COMFORT LIVING FURNITURE INC., Plaintiff, v. MCDONALD DESIGN FURNITURE INC. and 1571 HOLDING LLC, Defendant, 1571 HOLDING LLC, Third-Party Plaintiff, v. RYBAK DEVELOPMENT AND CONSTRUCTION CORP., Third-Party Defendant,


Unpublished Opinion

Hon. Leon R. Uchelsman JSC.

HON. LEON R. UCHELSMAN, The defendant/third party plaintiff has moved seeking to vacate the note of issue and for an extension of time in which to move for summary judgment The third party defendant has moved seeking to dismiss the complaint oh the grounds it fails to state any cause of action, essentially seeking summary judgment the complaint alleges no causes of action. The motions have been opposed respectively and papers have been submitted by the parties and arguments held. After reviewing all the arguments this court now makes the, following determination.

Background

As recorded in prior orders in July 2001, Matthew Ferrigno and Victoria Ferrigno leased their property located at 1571 McDonald Avenue, Brooklyn, NY to the defendant McDonald Design Furniture for a duration of 100 years. Located on this property was a. building ("the Store") and an adjacent large open area ("Lot"). In February 2010, Matthew Ferrigno and Victoria Ferrigno changed the name of the owner of the land to Ferrigno Family Trust and renewed their lease with the defendant.

In September 2011, defendant, subleased the first floor of the store to Comfort Living. Furniture for a duration of 10 years Subsequently, in October 2012, defendant subleased the basement of the store to the plaintiff for a duration of 9 years Prior to the defendant commencing excavating the lot. the defendant created a holding company called 1571 Holding LLC In January 2018, a permit to excavate property was issued to 1571 Holding LLC After excavation work commenced, plaintiff claims that due to negligence on behalf of the construction crew, the store experienced severe flooding which destroyed a significant portion of plaintiff's inventory, forced the plaintiff to close the store for a period of time, and forced the plaintiff to expend a significant amount of time and money in order to clean up the flooded area and to replace the destroyed merchandise. A lawsuit was commenced seeking damages for those losses sustained. The defendant 1571 Holding LLC commenced an action against, third party defendant Rybak Development and Construction Corp., alleging that defendant was responsible for the damages sustained. As noted, Rybak has moved seeking to dismiss the third party complaint and the defendant/third party plaintiff has moved seeking to vacate the note of issue and for additional time to seek summary judgement.

Conclusions of Law

Where the material facts at issue in a case are in dispute summary judgment cannot be granted (Zuckerman v. City of New York, 49 N.Y.S.2d 557, 427 N.Y.S.2d 595 [1980]). Generally, it is for the jury, the trier of fact to determine the legal cause of any injury, however, where only one conclusion may be drawn from the facts then the question of legal cause may be decided by the trial court as a matter of law (Marino v. Jamison, 189 A.D.3d 1021, 136 N.Y.S.3d 324 [2d Dept., 2021).

The third party complaint filed by 1571 Holding LLC contains three causes of action, common law and contractual indemnification and contribution all directed at Rybak for the work Rybak conducted at the premises. Rybak has moved seeking to dismiss the third party complaint on the grounds it never entered into, a contract with 1571 Holding LLC Rather, the contract was entered into with non-party 1571 Development LLC and therefore cannot owe any indemnification or contribution to the third party plaintiff.

The Construction Management Agreement stapes it is entered into between Rybak and 1571 Development LLC. However, the signature page lists third party plaintiff 1571 Holding LLC and it is executed by Semyon Vays as a member (see, Construction Management Agreement [NYSCEF Doc. No. 131]). Further, the rider to the agreement is executed by Mark Zeldin on behalf of 1571 Development LLC. Thus, there is confusion as to the correct party that executed the contract together with Rybak, In addition, the deposition testimony of Semyon Vays does not resolve this confusion. Mr. Vays testified that in October 2018 a sublease agreement was entered into whereby 1571 Holding subleased the premises to 1571 Development (see, Deposition of Semyon Vays, page 198 [NYSCEF Doc. No. 135]). It: is difficult to conclude that 1571 Development LLC, as a subtenant entered into contracts for construction Work as an owner. Moreover, that sublease specifically states that "all of the terms and conditions of the Ground Lease shall be binding on the: parties to this Sublease, their successors and assigns, as if they were the parties thereto; that is, those binding the Landlord in the Ground Lease shall bind Sub-Landlord herein, and those binding the tenant in the Ground Lease shall bind Sub-Tenant herein" see. Paragraph 4 of the sublease [NYSCEF Doc. No. 130]). Consequently, the sub-tenant 1571 Development maintains all the rights and obligations of 1571 Holding LLC the tenant of the ground lease. Thus, there are questions whether they may be treated as the same entity. Further confusion exists because the sublease is executed on behalf of 1571 Development. LLC by Sergey Rybak. Mr. Rybak is listed as the president of the third party defendant. Rybak Development and Construction Corp., (see. Construction Management Agreement [NYSCEF Doc. No. 131]). Thus the same individual is an authorized signatory of both entities that executed the construction agreement. There are thus certainly questions of fact concerning the relationship between 1571 Development and 1571 Holding (and Rybak Development) sufficient to deny any summary determination regarding the correct entity that entered, into the agreement with Rybak.

Turning to the specific claims, common law or implied indemnification permits a party who has been required to pay to recover from the wrongdoer (Schottland v. Brown Harris Stevens Brooklyn LLC, 137 A.D.3d 997, 27 N.Y.S.3d 634 [2d Dept., 2016]). It is well settled that to establish a claim for indemnification the plaintiff must prove not Only that it was not guilty of any negligence but must also prove that Rybak was guilty of some negligence that contributed to the causation of the accident (Perri v. Gilbert Johnson Enterprises Ltd., 14 A.D.3d 681, 790 N.Y.S.2d 25 [2d Dept., 2005]). There are surely questions whether any negligence was committed and consequently the motion seeking to dismiss the two indemnification claims are denied.

Further, it is well settled that contribution is available where two or more tortfeasors combine to cause an injury and is determined in accordance with the relative culpability of each such person (Godov v. Abamaster of Miami Inc., 302 A.D.2d 57, 754 N.Y.S.2d 301 [2d Dept.., 2003]). CPLR §1401 states, that where two or more persons (or entities) are subject to liability for the same "personal injury, injury to property or wrongful death" they may claim contribution among them (id). Thus, contribution is only available.' where tort liability is. sought in the underlying case (Board of Education of Hudson City School District v. Sargent, Webster, Crenshaw & Folley, 71 N.Y.2d 21, 523 KY S2d 475 [1987]). Thus, contribution is unavailable where damages sought are exclusively for breach of contract' (Ruby Land Development Ltd, v. Toussie, 4 A.D.3d 518, 771 N.Y.S.2d 701 [2d Dept., 2004]). An examination of the plaintiff's third party complaint demonstrates the claims are based upon negligence in addition to breach of contract and consequently th motion seeking to dismiss the contribution cause of action is denied.

Thus, the motion seeking summary judgment dismissing the third party complaint is denied.

Concerning the motion seeking to strike the note of issue, it is true that a timely motion to vacate a Note of Issue should be granted where the movant has demonstrated that the case is. not ready for trial (Mosley v. Flavius, 13 A.D.3d 346, 785 NY'S 2d 742 [2d Dept., 2004], see, also, 22 NYCRR §202.21(e)). The defendant/third party plaintiff asserts that discovery has not been completed. The third party defendant does, not really dispute that contention but asserts the: defendant/third party plaintiff waived any requests for any further discovery. There is no merit to the argument the requests for any further discovery was waived. Further, the note of issue contains a jury demand that is improper. Therefore, the motion seeking to vacate the note of issue, is granted. The time in which to file, any summary judgment motion is extended to sixty days following the completion of all discovery.

So ordered.


Summaries of

Comfort Living Furniture Inc. v. Mcdonald Design Furniture Inc.

Supreme Court, Kings County
May 18, 2023
2023 N.Y. Slip Op. 31691 (N.Y. Sup. Ct. 2023)
Case details for

Comfort Living Furniture Inc. v. Mcdonald Design Furniture Inc.

Case Details

Full title:COMFORT LIVING FURNITURE INC., Plaintiff, v. MCDONALD DESIGN FURNITURE…

Court:Supreme Court, Kings County

Date published: May 18, 2023

Citations

2023 N.Y. Slip Op. 31691 (N.Y. Sup. Ct. 2023)