CNP Mechanical, Inc. v. Allied Builders, Inc.

Appellate Division of the Supreme Court of New York, Fourth Department
Oct 2, 2009
66 A.D.3d 1340 (N.Y. App. Div. 2009)

Opinion

No. CA 09-00255.

October 2, 2009.

Appeal from a judgment of the Supreme Court, Monroe County (Kenneth R. Fisher, J.), entered September 15, 2008 in a breach of contract action. The judgment was entered upon the order in appeal No. 1 and awarded plaintiff the sum of $70,347.09 against defendant Allied Builders, Inc.

DUKE, HOLZMAN, PHOTIADIS GRESENS LLP, BUFFALO (JAMES W. GRESENS OF COUNSEL), FOR DEFENDANTS-APPELLANTS.

GATES ADAMS, P.C., ROCHESTER (RICHARD T. BELL, JR., OF COUNSEL), FOR PLAINTIFF-RESPONDENT.

Present: Scudder, P.J., Hurlbutt, Peradotto, Green and Gorski, JJ.


It is hereby ordered that the judgment so appealed from is unanimously reversed on the law without costs and the motion is denied.

Memorandum: Plaintiff commenced this action seeking, inter alia, $429,332.46 in damages resulting from the alleged breach by defendant Allied Builders, Inc., the general contractor, of its subcontract with plaintiff. We agree with defendants that Supreme Court erred in granting plaintiffs motion seeking partial summary judgment in the amount of $62,077.48. In support of its motion, plaintiff submitted a "Subcontract Summary" (Summary) prepared by defendants' counsel, which allegedly constituted an admission by defendants that plaintiff was owed a minimum of $62,077.48. In opposition to the motion, defendants submitted evidence that the Summary was prepared for the purpose of settlement negotiations and was therefore inadmissible as proof of the amount of damages ( see CPLR 4547). We conclude that the court erred in determining that the Summary was admissible because it contained readily verifiable facts with respect to the amount owed to plaintiff pursuant to the subcontract and thus erred in granting plaintiffs motion based on the Summary. Even assuming, arguendo, that the Summary was admissible, we further conclude that plaintiff itself raised an issue of fact with respect to the amount set forth in the Summary by submitting documents in its reply papers, including its responses to defendants' interrogatories, that conflict with the individual amounts listed in the Summary ( see generally Zuckerman v City of New York, 49 NY2d 557, 562).


Summaries of

CNP Mechanical, Inc. v. Allied Builders, Inc.

Appellate Division of the Supreme Court of New York, Fourth Department
Oct 2, 2009
66 A.D.3d 1340 (N.Y. App. Div. 2009)
Case details for

CNP Mechanical, Inc. v. Allied Builders, Inc.

Case Details

Full title:CNP MECHANICAL, INC., Respondent, v. ALLIED BUILDERS, INC., et al.…

Court:Appellate Division of the Supreme Court of New York, Fourth Department

Date published: Oct 2, 2009

Citations

66 A.D.3d 1340 (N.Y. App. Div. 2009)
2009 N.Y. Slip Op. 6892
885 N.Y.S.2d 790

Citing Cases

Reem Contracting v. Altschul & Altschul

However, they concede that the audit is inadmissible at trial, and thus, as previously held on plaintiffs'…

Reem Contracting v. Altschul & Altschul

Moreover, the court finds that there are issues of fact as to whether plaintiffs would have prevailed or…