From Casetext: Smarter Legal Research

Fed. Energy Regulatory Comm'n v. Etracom LLC

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF CALIFORNIA
Mar 7, 2017
No. 2:16-cv-01945-SB (E.D. Cal. Mar. 7, 2017)

Opinion

No. 2:16-cv-01945-SB

03-07-2017

FEDERAL ENERGY REGULATORY COMMISSION, Plaintiff, v. ETRACOM LLC, and MICHAEL ROSENBERG, Defendant.


ORDER REGARDING SCOPE OF REVIEW

The parties dispute the scope of review and the applicable procedural rules in this matter. The Court ordered simultaneous briefing regarding the scope of the Court's de novo review pursuant to the Federal Power Act. ECF No. 19. For the reasons discussed herein, the Court holds that the Federal Rules of Civil Procedure (FRCP) apply to this action brought pursuant to Federal Power Act § 31(d)(3), 16 U.S.C. § 823b(d)(3).

Background

A preliminary statement of the facts is as follows. ETRACOM LLC (ETRACOM) is a financial trading firm founded and principally owned by Michael Rosenberg (Rosenberg), which trades financial products in the wholesale energy market operated by the California independent System Operator Corporation (CAISO). The Federal Energy Regulatory Commission (FERC or "the Commission") began an investigation in to an allegedly fraudulent scheme perpetrated by Respondents in 2011. During the investigation FERC's Office of Enforcement (Enforcement) obtained and reviewed thousands of pages of documents, analyzed hundreds of thousands of electricity trades, and took sworn testimony of Rosenberg and an ETRACOM contractor. Ultimately, Enforcement determined that Respondents engaged in an unlawful scheme to manipulate the CAISO market. On December 16, 2015, FERC issued an Order to Show Cause, thus initiating an administrative proceeding. Five days later, Enforcement filed with FERC the documents produced by ETRACOM and third parties during the investigation, as well as non-public CAISO market data and Enforcement's analyses of ETRACOM's trades.

Pursuant to the Commission's Order to Show Cause, Respondents were given two options for contesting Enforcement's findings: Option 1, a formal public hearing on the record before an ALJ, and Option 2, a streamlined proceeding under which if FERC concludes that a penalty is appropriate, the Commission must consider the seriousness of the violation and the efforts of Respondents to remedy the violation in a timely manner. Respondents elected for Option 2. Subsequently, Respondents requested discovery and asked FERC to require CAISO to disclose information regarding relevant market design flaws and software pricing/modeling errors. The Commission denied the motion because Respondents rejected the opportunity for a formal ALJ proceeding under Option 1.

Based on the administrative record and the parties' submissions, FERC issued an 82-page Order Assessing Civil Penalties against Respondents on June 17, 2016. Accordingly, FERC assessed civil penalties of $2.4 million against ETRACOM and of $100,000 against Rosenberg. ETRACOM was also ordered to disgorge unjust profits of $315,072 plus applicable interest. Because Respondents have yet to pay the civil penalties assessed, FERC instituted this action in the District Court for the Eastern District of California on August 17, 2016. ECF No. 1. Respondents answered the Complaint on October 17, 2016. ECF No. 16. FERC then filed a Motion to Affirm Civil Penalties Assessed by FERC on December 1, 2016. ECF No. 17. The parties, however, disputed this Court's scope of review. ECF No. 15. The Court ordered briefing regarding the scope of review and applicable procedural rules. ECF No. 19. FERC contends that this Court's review is limited to the administrative record, and the Court must review the administrative record "de novo," i.e., as standing in the shoes of the Commission. Respondents contend that the FRCP apply to this action, that they are entitled to discovery, and that this Court reviews the entire record non-deferentially.

Analysis

The FPA governs this action. FPA § 31(d) provides two pathways by which a civil penalty may be imposed. The default Option 1 provides that once FERC provides notice of its proposed penalty,

the Commission shall assess the penalty, by order, after a determination of violation has been made on the record after an opportunity for an agency hearing pursuant to [5 U.S.C. § 554] before an administrative law judge . . . . Such assessment order shall include the administrative law judge's findings and the basis for such assessment . . . . Any person against whom a penalty is assessed under this paragraph may . . . institute an action in the United States court of appeals for the appropriate judicial circuit for judicial review of such order in accordance with chapter 7 of title 5. The court shall have jurisdiction to enter a judgment affirming, modifying, or setting aside in whole or in [p]art, the order of the Commission, or the court may remand the proceeding to the Commission for such further action as the court may direct.
16 U.S.C. § 823b(d)(1). Option 1 "describes a traditional form ofjudicial review of agency action, based on the record developed in an agency proceeding, which is familiar to administrative law." FERC v. City Power Marketing, LLC, No. 15-1428(JDB), 2016 WL 4250233 (Aug. 10, 2016 D.D.C.). Alternatively, Option 2 provides an expedited process for assessing civil penalties:
(A) In the case of any civil penalty with respect to which the procedures of this paragraph have been elected, the Commission shall promptly assess such penalty, by order, after the date of the receipt of the notice . . . of the proposed penalty.

(B) If the civil penalty has not been paid within 60 calendar day . . . , the Commission shall institute an action in the appropriate district court of the United States for an order affirming the assessment of the civil penalty. The court shall have authority to review de novo the law and the facts involved, and shall have jurisdiction to enter a judgment enforcing, modifying, and enforcing as so modified, or setting aside in whole or in [p]art such assessment.
16 U.S.C. § 823b(d)(3). "FERC has consistently interpreted Option 2 as not requiring any procedural protections prior to the penalty assessment, but it exercises its discretion to provide certain protections to avoid the perception of unfairness." FERC v. Maxim Power Corp., No. 15-30113-MGM, 2016 WL 4126378 (D. Mass. July 21, 2016). Respondents contend that they are entitled to discovery pursuant to the FRCP under Option 2.

Federal Rule of Civil Procedure 1

The Court begins its analysis with Fed. R. Civ. P. 1, which provides that the FRCP "govern the procedure in all civil actions and proceedings in the United States district courts, except as stated in Rule 81." It is undisputed that Rule 81 is inapplicable to this case. Because Congress authorized the promulgation of the FRCP, they "apply by their own force to all litigants before the court," and apply with "full force" to the United States Government. Mattingly v. United States, 939 F.2d 816, 818 (9th Cir. 1991). The Court can only decline to apply the FRCP "if the Rule in question transgresses the terms of the Rules Enabling Act or the Constitution." United States v. Orr Water Ditch Co., 391 F.3d 1077, 1082 (9th Cir. 2004). The only exception to the universal application of the FRCP is where Congress has allowed for summary proceedings "expressly authorized by statute." SEC v. McCarthy, 322 F.3d 650, 655 (9th Cir. 2003). For this exception to apply, there must be a "clear expression of congressional intent to exempt actions" from the FRCP. Califano v. Yamasaki, 442 U.S., 682, 700 (1979).

The FPA does not explicitly make the FRCP inapplicable to a proceeding in a United States district court under FPA § 31(d)(3). Rather, FPA § 31(d)(3) provides that where, as here, Respondent does not pay the assessed civil penalty within 60 days of assessment, the Commission shall institute a civil action in the appropriate district court. As the Ninth Circuit has noted, "[t]he word 'action' in its usual legal sense means 'a suit brought in a court; a formal complaint within the jurisdiction of a court of law,' and 'includes all the formal proceedings in a court of justice attendant upon the demand of a right . . . in such court." Cann v. Carpenters' Pension Trust Fund for N. Cal., 989 F.2d 313, 316 (9th Cir. 1993) (quoting Black's Law Dictionary 26 (5th ed. 1983)). The Court finds no clear expression of congressional intent to exempt actions pursuant to FPA § 31(d)(3), Option 2, from the application of the FRCP. Accordingly, the FRCP apply by their own force to this matter.

Legislative History Demonstrates FRCP Apply to Option 2 Proceedings

Moreover, the legislative history of similar federal statutes demonstrates congressional intent that the FRCP would apply to Option 2 proceedings under the FPA. The Court is directed to "interpret similar language in the same way." Shirk v. United States ex rel. Dept. of Interior, 773 F.3d 999, 1004 (9th Cir. 2014). Similar language in federal statutes is indicative of congressional intent for that statutory language to share a common meaning. See Northcross v. Bd. Of Ed. of Memphis City Sch., 412 U.S. 427, 428 (1973).

Congress has enacted two-path adjudicatory options, such as at issue here, in other contexts. For example, in 1978, Congress enacted the National Energy Conservation Policy Act, Pub. L. No. 95-619, 92 Stat. 3206 (1978) (NECPA), and provided for the assessment of civil penalties under a two-path track. NECPA § 423 (codified at 42 U.S.C. § 6303). The Option 2 language of the NECPA is identical to that contained in FPA § 31(d)(3). NECPA § 432(d)(3). In so doing, Congress recognized that, in assessing civil penalties under Option 2 of the NECPA, the "Administrator would issue a penalty order on the basis of the evidence before him but without a hearing and file a petition in district court seeking a judgment assessing the civil penalty." ECF No. 21-11. After penalty assessment, "[t]he court will consider the violation and the amount of the assessment as a de novo proceeding applying all the normal Federal Rules of Procedure and Evidence." Id.

Congress enacted the Powerplant and Industrial Fuel Use Act, Pub. L. No. 95-620, title VII, § 723, Nov. 9, 1978, 92 Stat. 3289, 3333 (codified at 42 U.S.C. § 8433(d)) (PIFUA), in the same year that it enacted NECPA, with identical two-path language for civil penalty assessment. The legislative history likewise demonstrates that an Option 2 proceeding under the PIFUA involves a de novo proceeding in which "all normal federal rules of procedure and evidence" apply. ECF No. 21-12. The legislative history of the NECPA and PIFUA clearly demonstrate that the FRCP are intended to apply to Option 2 proceedings under those statutes. Because this Court must interpret similar language in a similar way, the Court interprets FPA § 31(d)(3) to provide the procedural protections contemplated by Congress when it enacted Option 2 of the NECPA and PIFUA. Accordingly, the FRCP apply to this action under Option 2 of FPA § 31(d).

Federal District Courts Consistently Apply FRCP to Option 2 Proceedings

Other federal district courts to decide the issue have likewise held that there is no clear expression of congressional intent in the FPA to depart from the FRCP under Option 2 penalty assessment proceedings. See Maxim Power Corp., 2016 WL 4126378; City Power Marketing, LLC, 2016 WL 4250233; FERC v. Silkman, No. 1:16-cv-00205-JAW, 2017 WL 374697 (Jan. 26, 2017 D. Me.). Each of these courts rejected the very arguments proffered by FERC in this case to hold that the FRCP apply to an action brought pursuant to FPA § 31(d)(3). Those cases proceeded as standard civil actions. While not binding authority, the reasoning set forth by the Maxim Power Corp., City Power Marketing, and Silkman courts is highly persuasive. For these reasons, the Court concludes that the FRCP apply to this action.

Accordingly, IT IS HEREBY ORDERED THAT:

1. The Federal Rules of Civil Procedure shall govern this action.

2. Pursuant to 16 U.S.C. § 823b(d)(3), the Court shall review the penalty order issued by the FERC de novo both as to the facts and the law.

3. The parties are encouraged to either stipulate to a discovery schedule or request a discovery conference with the Court.

IT IS SO ORDERED. The Clerk of Court is directed to enter this Order and forward copies to counsel.

DATED this 7th day of March, 2017.

/s/_________

Stanley A. Bastian

United States District Judge


Summaries of

Fed. Energy Regulatory Comm'n v. Etracom LLC

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF CALIFORNIA
Mar 7, 2017
No. 2:16-cv-01945-SB (E.D. Cal. Mar. 7, 2017)
Case details for

Fed. Energy Regulatory Comm'n v. Etracom LLC

Case Details

Full title:FEDERAL ENERGY REGULATORY COMMISSION, Plaintiff, v. ETRACOM LLC, and…

Court:UNITED STATES DISTRICT COURT EASTERN DISTRICT OF CALIFORNIA

Date published: Mar 7, 2017

Citations

No. 2:16-cv-01945-SB (E.D. Cal. Mar. 7, 2017)

Citing Cases

Fed. Energy Regulatory Comm'n v. Powhatan Energy Fund, LLC

To date, five federal district courts have decided the issue. Fed. Energy Regulatory Comm'n v. Barclays Bank…