From Casetext: Smarter Legal Research

Fraser v. Baybrook Building Co.

Court of Appeals of Texas, First District, Houston
Jun 12, 2003
No. 01-02-00290-CV (Tex. App. Jun. 12, 2003)

Summary

In Fraser, the Court citedCVN Group for the proposition that a contractor may secure a valid mechanic's lien against a homestead on which work was performed if the constitutional and statutory procedures set forth in Article 16, Section 50 of the Constitution and Section 53.254 of the Property Code are followed.

Summary of this case from Cavazos v. Munoz

Opinion

No. 01-02-00290-CV.

June 12, 2003.

Appeal from the 212th District Court, Galveston County, Texas, Trial Court Cause No. 99CV0688.

Panel consists of Justices HEDGES, JENNINGS, and ALCALA.


MEMORANDUM OPINION


Appellants George and Beth Fraser (the Frasers) sued Baybrook Building Company, Inc. (Baybrook) for breach of contract, fraud, conversion, trespass, violations of the Texas Residential Construction Disclosure Statement, and violations of the Texas Deceptive Trade Practices Act (DTPA) in connection with a contract to construct a house. Baybrook counterclaimed for breach of contract, breach of the duty of good faith and fair dealing, unjust enrichment, and tortious interference with the construction contract. Baybrook also claimed a lien on the house and sought judicial foreclosure. A jury found in favor of Baybrook and awarded $81,551 in actual damages and $35,000 in attorney's fees, and the trial court ordered judicial foreclosure on Baybrook's lien to satisfy the judgment.

Tex. Bus. Comm. Code Ann. § 17.41-.63 (Vernon 2002).

In seven issues, the Frasers contend that the evidence was factually insufficient to support two of the jury's findings and that the trial court erred by declining to submit a proper jury instruction on damages, ordering a judicial foreclosure on an invalid lien, allowing the proceeds of the foreclosure sale to secure attorney's fees awarded to Baybrook, and declining to award attorney's fees to the Frasers. We modify the judgment and affirm as modified.

Factual Procedural Background

On June 11, 1998, the Frasers entered into an agreement with Baybrook to have a house built in Galveston County. The plans for the house were drawn up by the Frasers and called for a construction material known as "Rastra" and for steel wall supports, trusses, and roofing shingles. The Frasers hired Saaduddin Ahmed to engineer the plans. Under the proposal, Baybrook agreed to furnish the materials and labor necessary to complete the contemplated construction. Thereafter, on August 7, 1998, Baybrook entered into a mechanic's and materialman's lien contract with the Frasers by which Baybrook agreed to complete construction by July 31, 1999. The Frasers negotiated a loan with Colonial Savings (Colonial) in the amount of $259,500 to secure Baybrook's services.

After experiencing several delays, Baybrook was unable to complete construction by the July 1999 deadline. The Frasers sued Baybrook, seeking damages for the loss of a loan commitment at a favorable interest rate, the cost of completing the construction in a good and workmanlike manner, mental anguish, diminished market-value of the property, and attorney's fees. Baybrook counterclaimed, seeking damages for the unpaid balance due under the contract, interest on the unpaid balance, and attorney's fees. The case was tried to a jury.

The jury found that (1) Baybrook complied with its proposal with the Frasers, (2) Baybrook did not complete construction of the house in a good and workmanlike manner, (3) Baybrook's failure to complete construction in a good and workmanlike manner was not the proximate cause of the Frasers' damages, (4) the Frasers were not entitled to recover attorney's fees, (5) Baybrook substantially performed under the June 11, 1998 proposal, (6) Baybrook was entitled to recover $81, 551 under the June 11, 1998 proposal, and (7) Baybrook was entitled to recover $35,000 in attorney's fees. The trial court entered judgment in accordance with the jury's findings and ordered judicial foreclosure of Baybrook's mechanic's and materialman's lien to satisfy the judgment. The Frasers subsequently filed this appeal.

Factual Sufficiency

In their sixth and seventh issues, the Frasers argue that the judgment should be reversed because the evidence was factually insufficient to support the jury's findings that (1) Baybrook complied with the June 11, 1998 proposal and (2) Baybrook's failure to complete construction in a good and workmanlike manner was not the proximate cause of the Frasers' damages.

We will sustain a factual sufficiency challenge only if, after viewing all the evidence, the evidence is so weak or the verdict so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986). As we examine the evidence, we remain mindful that the jury is the sole judge of witness credibility and the weight to be given testimony. McGalliard v. Kuhlmann, 722 S.W.2d 694, 697 (Tex. 1986). The jury may believe one witness and disbelieve another and resolve inconsistencies in any testimony. Id. This Court cannot substitute its opinion for that of the trier of fact or determine that it would have weighed the evidence differently or reached a different conclusion. Hollander v. Capon, 853 S.W.2d 723, 726 (Tex.App.-Houston [1st Dist.] 1993, writ denied).

A. Compliance Under the June 11, 1998 Proposal

Seventeen witnesses testified at trial. There was some testimony that (1) the house was not completed in a timely manner, (2) the house failed inspection, (3) the house had various construction problems, and (4) the Frasers were forced to hire additional contractors to correct and complete Baybrook's faulty work. The Frasers contend that this testimony established that Baybrook did not comply with the June 11, 1998 proposal.

Other testimony, however, reflects that (1) the Frasers prevented Baybrook from obtaining a final inspection on the house, (2) the Frasers would not allow Baybrook to install a water heater in accordance with the Frasers' design, (3) the Frasers prevented Baybrook from obtaining a gas permit, (4) the Frasers discharged Baybrook before it could complete construction, (5) the Frasers prevented Baybrook from passing the final inspection of the house, (6) Baybrook "basically finished" construction on the house, and (7) problems existed with the Frasers' house design calling for "Rastra" in combination with a steel truss system. Baybrook contends that this testimony established that any faulty construction resulted from the Frasers' substandard plans and their interference with Baybrook's completing the house.

In finding that Baybrook complied with the June 11, 1998 proposal, the jury reconciled the divergent views from a variety of witnesses. We decline to circumvent the jury's role as the sole judge of witness credibility and the weight to accord testimony in order to arrive at a different result. See McGalliard, 722 S.W.2d at 697. After reviewing the record, we hold that the evidence that Baybrook complied with the June 11, 1998 proposal was not so weak or the jury's verdict so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain, 709 S.W.2d at 176.

We overrule issue six.

B. Proximate Cause of the Frasers' Damages

In issue seven, the Frasers contend that the evidence at trial was factually insufficient to support the jury's finding that, although Baybrook did not complete construction in a good and workmanlike manner, this failure did not proximately cause the Frasers' damages. The Frasers reiterate here the same arguments that were raised in their previous factual-sufficiency challenge. For the reasons stated above, we reject these arguments.

We overrule issue seven.

Jury Instruction on Damages

In their fifth issue, the Frasers contend that the trial court erred by not including an instruction on the proper measure of damages in the charge to the jury. To preserve error based on an omitted instruction in a jury charge, a party must object to the charge and tender a substantially correct instruction to the trial court. Mason v. Southern Pac. Transp. Co., 892 S.W.2d 115, 117 (Tex.App.-Houston [1st Dist.] 1994, writ denied). The Frasers neither objected to the charge nor submitted a written instruction to the trial court. Their complaint is therefore waived on appeal. Tex.R.App.P. 33.1.

We overrule issue five.

Mechanic's and Materialman's Lien

In their first and second issues, the Frasers contend that the trial court erred in ordering judicial foreclosure on Baybrook's mechanic's and materialman's lien. The Frasers assert that the lien was invalid because it did not adhere to constitutional and statutory prerequisites for perfecting a lien on a homestead. See Tex. Const. art. XVI, § 50(a)(5); Tex. Prop. Code Ann. §§ 53.001-.260 (Vernon Supp. 2003). Alternatively, the Frasers contend that, to the extent Baybrook did perfect a lien on the homestead, Baybrook cannot enforce the lien because it was assigned to Colonial.

Baybrook does not contest that the Frasers' house is a "homestead" under Texas law. See Tex. Const. art. XVI, § 50.

Baybrook contends that the mechanic's and materialman's lien contract entered into on August 7, 1998 created a valid lien on the Frasers' homestead. Under that contract, Baybrook agreed to construct a residence on the Frasers' property. In exchange for Baybrook's services, the Frasers executed a $259,500 mechanic's lien note, naming Baybrook as payee. Furthermore, the contract provided:

This Mechanic's Lien Contract is made . . . between the undersigned owner [the Frasers] and Contractor [Baybrook] and provides for a transfer of lien to Colonial Savings, F.A.

In addition, paragraph 5 of the contract states:

5. Assignment of Mechanic's Lien Contract. In consideration of Lender's [Colonial's] advance of all or a portion of the Contract Price, Contractor hereby transfers and assigns to Lender . . . all of Contractor's rights and liens in this Contract and Lender is subrogated to all the rights and equities of Contractor.

A review of the August 7, 1998 contract shows that any liens Baybrook may have acquired through that contract were assigned to Colonial in exchange for Colonial's commitment to provide interim construction financing. Baybrook was free to assign any rights or liens it acquired under the contract. See State Farm Fire Cas. Co. v. Gandy, 925 S.W.2d 696 (Tex. 1996). Irrespective of whether the lien satisfies the constitutional and statutory prerequisites to perfecting a lien on a homestead, we hold that Baybrook did not possess a mechanic's and materialman's lien because it assigned any liens it may have acquired under the August 7, 1998 contract to Colonial, thus giving Colonial the exclusive right to foreclose on the liens.

Baybrook has pointed us to no other document in the record that would establish a valid mechanic's and materialman's lien on the Frasers' homestead. Because Baybrook relies on the August 7, 1998 contract as its sole basis in claiming lienholder status, and because Baybrook assigned its liens under that contract to Colonial, we hold that the trial court erred in ordering judicial foreclosure on a mechanic's and materialman's lien that Baybrook did not possess and, therefore, could not enforce.

We sustain issues one and two. Because we sustain these issues, we need not address the Frasers' third issue, which challenges the trial court's allowing the proceeds of the foreclosure sale to secure attorney's fees awarded to Baybrook.

Attorney's Fees

In their fourth issue, the Frasers contend that the trial court erred by declining to award their claim for attorney's fees. The Frasers assert that, because they were entitled to judgment as a matter of law, and because they are a prevailing party, they must be awarded attorney's fees. See Tex. Civ. Prac. Rem. Code Ann. § 38.001 (Vernon Supp. 2003); Tex. Bus. Comm. Code Ann. § 17.50(d).

The Frasers have not shown how or why they were entitled to judgment as a matter of law and, therefore, have not shown that they prevailed in this lawsuit. Thus, we hold that the trial court did not err by declining to award attorney's fees to the Frasers.

We overrule issue four.

Conclusion

We modify the judgment of the trial court by deleting all portions that order judicial foreclosure of a mechanic's and materialman's lien in favor of Baybrook. We affirm the judgment as modified.


Summaries of

Fraser v. Baybrook Building Co.

Court of Appeals of Texas, First District, Houston
Jun 12, 2003
No. 01-02-00290-CV (Tex. App. Jun. 12, 2003)

In Fraser, the Court citedCVN Group for the proposition that a contractor may secure a valid mechanic's lien against a homestead on which work was performed if the constitutional and statutory procedures set forth in Article 16, Section 50 of the Constitution and Section 53.254 of the Property Code are followed.

Summary of this case from Cavazos v. Munoz
Case details for

Fraser v. Baybrook Building Co.

Case Details

Full title:GEORGE AND BETH FRASER, Appellants v. BAYBROOK BUILDING CO., INC., Appellee

Court:Court of Appeals of Texas, First District, Houston

Date published: Jun 12, 2003

Citations

No. 01-02-00290-CV (Tex. App. Jun. 12, 2003)

Citing Cases

Rochelle v. Travis Servs. Grp.

CVN Grp., Inc. v. Delgado, 47 S.W.3d 157, 164 (Tex. App.-Austin 2001), rev'd on other grounds, 95 S.W.3d 234…

Cavazos v. Munoz

This court's reading of the Austin Court of Appeals' decision inCVN Group is bolstered by an unpublished…