PROCEDURAL HISTORY

Action for a judgment declaring the plaintiff's rights in certain real property, brought to the Superior Court in the judicial district of New Haven at Meriden, where the court, DiPentima, J., granted the defendant's motion for summary judgment and rendered judgment thereon, from which the plaintiff appealed to this court. Affirmed.

James M. Miele, for the appellant (plaintiff).

Robert N. Reynolds, Jr., for the appellee (defendant).


OPINION


The plaintiff, Dalton Enterprises, Inc., appeals from the summary judgment rendered in favor of the defendant, Boston Maine Corporation. The plaintiff sought a declaratory judgment giving it an easement by prescription over certain land belonging to the defendant. On appeal, the plaintiff claims that the trial court improperly determined that General Statutes § 47-27 barred the plaintiff from acquiring a prescriptive easement over the defendant's property. We affirm the judgment of the trial court.

General Statutes § 47-27 provides: "Title by adverse possession by or against railroad and railway companies. No length of possession, user or occupancy of land belonging to a railroad or street railway corporation and used for its corporate purposes shall create or continue any right in or to such land. No length of possession, user or occupancy by a railroad or street railway corporation of land belonging to another shall create or continue any right in or to such land."

The plaintiff owns land in Cheshire adjacent to land owned by the defendant, a railroad corporation. Until November, 1994, the defendant's affiliate, the Springfield Terminal Company, operated a railroad on the land owned by the defendant. Since November, 1994, the railway on this land has remained inactive.

The trial court held that § 47-27 applied to bar the plaintiff from adversely possessing the disputed parcel during the period from 1965 to 1994 when the defendant railway company used the property for its corporate purpose. Given this statutory bar, the trial court determined that the plaintiff's adverse possession of the disputed parcel did not commence until November, 1994, when the defendant ceased to use the property for its corporate purpose, and, that accordingly, the action was premature.

The plaintiff does not dispute the fact that, prior to the discontinuance of operation of the railway on the disputed parcel in 1994, the property was being used for the defendant's corporate purpose. Further, the defendant does not dispute the fact that since the discontinuance of operation of the railway in 1994, the disputed parcel has not been used for its corporate purpose.

General Statutes § 47-37 provides: "No person may acquire a right-of-way or any other easement from, in, upon or over the land of another, by the adverse use or enjoyment thereof, unless the use has been continued uninterrupted for fifteen years."

A necessary element of a claim of easement by prescription is the continuous use of the land for a period of fifteen years. General Statutes § 47-37; Reynolds v. Soffer, 190 Conn. 184, 187, 459 A.2d 1027 (1983); Gioielli v. Mallard Cove Condominium Assn., Inc., 37 Conn. App. 822, 829, 658 A.2d 134 (1995). The plain language of § 47-27 prevents the creation of any interest in the disputed parcel during the period of corporate use of the land. This statute accordingly serves as a toll on the time period necessary for the creation and perfection of prescriptive rights on the disputed parcel while the land is being used for the defendant's corporate purposes.

We conclude that the trial court correctly interpreted § 47-27 as applied to this case. This statute serves as a toll on the time period necessary for creating a prescriptive easement. In a thoughtful, comprehensive and well-reasoned memorandum of law, the trial court addressed the arguments of the parties. We could not state and resolve the issue any better and, therefore, adopt the trial court's decision. See 45 Conn. Sup. 251, ___ A.2d ___ (1997).


Summaries of

Dalton Enterprises v. Boston and Maine Corp.

Appellate Court of Connecticut
Mar 31, 1998
48 Conn. App. 251 (Conn. App. Ct. 1998)
Case details for

Dalton Enterprises v. Boston and Maine Corp.

Case Details

Full title:DALTON ENTERPRISES, INC. v . BOSTON AND MAINE CORPORATION

Court:Appellate Court of Connecticut

Date published: Mar 31, 1998

Citations

48 Conn. App. 251 (Conn. App. Ct. 1998)
707 A.2d 347

Citing Cases

Ventres v. Goodspeed Airport

A "nonprofit land-holding organization" is defined by that section to include any nonprofit, nonstock…

Paradis v. Burns

It is well established that one claiming a prescriptive easement over land must plead, as well as prove, his…