From Casetext: Smarter Legal Research

Grandfeld II, LLC v. Kohl's Dep't Stores, Inc.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Jul 18, 2018
163 A.D.3d 782 (N.Y. App. Div. 2018)

Opinion

2016–01279 Index No. 22962/09

07-18-2018

GRANDFELD II, LLC, respondent-appellant, v. KOHL'S DEPARTMENT STORES, INC., et al., appellants-respondents.

Pillsbury Winthrop Shaw Pittman LLP, New York, NY (E. Leo Milonas and Jay D. Dealy of counsel), for appellants-respondents. Somer Heller & Corwin, LLP (Michael C. Marcus, New York, NY, of counsel), for respondent-appellant.


Pillsbury Winthrop Shaw Pittman LLP, New York, NY (E. Leo Milonas and Jay D. Dealy of counsel), for appellants-respondents.

Somer Heller & Corwin, LLP (Michael C. Marcus, New York, NY, of counsel), for respondent-appellant.

REINALDO E. RIVERA, J.P., SHERI S. ROMAN, SYLVIA O. HINDS-RADIX, LINDA CHRISTOPHER, JJ.

DECISION & ORDER

In an action, inter alia, to recover damages for breach of a lease, the defendants appeal, and the plaintiff cross-appeals, from a judgment of the Supreme Court, Suffolk County (Elizabeth H. Emerson, J.), entered December 7, 2015. The judgment, insofar as appealed from, upon a decision on the issue of liability of the same court dated February 4, 2013, and upon a decision on the issue of damages of the same court dated July 13, 2015, made after a single nonjury trial, is in favor of the plaintiff and against the defendants in the total sum of $5,726,102.32. The judgment, insofar as cross-appealed from, awarded the plaintiff damages in the total sum of only $5,726,102.32.

ORDERED that the judgment is affirmed insofar as appealed and cross-appealed from, without costs or disbursements.

In June 2009, the plaintiff commenced this action alleging that the defendants breached a "ground lease" (hereinafter the lease) dated October 17, 2003, whereby the defendants agreed to, among other things, build and operate a department store on the plaintiff's property located in the Town of Brookhaven. The lease contemplated an initial term of 20 years, with 5–year renewal options, and that, at the end of the lease, the plaintiff would take ownership of the building. The lease also provided that if certain contingencies were not met, either party could terminate the lease by giving written notice to the other party, whereupon neither party would have any further liability or obligation.

After the plaintiff, on May 23, 2008, satisfied the condition of obtaining zoning approval, the defendants were required to use commercially reasonable efforts to obtain governmental approvals within six months. The lease defined governmental approvals as "all land use approvals and other approvals which, in [the defendants'] reasonable discretion, may be necessary for the construction and operation of the Building, including, without limitation, zoning variances, site plan approvals, building permits, access and utility easements, side yard agreements and other necessary or required approvals of the Building." The defendants retained various firms to assist them in obtaining the governmental approvals and, on October 24, 2008, a building permit was issued by the Town of Brookhaven. However, the defendants did not commence construction and instead, by letter dated January 21, 2009, notified the plaintiff that they were terminating the lease because the defendants had not obtained all governmental approvals. The defendants referred to their failure to obtain a New York State Highway Work Permit from the New York State Department of Transportation (hereinafter the DOT permit).

During a nonjury trial, the plaintiff presented evidence showing that the DOT permit was not required until construction was nearly complete, at or near the time that the application for the certificate of occupancy was to be submitted. Additionally, both parties presented testimony from real estate appraisers on the issue of the amount of damages sustained by the plaintiff as a result of the termination of the lease. The Supreme Court determined that the defendants breached the lease, resulting in damages to the plaintiff in the total sum of $5,726,102.32, and entered judgment accordingly. The defendants appeal, and the plaintiff cross-appeals, from the judgment.

"In reviewing a determination made after a nonjury trial, the power of the Appellate Division is as broad as that of the trial court, and this Court may render the judgment it finds warranted by the facts, taking into account in a close case that the trial judge had the advantage of seeing the witnesses" ( ProHealth Care Assoc., LLP v. Shapiro, 46 A.D.3d 792, 793, 849 N.Y.S.2d 276 ; see Campbell v. Campbell, 107 A.D.3d 929, 930, 966 N.Y.S.2d 906 ; Dilapi v. Empire Drilling & Blasting, Inc., 62 A.D.3d 936, 937, 880 N.Y.S.2d 115 ).

When parties set down their agreement in a clear, complete document, their writing should be enforced according to its terms (see W.W.W. Assoc. v. Giancontieri, 77 N.Y.2d 157, 162, 565 N.Y.S.2d 440, 566 N.E.2d 639 ). This principle is particularly important in the context of real property transactions, where commercial certainty is a paramount concern, and where the instrument was negotiated between sophisticated, counseled business people negotiating at arm's length (see Madison Ave. Leasehold, LLC v. Madison Bentley Assoc., LLC, 8 N.Y.3d 59, 66, 828 N.Y.S.2d 254, 861 N.E.2d 69 ; Vermont Teddy Bear Co. v. 538 Madison Realty Co., 1 N.Y.3d 470, 475, 775 N.Y.S.2d 765, 807 N.E.2d 876 ). A contract provision requiring the exercise of "reasonable discretion" includes a promise not to act arbitrarily, irrationally, or without reasonable basis (see ProSource Technologies, LLC v. Housing Trust Fund Corp., 49 Misc.3d 1205[A], 2015 WL 5797028 [Sup. Ct., Albany County]; see also Dalton v. Educational Testing Serv., 87 N.Y.2d 384, 389, 639 N.Y.S.2d 977, 663 N.E.2d 289 ; Tedeschi v. Wagner Coll., 49 N.Y.2d 652, 659, 427 N.Y.S.2d 760, 404 N.E.2d 1302 ; Legend Autorama, Ltd. v. Audi of Am., Inc., 100 A.D.3d 714, 716, 954 N.Y.S.2d 141 ; Richbell Info. Servs. v. Jupiter Partners, 309 A.D.2d 288, 302, 765 N.Y.S.2d 575 ).

In this case, it was unreasonable for the defendants to consider the DOT permit a governmental approval that had to be obtained for construction to commence, as it was not necessary until the near completion of construction. The defendants' contention that the DOT permit was a governmental approval within the meaning of the lease, since it was necessary for the operation of the building, would render meaningless the six-month time limitation to obtain such governmental approvals (see Nomura Home Equity Loan, Inc., Series 2006–FM2 v. Nomura Credit & Capital, Inc., 30 N.Y.3d 572, 69 N.Y.S.3d 520, 92 N.E.3d 743 ; CNR Healthcare Network, Inc. v. 86 Lefferts Corp., 59 A.D.3d 486, 489, 874 N.Y.S.2d 174 ). A contract should be read as a whole, with every part interpreted with reference to the whole; if possible, the contract will be interpreted so as to give effect to its general purpose (see Beal Sav. Bank v. Sommer, 8 N.Y.3d 318, 324, 834 N.Y.S.2d 44, 865 N.E.2d 1210 ; Excess Ins. Co. Ltd. v. Factory Mut. Ins. Co., 3 N.Y.3d 577, 582, 789 N.Y.S.2d 461, 822 N.E.2d 768 ; Matter of Westmoreland Coal Co. v. Entech, Inc., 100 N.Y.2d 352, 358, 763 N.Y.S.2d 525, 794 N.E.2d 667 ). Here, the general purpose of the lease was to set forth the chronological steps for the construction and operation of the store. Once the defendants obtained the governmental approvals necessary to commence construction, they could not terminate the lease on the ground that additional governmental approvals would be required in the future when construction was nearly complete (cf. Prince–Vomvos v. Winkler Real Estate, Inc., 140 A.D.3d 1043, 1045, 35 N.Y.S.3d 186 ; Newfield v. General Motors Corp., 84 A.D.2d 548, 549, 443 N.Y.S.2d 239, affd 56 N.Y.2d 818, 452 N.Y.S.2d 570, 438 N.E.2d 103 ; Mec–Guy Realty Corp. v. Amerada Hess Corp., 69 A.D.2d 812, 813, 415 N.Y.S.2d 54 ). Thus, we agree with the Supreme Court's finding that the defendants breached the lease. If we accepted the defendants' contention that the governmental approvals necessary for construction and operation of the building include approvals that could be obtained at or near the time of an application for a certificate of occupancy, then the inability to obtain a certificate of occupancy—which can only be obtained after completion of construction—could be used as a basis for avoiding the defendants' responsibility to commence construction. Such an interpretation of the contract would be a plainly unreasonable result (see Brown Bros. Elec. Contrs. v. Beam Constr. Corp., 41 N.Y.2d 397, 400, 393 N.Y.S.2d 350, 361 N.E.2d 999 ).

The lease provides that, in the event of the defendants' default, the plaintiff is entitled to "the discounted net present value of the balance of the annual fixed rent for the remainder of the Term minus the then fair market rental value of the Premises for the remainder of the Term." The defendants contend that the Supreme Court should have adopted the fair market rental valuation of their expert, and the plaintiff asserts that the court should have adopted the discount rate of its expert. As valuation is largely a question of fact, trial courts have considerable discretion in reviewing the relevant evidence (see White v. Farrell, 20 N.Y.3d 487, 500, 964 N.Y.S.2d 467, 987 N.E.2d 244 ; Matter of Consolidated Edison Co. of N.Y., Inc. v. City of New York, 8 N.Y.3d 591, 597, 838 N.Y.S.2d 458, 869 N.E.2d 634 ; W.T. Grant Co. v. Srogi, 52 N.Y.2d 496, 510, 438 N.Y.S.2d 761, 420 N.E.2d 953 ). We agree with the court's determination to adopt the analysis of the plaintiff's expert regarding fair market rental value, but to apply the discount rate of the defendants' expert (see Matter of W.O.R.C. Realty Corp. v. Board of Assessors, 100 A.D.3d 75, 91, 951 N.Y.S.2d 36 ; Saccone v. Gross, 84 A.D.3d 1208, 1209, 923 N.Y.S.2d 878 ).

The Supreme Court's determination that the defendants breached the lease, resulting in damages in the total sum of $5,726,102.32, is amply supported by the evidence adduced at trial and warranted by the facts, and we discern no basis to disturb the judgment (see Northern Westchester Professional Park Assoc. v. Town of Bedford, 60 N.Y.2d 492, 499, 470 N.Y.S.2d 350, 458 N.E.2d 809 ; Family Operating Corp. v. Young Cab Corp., 129 A.D.3d 1016, 1018, 12 N.Y.S.3d 213 ; White v. Guerrera, 50 A.D.3d 779, 779, 854 N.Y.S.2d 648 ).

The parties' remaining contentions are without merit.

RIVERA, J.P., ROMAN, HINDS–RADIX and CHRISTOPHER, JJ., concur.


Summaries of

Grandfeld II, LLC v. Kohl's Dep't Stores, Inc.

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department
Jul 18, 2018
163 A.D.3d 782 (N.Y. App. Div. 2018)
Case details for

Grandfeld II, LLC v. Kohl's Dep't Stores, Inc.

Case Details

Full title:Grandfeld II, LLC, respondent-appellant, v. Kohl's Department Stores…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Second Judicial Department

Date published: Jul 18, 2018

Citations

163 A.D.3d 782 (N.Y. App. Div. 2018)
163 A.D.3d 782
2018 N.Y. Slip Op. 5289

Citing Cases

Kaplan v. Kaplan

. "A contract should be read as a whole, with every part interpreted with reference to the whole; if…

Thomas & Betts Corp. v. Trinity Meyer Util. Structures

The words "subject to" in Section 6.2 cannot be said to be "unmistakable language" creating a condition…