From Casetext: Smarter Legal Research

Graciano Corp. v. Lanmark Grp.

Supreme Court of New York, First Department
Nov 14, 2023
221 A.D.3d 473 (N.Y. App. Div. 2023)

Opinion

1002-, 1003 Index No. 652750/14 Case Nos. 2023-00896, 2023-00898

11-14-2023

GRACIANO CORPORATION, Plaintiff–Respondent, v. LANMARK GROUP, INC., et al., Defendants–Appellants. Lanmark Group, Inc., Third–Party Plaintiff–Appellant, v. Liberty Mutual Insurance Company, Third–Party Defendant–Respondent.

Cullen and Dykman LLP, Garden City (Jean–Pierre Van Lent of counsel), for appellants. Marco Law, PLLC, Manhasset (George A. Marco of counsel), for respondents.


Cullen and Dykman LLP, Garden City (Jean–Pierre Van Lent of counsel), for appellants.

Marco Law, PLLC, Manhasset (George A. Marco of counsel), for respondents.

Kapnick, J.P., Singh, Moulton, Shulman, Rosado, JJ.

Judgment, Supreme Court, New York County (Joel M. Cohen, J.), entered September 27, 2022, awarding plaintiff Graciano Corporation damages against defendants, unanimously affirmed, without costs. Appeal from order (denominated a decision), same court and Justice, entered August 12, 2022, which, insofar as appealed from as limited by the briefs, after a nonjury trial, found in favor of Graciano on its cause of action for breach of contract and its cause of action for monies due under the terms of a payment bond, dismissed the counterclaim for breach of contract asserted by defendant Lanmark Group, Inc. and dismissed Lanmark's third-party complaint, unanimously dismissed, without costs, as subsumed in the appeal from the judgment. In this breach of contract action, Graciano seeks to recover damages for breach of a subcontract between it and Lanmark, the general contractor on a project to restore a public school in Brooklyn. Under the terms of the subcontract, Graciano was to provide the masonry work for the project. The main issue at trial was whether Lanmark's issuance of "Addendum 3," which purported to "delete" certain work, constituted a "cardinal change" to the subcontract, or whether Graciano's election to treat the subcontract as abandoned constituted a breach.

After trial, Supreme Court properly found that Lanmark's issuance of Addendum No. 3 constituted a "cardinal change" — that is, a change that affected "the essential identity or main purpose of the contract, such that it constitutes a new undertaking" — and thus was an abandonment of the subcontract ( Matter of Tutor Perini Corp. v. City of N.Y. Off. of Admin. Trials & Hearings Contract Dispute Resolution Bd., 193 A.D.3d 665, 666, 148 N.Y.S.3d 64 [1st Dept. 2021], lv denied 38 N.Y.3d 903, 2022 WL 839554 [2022] [internal quotation marks omitted]). Although the contract permitted Lanmark to "delete" or "modify" Graciano's scope of work, the evidence supported the court's finding that the extensive deletions to the scope of work set forth in Addendum No. 3 alter the essential identity of the contract (see id. ; see also Del Balso Constr. Corp. v. City of New York, 278 N.Y. 154, 160, 15 N.E.2d 559 [1938] ). Lanmark did not make these deletions out of necessity; on the contrary, Lanmark's corporate secretary conceded that Graciano was not in default, and that all of the deleted work remained outstanding and was ultimately performed by Lanmark's own workforce.

Despite defendants’ position otherwise, this Court's decision on a prior appeal did not find as a matter of law that there was no cardinal change. Rather, this Court affirmed the dismissal of Graciano's quantum meruit claim solely based on the legal point that "a valid and enforceable written contract governed the subject matter at issue, and, therefore, recovery in quasi contract for events arising out of the same subject matter is precluded" ( Graciano Corp. v. Lanmark Group, Inc., 184 A.D.3d 435, 436, 125 N.Y.S.3d 98 [1st Dept. 2020], citing Parker Realty Group, Inc. v. Petigny, 14 N.Y.3d 864, 865–866, 903 N.Y.S.2d 325, 929 N.E.2d 387 [2010] ). Furthermore, in specifically addressing the "cardinal change" issue, we found simply that Supreme Court had properly denied Lanmark's motion for summary judgment on its counterclaim for breach of contract, as "issues of fact exist[ed] as to whether Lanmark's issuance of Addendum No. 3 breach[ed] ... a fundamental obligation of the contract, relieving [Graciano] from the effect of the no damages for delay clause" ( Graciano Corp., 184 A.D.3d at 435, 125 N.Y.S.3d 98 [internal quotation marks omitted]). Supreme Court correctly declined to enforce the no-damages-for-delay clause based on its finding that Lanmark fundamentally breached its contractual obligations. Among other things, the court's fact findings, which were supported by abundant evidence, established that Lanmark failed to substantially fulfill its express contractual obligation to schedule and coordinate the work on the project, resulting in extensive work interruptions or delays (see Corinno Civetta Constr. Corp. v. City of New York, 67 N.Y.2d 297, 309, 502 N.Y.S.2d 681, 493 N.E.2d 905 [1986] ; Clifford R. Gray, Inc. v. City School Dist. of Albany, 277 A.D.2d 843, 845, 716 N.Y.S.2d 795 [3d Dept. 2000] ).

Supreme Court also properly rejected Lanmark's reliance on article 8.1 of the contract, which addresses change orders and requires strict compliance as a condition precedent to recovery by Graciano. With respect to Graciano's claim for recovery on an acceleration change order, the condition precedent in article 8.1 does not apply to that claim because the condition pertains to only notice of extra work and the acceleration change order was effectively a notice of delay (see Gemma Constr. Co. v. City of New York, 246 A.D.2d 451, 456, 668 N.Y.S.2d 195 [1st Dept. 1998] ). With respect to Graciano's claim regarding the proposed window kerf change order, Graciano's noncompliance with the condition precedent as to that change order is excusable because Lanmark effectively consented to operating outside of the subcontract's technical requirements as to that work ( DeGraw Constr. Group, Inc. v. HPDC2 Hous. Dev. Fund Co., Inc., 189 A.D.3d 405, 406, 137 N.Y.S.3d 8 [1st Dept. 2020] ). Indeed, rather than denying the proposal, Lanmark restated Graciano's position when submitting the proposal to the New York City School Construction Authority, under whose auspices the restoration project was undertaken (see id. at 405, 137 N.Y.S.3d 8 ; cf. Huff Enters. v. Triborough Bridge & Tunnel Auth., 191 A.D.2d 314, 317, 595 N.Y.S.2d 178 [1st Dept. 1993], lv denied 82 N.Y.2d 655, 602 N.Y.S.2d 804, 622 N.E.2d 305 [1993] ).

We reject defendants’ contention that plaintiff failed to comply with the conditions precedent in articles 3.4 and 3.5. The language at issue in those articles — for example, a provision stating that Graciano's failure to provide timely notice of delays "MAY be sufficient cause" for Lanmark to deny a schedule change — did not express conditions precedent. In fact, the language in those articles is not conditional at all, much less unmistakably conditional (see VXI Lux Holdco S.A.R.L. v. SIC Holdings, LLC, 171 A.D.3d 189, 194–195, 98 N.Y.S.3d 1 [1st Dept. 2019] ).

We have considered defendants’ remaining arguments, including that Supreme Court made certain errors in assessing damages, and find them unavailing.


Summaries of

Graciano Corp. v. Lanmark Grp.

Supreme Court of New York, First Department
Nov 14, 2023
221 A.D.3d 473 (N.Y. App. Div. 2023)
Case details for

Graciano Corp. v. Lanmark Grp.

Case Details

Full title:Graciano Corporation, Plaintiff-Respondent, v. Lanmark Group, Inc., et…

Court:Supreme Court of New York, First Department

Date published: Nov 14, 2023

Citations

221 A.D.3d 473 (N.Y. App. Div. 2023)
198 N.Y.S.3d 62
2023 N.Y. Slip Op. 5703

Citing Cases

Lein Realty Corp. v. Weinfeld

, triable issues of fact concerning the alleged breach of contract would preclude an award of summary…