Fort Walton Beach Lincoln-Mercury, Inc. v. Pearson

District Court of Appeal of Florida, First District
May 14, 1999
731 So. 2d 859 (Fla. Dist. Ct. App. 1999)

Summary

reversing and remanding summary judgment in favor of plaintiff because the undisputed facts and the law of contracts showed that defendant was entitled to summary judgment

Summary of this case from United Servs. Auto. Ass'n v. Velez

Opinion

No. 98-1579

Opinion filed May 14, 1999.

An appeal from the Circuit Court for Okaloosa County, Judge Jack R. Heflin.

John H. Fleming, Patricia B. Cunningham, and Ann G. Fort of Sutherland, Asbill Brennan LLP, Atlanta, and Dean Bunch of Sutherland, Asbill Brennan LLP, Tallahassee, for Appellant.

Steven B. Bauman and James W. Grimsley of Smith, Grimsley, Bauman, Pinkerton, Petermann Wells, Fort Walton Beach, and Barbara E. Pusch, Fort Walton Beach, Attorney Pro Hac Vice, and Kenneth L. Funderburk, Phenix City, Alabama, Attorney Pro Hac Vice, for Appellee.


This is an appeal from an order granting summary judgment in favor of plaintiff/appellee Gary J. Pearson, and denying the summary judgment motion of appellant Fort Walton Beach Lincoln-Mercury, Inc. (FWBLM), in a suit arising out of the termination of Pearson's dealership/management agreements with Ford Motor Company and its subsidiaries. We reverse and remand for entry of summary judgment in favor of FWBLM.

The facts of this case are summarized in our previous opinion, Pearson v. Ford Motor Co., 694 So.2d 61 (Fla. 1st DCA 1997).

Notwithstanding Pearson's technical arguments, which we find to be without merit, this record demonstrates that there is no dispute with regard to the material facts: Pearson's management agreement was effectively terminated at the FWBLM board meeting on February 26, 1991; Pearson was given actual, albeit oral, notice at that meeting that the agreement was terminated; FWBLM never gave him written notice of termination, as required by the management agreement; following the aforesaid board meeting, the parties acted in a manner which indicated that the agreement was terminated; Pearson's monthly salary at the time of the termination was $5,500; under the termination provision of the management agreement, FWBLM gave him a check for $7,618.87 on March 12, 1991, which he endorsed and cashed the next day; and Pearson did not raise the argument that FWBLM breached the management agreement by failing to give him written notice and by failing to pay him under the termination provision until suit was filed in circuit court nearly four years later. Applying the law of contracts to these undisputed facts, we find that by his actions following the aforesaid FWBLM board meeting, Pearson waived the contractual requirement of written notice.

See Mark v. Hahn, 177 So.2d 5 (Fla. 1965) (waiver of a contractual condition "may be inferred from conduct or acts putting one off his guard and leading him to believe that a right has been waived); Torres v. K-Site 500 Associates, 632 So.2d 110 (Fla. 3d DCA 1994) ("A party may waive any rights to which he or she is legally entitled, by actions or conduct warranting an inference that a known right has been relinquished"); American Somax Ventures v. Touma, 547 So.2d 1266 (Fla. 4th DCA 1989) (failure to give written notice of extensions of the closing date on a home purchase agreement was waived through the conduct of the purchasers);Crosslands Properties, Inc. v. Univest Crossland Trace, Ltd., 516 So.2d 320 (Fla. 2d DCA 1987) (under some circumstances, "written contracts can be modified by subsequent oral agreement of the parties, even though the written contract purports to prohibit such modification"); Arbogast v. Bryan, 393 So.2d 606 (Fla. 4th 1981) (plaintiff waived strict compliance with a contractual agreement regarding payment of his commissions where he "voiced no objection for over six years"); Ferslew v. Relaford, 351 So.2d 368 (Fla. 1st DCA 1977) (landlord waived strict performance of the lease contract when she "failed to complain of any of the alleged defaults within a reasonable time"). See also, Little Beaver Enterprises v. Humphreys Railways, Inc., 719 F.2d 75 (4th Cir. (Va.) 1983) (a vessel owner was not barred from recovering from a ship repairer for breach of express warranty because of the vessel owner's failure to comply with a contractual 30-day written notice requirement, because the ship repairer had actual notice and acted upon it);Canada v. Allstate Ins. Co., 411 F.2d 517 (5th Cir. (Fla.) 1969) (failure to give an insurance agent written notice of termination did not entitle him to recover commissions on policy renewals after the agent accepted severance pay and indicated that his employment had been terminated).

The summary judgment for Pearson is REVERSED and the case is REMANDED to the trial court for entry of summary judgment for FWBLM on count X of the complaint.

VAN NORTWICK and PADOVANO, JJ., CONCUR.


Summaries of

Fort Walton Beach Lincoln-Mercury, Inc. v. Pearson

District Court of Appeal of Florida, First District
May 14, 1999
731 So. 2d 859 (Fla. Dist. Ct. App. 1999)

reversing and remanding summary judgment in favor of plaintiff because the undisputed facts and the law of contracts showed that defendant was entitled to summary judgment

Summary of this case from United Servs. Auto. Ass'n v. Velez
Case details for

Fort Walton Beach Lincoln-Mercury, Inc. v. Pearson

Case Details

Full title:FORT WALTON BEACH LINCOLN-MERCURY, INC., Appellant, v. GARY J. PEARSON…

Court:District Court of Appeal of Florida, First District

Date published: May 14, 1999

Citations

731 So. 2d 859 (Fla. Dist. Ct. App. 1999)

Citing Cases

United Servs. Auto. Ass'n v. Velez

Because there were no material facts in dispute and because Velez had put forth neither opposition to USAA's…