Opinion
4:08CV3038.
July 9, 2008
ORDER
IT IS ORDERED that the plaintiff's motion for an enlargement of time and continuance (filing 37) is granted, as follows:
1. The plaintiff is granted a 3-week enlargement of time, until August 11, 2008, to file a brief and affidavits in support of its motion for default judgment.
2. The Rule 56(b) default judgment hearing is continued to August 20, 2008, at 1:00 p.m., in Courtroom No. 1, Robert V. Denney Federal Building, 100 Centennial Mall North, Lincoln, Nebraska.
3. The clerk of the court shall send copies of this order to the following addresses:
Scharpf's Construction, Inc.
c/o John Wayne Cox
512 Spring Street
Galena, Illinois 61036
James Scharpf
507 Jo Daviess Street
Galena, Illinois 61036