiff appeals.

"When the language of a contract is ambiguous, its construction presents a question of fact that may not be resolved by the court on a motion for summary judgment" ( Shadlich v. Rongrant Assoc., LLC, 66 A.D.3d 759, 760, 887 N.Y.S.2d 228 ; see Sabre Real Estate Group, LLC v. JQ1 Assoc., LLC, 204 A.D.3d 1051, 1052, 165 N.Y.S.3d 336 ; Five Corners Car Wash, Inc. v. Minrod Realty Corp., 134 A.D.3d 671, 672, 20 N.Y.S.3d 578 ). "A contract is ambiguous if the terms are susceptible to more than one reasonable interpretation" ( Archstone v. Tocci Bldg. Corp. of N.J., Inc., 101 A.D.3d 1062, 1064, 956 N.Y.S.2d 499 ; see Evans v. Famous Music Corp., 1 N.Y.3d 452, 458, 775 N.Y.S.2d 757, 807 N.E.2d 869 ). Contrary to the plaintiff's contention, an ambiguity exists as to whether the Assignment provided that the plaintiff may be liable for the sums due on the note to the extent of the proceeds from the sale of the property. Moreover, the plaintiff did not establish as a matter of law the parties’ intent as it relates to the competing interpretations of the Assignment based on either the four corners of the parties’ agreement or any extrinsic evidence submitted (see Sabre Real Estate Group, LLC v. JQ1 Assoc., LLC, 204 A.D.3d at 1053, 165 N.Y.S.3d 336 ; New Plan of Hillside Vil., LLC v. Surrette, 108 A.D.3d 512, 513, 969 N.Y.S.2d 122 ; Dobbs v. North Shore Hematology–Oncology Assoc., P.C., 106 A.D.3d 771, 772, 965 N.Y.S.2d 520 ).

The plaintiff's remaining contention is improperly raised for the first time on appeal. Accordingly, the Supreme Court properly denied the plaintiff's motion for summary judgment dismissing Cestaro's counterclaim.

LASALLE, P.J., BARROS, BRATHWAITE NELSON and MILLER, JJ., concur.


Summaries of

Hong v. Renval Constr.

Supreme Court of New York, Second Department
Aug 9, 2023
219 A.D.3d 593 (N.Y. App. Div. 2023)
Case details for

Hong v. Renval Constr.

Case Details

Full title:Jack Hong, appellant, v. Renval Construction, LLC, et al., defendants…

Court:Supreme Court of New York, Second Department

Date published: Aug 9, 2023

Citations

219 A.D.3d 593 (N.Y. App. Div. 2023)
194 N.Y.S.3d 541
2023 N.Y. Slip Op. 4196

Citing Cases

Szklarz v. Racer

"When the language of a contract is ambiguous, its construction presents a question of fact that may not be…

Underhill Venture, LLC v. Sarang

. Moreover, the contract is ambiguous as to whether the defendants' alleged failure to pay for certain extras…