From Casetext: Smarter Legal Research

California Electric Power Co. v. United States, (1945)

United States Court of Federal Claims
May 7, 1945
60 F. Supp. 344 (Fed. Cl. 1945)

Opinion

Nos. 45688, 45916.

May 7, 1945.

Henry W. Coil, of Riverside, Cal. (Douglas L. King, of Riverside, Cal., on the brief), for plaintiff.

William A. Stern, II, of Washington, D.C., and Francis M. Shea, Asst. Atty. Gen., for defendant.

Before WHALEY, Chief Justice, and LITTLETON, WHITAKER, JONES, and MADDEN, Judges.


Actions by the California Electric Power Company against the United States to recover overcharges for electric power taken by plaintiff from a generating plant at Boulder Dam.

Judgments for plaintiff in accordance with opinion.

These cases having been heard by the Court of Claims, the court, upon the evidence and the report of a commissioner, makes the following special findings of fact:

1. Plaintiff is a Delaware corporation. Prior to June 30, 1941, its name was Nevada-California Electric Corporation. Southern Sierras Power Company, a Wyoming corporation, owned and operated a system of electric power plants and lines serving the southeastern portion of California. Plaintiff owned its outstanding stock and completely controlled it. On December 1, 1936, it was liquidated and plaintiff acquired all its assets and assumed all its contracts and liabilities. Plaintiff, therefore, has all the rights of Nevada-California Electric Corporation and Southern Sierras Power Company.

2. In accordance with the provisions of Section 5 of the Boulder Canyon Project Act approved December 21, 1928, 43 U.S.C.A. § 617d, the Secretary of the Interior, on April 25, 1930, promulgated General Regulations for the lease and sale of electrical energy at the Boulder Dam. Plaintiff's Exhibit 2, pp. 103-114, contains a true copy of said General Regulations, as amended on March 10, 1931, July 1, 1931, and November 16, 1931.

3. Pursuant to the provisions of the Boulder Canyon Project Act, approved December 21, 1928, 45 Stat. 1057, 43 U.S.C.A. § 617 et seq., requiring the Secretary of the Interior, prior to the expenditure of any money in the construction of the dam, to make provision by contract for revenues adequate in his judgment to insure payment of all expenses of operation and maintenance and the repayment with interest within 50 years of the date of completion of the works of all amounts advanced to the fund created for the construction of the dam, the Secretary of the Interior, on April 26, 1930, caused to be executed in the name of the United States a contract with the City of Los Angeles and Southern California Edison Company, Ltd., for the lease of power privileges. (Exhibit A to petitions and made a part hereof by reference.)

4. By the contract of lease of power privileges, the City of Los Angeles and Southern California Edison Company, Ltd. were made, severally, lessees of the power plant machinery of the dam to be constructed, and were obligated to generate at cost electric energy for themselves and other allottees of energy with whom contracts were to be made by the Secretary for the sale of energy, the principal allottee being the Metropolitan Water District. This contract of lease with power privileges was to begin to run as to the City of Los Angeles when water should become ready for delivery to it, and it and certain municipal corporations, which as allottees were entitled to have their energy generated by the City, were obligated and entitled to commence taking energy when the Secretary of the Interior should announce that 1,250,000,000 kilowatt-hours of energy per year were ready for delivery. The Metropolitan Water District was to become obligated and entitled to begin receiving its energy, generated by the City, when the Secretary should announce that 2,000,000,000 kilowatt-hours were available, but not sooner than one year after energy should become ready for delivery to the City. Southern California Edison Company, Ltd. and allottees under it (Southern Sierras Power Co. and Los Angeles Gas Electric Corporation) were to become obligated and entitled to begin receiving energy when the Secretary should announce that water capable of generating 4,240,000,000 kilowatt-hours per year was available, but not sooner than three years after commencement of delivery to the City. This contract of lease of power privileges was to expire as to both the City and Southern California Edison Company, Ltd., and the allottees under each, at the expiration of 50 years after the date it should become effective as to the City. It thus had 50 years to run as to the City and municipal corporations, 49 years as to Metropolitan Water District, and 47 years as to Southern California Edison Company, Ltd. and the allottees under it.

The City was required to generate energy for itself, the Metropolitan Water District, the States of Nevada and Arizona if they should desire to contract for energy, and the municipal corporations. Southern California Edison Company, Ltd., was required to generate energy for itself, Los Angeles Gas Electric Corporation, and Southern Sierras Power Co.

The entire firm energy, 4,240,000,000 kilowatt-hours, was allocated to the lessees and allottees, but since there was a probability that the height of the dam would be raised, thus giving an additional 90,000,000 kilowatt-hours, the United States reserved the right to dispose of this 90,000,000 kilowatt-hours to any municipality by firm contract.

Total firm energy was fixed as 4,240,000,000 kilowatt-hours per year for the first year of complete operation (June 1 to May 31, inclusive), subject to a progressive reduction of 8,760,000 kilowatt-hours each year thereafter because of silting and increased irrigation above the dam. Secondary energy was defined as all energy generated in any year in excess of the amount of firm energy for that year. There was a further provision that, "in arriving at the respective rates for `firm energy' and `secondary energy" as fixed herein, recognition has been given to the fact that `secondary energy' cannot be relied upon as being at all times available, but was subject to diminution or temporary exhaustion; whereas `firm energy' is the amount of energy agreed upon as being available continuously as required during each year of the contract period."

Each lessee (and by later contracts, each allottee who executed a contract) was obligated to take and/or pay for a stated percentage of firm energy per year. The price of firm energy was fixed at 1.63 mills per kilowatt-hour and secondary energy at one-half mill per kilowatt-hour, but there was a load-building or absorption period proviso to the effect that in order to afford a reasonable time for the lessees, City of Los Angeles and Southern California Edison Company, Ltd., to absorb the energy contracted for, the minimum annual payments by each for the first three years after energy should be ready for delivery to such lessees, respectively, as announced by the Secretary, should be as follows, in percentages of the ultimate annual obligation to take and/or pay for firm energy:

First year ................ 55 percent Second year ............... 70 percent Third year ................ 85 percent Fourth and subsequent years 100 percent

The proviso also stated that:

"During said absorption period, if the quantity of energy taken in any one year (June 1 to May 31, inclusive), is in excess of the above percentage of the ultimate obligation during such year to take and/or pay for firm energy, such excess shall be paid for at the rate for secondary energy."

The contract of lease of power privileges also contained the following provision:

"(37) Any modification, extension, or waiver by the Secretary of any of the terms, provisions, or requirements of this contract for the benefit of any one or more of the allottees (including the lessees) shall not be denied to any other. (Exhibit A to petitions.)"

5. Article V, subdivision F, clause (ii) of the General Regulations and Article (14), subdivision F, clause (ii) of the Lease of April 26, 1930, provided that so much of the energy contracted for by the Municipalities of Pasadena, Burbank and Glendale and not taken or used by them should be taken and paid for by the City of Los Angeles. (Plaintiff's Ex. 2, p. 138.)

6. Also on April 26, 1930, the Secretary caused to be executed a contract between the United States and the Metropolitan Water District whereby the latter agreed to take and/or pay for 36 percent of the firm energy at 1.63 mills per kilowatt-hour, and secondary energy at one-half mill per kilowatt-hour, but with a three-year load-building or absorption period proviso against the firm energy similar to the one in the contract of lease of power privileges described in finding 3. (Plaintiff's Ex. 2, p. 157.)

Contracts having thus been entered into which in the opinion of the Secretary complied with the requirements of the Boulder Canyon Project Act, the work of constructing the dam was started, and was completed in the year 1936.

7. On November 12, 1931, the Secretary caused to be executed a contract between the United States and the Los Angeles Gas Electric Corporation for the purchase of and/or payment for a certain percentage of firm energy, and on November 5, 1931, he caused a similar contract to be executed with Southern Sierras Power Company. On September 29, 1931, November 12, 1931, and November 10, 1931, he caused similar contracts to be entered into between the United States and the municipal corporations of Pasadena, Glendale, and Burbank, respectively. Each of these contracts bound the contractor to take and/or pay for the stated percentage of firm energy and fixed the price of firm energy at 1.63 mills per kilowatt-hour. None of them contained a loading-building or absorption period proviso against firm energy, as did the contract of lease of power privileges in favor of the City of Los Angeles and Southern California Edison Company, Ltd., and the contract with Metropolitan Water District in favor of Metropolitan Water District. Each of them contained a provision reciting that the United States had entered into the contract of lease of power privileges of April 26, 1930, and that a copy thereof was "attached hereto marked Exhibit A, and by this reference made a part hereof." (Plaintiff's Ex. 2, pp. 177, 197, 219, 239, and 259.)

The contract of November 5, 1931, between the United States and Southern Sierras Power Company provided that any charges not paid when due should bear a penalty of 1% per month until paid, and if the plaintiff was delinquent for 12 months in the payment of charges, no energy should, except with the consent of the Secretary, be generated for the plaintiff, and the Secretary reserved the right to terminate the plaintiff's contract and dispose of the energy elsewhere, the plaintiff nevertheless to remain liable to make the United States whole for the period of the contract for all loss or damage by reason of the plaintiff's failure to take and pay for its allotment of energy.

8. The contract of lease of power privileges and the contract with Metropolitan Water District, both dated April 26, 1930, together with the contracts of November 12, 1931, November 5, 1931, September 29, 1931, November 12, 1931, and November 10, 1931, with Los Angeles Gas Electric Corporation, Southern Sierras Power Company, and the cities of Pasadena, Glendale, and Burbank, respectively, bound the contractors (lessees and allottees) on final completion of the dam to take and/or pay for 100 percent of the firm energy, i.e., 4,240,000,000 kilowatt-hours per year, subject to the progressive reduction of 8,760,000 kilowatt-hours per year resulting from silting and upstream irrigation. The disposition was as follows:

fn1

To be contracted for as needed. (Plaintiff's Ex. 2, p. 25.)

------------------------------------------------------------------------------------------------------------------------------------------------ | Firm energy | |----------------------------------------------------------------------------------------------| | Minimum which | Contractor's obligation | Maximum which contractor | | United States | if energy is | can demand | Secondary energy | must supply | available (percent) | under various conditions | | (percent) | | (percent) | --------------------|-----------------------------------|-----------------------------|----------------------------|---------------------------- Arizona | 18 .............................. | ............................| 22 ................ | None. | | | | Nevada | 18 .............................. | ............................| 22 (18 percent plus 4 | None. | | | percent If not used | | | | by other State). | | | | | Metropolitan Water | 36 .............................. | 36..........................| 72 percent (its own | First call on all secondary District | | | minimum plus first | energy. | | | call on unused State | | | | energy). | Los Angeles ....... | 14.9054 (13 percent | 32.9054 (its minimum | 32.9054 .................. | Call on ½ secondary | plus uncontracted | plus ½ unused | | energy, subject to | municipality energy) | used State energy, | | Metropolitan's first | | subject to Metropolitan's | | call. | | first call). | | Pasadena ......... | 1.6183 .......................... | 1.6183 .................... | 1.6183 ................... | None. Glendale ......... | 1.8867 .......................... | 1.8867 .................... | 1.8867 ................... | None. Burbank .......... | 0.5896 .......................... | 0.5896 .................... | 0.5896 ................... | None.] Southern California | 7.2 ............................. | 21.6 (7.2 percent plus | 21.6 ..................... | Call on 80 percent of Edison | | 80 percent of ½ unused | | ½ of secondary energy, Co. | | used State energy). | | subject to Metropolitan's | | | | first call. Los Angeles Gas | 0.9 ............................. | 2.7 (0.9 percent plus | 2.7 ...................... | Call on 10 percent of Electric | | 10 percent of ½ unused | | ½ of secondary energy, Corp. | | used State energy). | | subject to Metropolitan's | | | | first call. Southern Sierras | 0.9 ............................. | 2.7 (0.9 percent plus | 2.7 ...................... | Call on 10 percent of Power Co. | | 10 percent of ½ unused | | ½ of secondary energy, | | State energy). | 2.7 ...................... | subject to Metropolitan's | | | | first call. |-----------------------------------|-----------------------------|----------------------------| Total ......... | 100 ............................. | 100 ........................| ...........................| ------------------------------------------------------------------------------------------------------------------------------------------------

9. Although it was not expected that the Secretary would announce that 1,250,000,000 kilowatt-hours per year of energy would be ready for delivery until about June 1, 1937, it was known that the dam would be completed in 1936 and that prior to the announcement substantial quantities of energy could be generated although not as much as 1,250,000,000 kilowatt-hours per year. This was because water would have to be released for irrigation and other purposes anyway and by running it through the power equipment energy could be produced. It was also known that for the same reason more than 1,250,000,000 kilowatt-hours and more than 2,000,000,000 kilowatt-hours, respectively, could be generated after each former announcement but prior to the announcements of 2,000,000,000 and 4,240,000,000 kilowatt-hours. Accordingly, the City of Los Angeles, Southern Sierras Power Company and Southern California Edison Company, Ltd., applied to the Secretary for interim contracts for that energy but at the rate for secondary energy. The application of Southern Sierras Power Company and Southern California Edison Company, Ltd., was a joint application. Southern Sierras Power Company also requested that a load-building or absorption period proviso be written into its contract for firm energy.

10. The City of Los Angeles protested against the Southern Sierras Power Company being given an interim contract at the secondary energy rate, as a result of which a conference was held on October 3, 1934, in Washington, D.C., at which were present representatives of the City of Los Angeles, Southern Sierras Power Company, the U.S. Bureau of Reclamation and the U.S. Department of the Interior, at which a "Memorandum of Understanding" was composed and signed by the representatives, which memorandum said that it was agreed that the United States would give the City an interim contract by which it could take energy at the secondary energy rate from the time energy could first be generated until the Secretary should announce that 1,250,000,000 kilowatt-hours of energy were ready for delivery, that the United States would give the municipalities of Pasadena, Glendale and Burbank load-building or absorption period provisos against their firm energy commitments similar to those originally given to the lessees and to Metropolitan Water District against their firm energy commitments, that the United States would give the Southern Sierras Power Company and the Nevada-California Power Company an interim contract by which they could take energy at the secondary energy rate from the time energy could first be generated until the time Southern Sierras Power Company should become firmly obligated to purchase power under its contract of November 5, 1931, and that the City would withdraw its protest against the giving of an interim contract to Southern Sierras Power Company and Nevada-California Power Company. (Plaintiff's Ex. 36.) This agreement, however, was never approved by the Secretary.

11. On October 22, 1934, a contract was entered into between the United States and the City of Los Angeles whereby the latter was permitted to begin operating a part of the generating machinery as soon as water should become available and to pay for energy taken by it prior to the announcement of 1,250,000,000 kilowatt-hours per year at only the rate for secondary energy. In consideration for this the City conveyed to the United States 640 acres of land which it owned within the reservoir site of the dam and on November 1, 1934, withdrew its objection to the awarding of an interim contract to the Southern Sierras Power Company. (Plaintiff's Ex. 23.) It was provided in this contract of October 22, 1934, that its provisions applied only to the period in advance of the taking effect of the lease of April 26, 1930, and that said lease should not be in any manner affected or modified by the contract of October 22, 1934. The City began taking energy under this interim contract of October 22, 1934 in October 1936, and continued taking under it until June 1, 1937.

12. The United States, acting by the Secretary of the Interior, on October 22, 1934, made another contract with the City of Los Angeles, containing, among others, the following provision:

Obligation of the City

"(9) The provisions of Article (14), Subdivision F, Clause (ii) of said Lease of Power Privilege, shall not be construed to require the City, during the first three years, to take or pay for, in any event, any portion of the respective allocations to the said Municipalities other than the amounts by which their respective requirements may be less than fifty-five per centum (55%) of their respective ultimate annual obligations for the first year, or less than seventy per centum (70%) of their respective ultimate annual obligations for the second year, or less than eighty-five per centum (85%) of their respective ultimate annual obligations for the third year."

(Exhibit 1 annexed to each of Plaintiff's Exhibits 4, 5 and 6.)

13. On October 30, 1934, November 1, 1934, and October 30, 1934, the municipal corporations of Pasadena, Glendale and Burbank, respectively, were given supplemental contracts containing three-year load-building or absorption period provisos against their firm energy commitments similar to the ones of the City of Los Angeles, Southern California Edison Company, Ltd., and Metropolitan Water District. (Plaintiff's Exs. 4, 6, and 5.)

14. The Secretary declined and refused in 1934, 1935, and 1936, to give to Southern Sierras Power Company either a load-building or absorption period proviso, or an interim contract for energy at the secondary energy rate.

15. In May 1937 the Secretary of the Interior announced and gave notice that 1,250,000,000 kilowatt-hours of energy per year would be ready for delivery on June 1, 1937, thus putting into effect on June 1, 1937, the original contractual obligations of the City of Los Angeles and the obligations of the municipal corporations of Pasadena, Glendale, and Burbank.

In June 1938, the Secretary announced and gave notice that 2,000,000,000 kilowatt-hours of energy per year would be available on July 1, 1938, thus putting into effect on July 1, 1938, the contractual obligations of Metropolitan Water District.

In May 1940, the Secretary announced and gave notice that water capable of generating 4,240,000,000 kilowatt-hours of energy per year would be available on June 1, 1940, thus putting into effect on June 1, 1940, the contractual obligations of Southern California Edison Company, Ltd., Los Angeles Gas Electric Corporation, and Nevada-California Electric Corporation which at that time had succeeded to the rights and contractual obligations of Southern Sierras Power Company.

16. On February 1, 1937, the City of Los Angeles acquired all of the properties of Los Angeles Gas Electric Corporation, including its contract of November 12, 1931, mentioned in finding 7. Nevertheless, the City of Los Angeles renewed its objection to the Secretary giving Nevada-California Electric Corporation an interim contract at the secondary energy rate.

17. On July 22, 1937, a supplemental contract was entered into between the United States and Nevada-California Electric Corporation whereby a part of the machinery to be later operated by Southern California Edison Company, Ltd. was leased to Nevada-California Electric Corporation for the purpose of generating energy until the time when the Secretary should announce that water capable of generating 4,240,000,000 kilowatt-hours of energy per year was available. (Exhibit 2 in appendix to petition in No. 45916, p. 36.) This supplemental contract provided that of this interim power thus generated, 114,280,000 kilowatt-hours during the first year, 114,048,000 during the second year, and 113,817,000 during the third year should constitute firm energy and be paid for by Nevada-California Electric Corporation at 1.63 mills — the firm energy rate — and that energy over and above those amounts should be secondary energy at the secondary energy rate. Then followed a load-building or absorption period proviso against this firm energy in language similar to the proviso in the contract of lease of power privileges of April 26, 1930. A copy of that lease was attached to and made a part of the July 22, 1937, contract. There was also a provision as follows:

"(33) In the event rates and charges more favorable than those herein required to be paid by the Company are granted to any present allottee or contractor of electrical energy to be developed at Boulder Dam power plant; then, and in such event, the rates and charges herein agreed to be paid by the Company shall be adjusted so that from and after the date such lesser rates and charges become effective the Company shall not be required to pay rates and charges greater than those required to be paid by any present allottee or contractor of electrical energy to be developed at Boulder Dam power plant; provided, however, that the provisions of this article shall not be construed to apply to rates and charges fixed in contracts covering the temporary resale of electrical energy allotted to The Metropolitan Water District of Southern California."

The period of operation under this supplemental contract of July 22, 1937, was from August 16, 1937 to May 31, 1940, inclusive, a period of 2 years, 9½ months. Thus plaintiff got a load-building or absorption period proviso, but not against the firm energy commitment in its original contract, and it got a contract for interim power, but a large part of the energy to be taken under it was to be paid for at the firm energy rate.

The energy taken by plaintiff under the supplemental contract of July 22, 1937, proved to be constant, but under that supplemental contract plaintiff's right to get it was subject to contingencies over which it had no control and to the prior rights of others, the provision of the contract being:

"* * * The Company shall not have the right to demand the release of any quantities of water for the generation of electrical energy, or otherwise, but shall have the right to the use of waters released from Lake Mead for the generation of electrical energy only as, if and when, as conclusively determined by the Secretary, water is available for the use of the Company for such purpose over and above quantities of water required for fullest operation of electrical generating equipment heretofore furnished and installed or hereafter to be furnished and installed by the United States for the use and benefit of The City of Los Angeles (and its Department of Water and Power), pursuant to the aforesaid contract of date April 26, 1930, and the aforesaid supplements thereto, hereinbefore designated as "Exhibit A," or pursuant to that certain contract between the United States and The City of Los Angeles, and its Department of Water and Power, of date October 22, 1934, designated "Permit and License to Use Machinery and Power Plant Facilities," and heretofore furnished and installed, or hereafter to be furnished and installed for the use and benefit of others that have contracted with the United States for the purchase of electrical energy to be generated at Boulder Dam power plant, and are entitled or obligated, under contracts heretofore made, to take electrical energy prior to the time Southern California Edison Company Ltd. is entitled or obligated to take electrical energy to be thus generated * * *."

18. At the time Nevada-California Electric Corporation entered into the supplemental contract of July 22, 1937, it was in great necessity of acquiring additional energy with which to supply the needs of its customers and was in some danger of losing a portion of its sources of acquiring energy, i.e., an interchange contract it had with Los Angeles Gas Electric Corp. It had done all it could do to induce the Secretary to give it a more favorable supplemental contract.

19. On July 6, 1938, the City of Los Angeles, it having in the meantime acquired by assignment the contractual obligations and rights of the Los Angeles Gas Electric Corporation, entered into another contract with the United States, known as the "Third Circuit Contract." (Plaintiff's Ex. 7.) Under this Third Circuit Contract the City of Los Angeles agreed to construct and maintain a third transmission circuit from the dam to Los Angeles and to take and/or pay for certain additional quantities of energy. This contract also provided that "in order to afford the City the same privileges, with respect to the firm energy contracted for by the Los Angeles Gas Electric Corporation under the Gas Corporation Contract, assigned by that corporation to the City, which have been afforded to certain other allottees," the City should have as to the firm energy taken under the Los Angeles Gas Electric Corporation contract a load-building or absorption period proviso similar to the one in its favor in the contract of lease of power privileges of April 26, 1930, and ones in the contracts of Metropolitan Water District and in the supplemental contracts of the municipal corporations of Pasadena, Glendale, and Burbank, and such a proviso was written into said Third Circuit Contract in the following language:

"* * * the minimum annual payments to be made by the City with respect to the firm energy so contracted for, for the first three years after such energy is ready for delivery to the City as assignee of the said Corporation, under the terms of the Lease and the Gas Corporation Contract, shall be as follows: in percentages of the ultimate annual obligation to take and/or pay for firm energy under said Gas Corporation Contract and said assignment thereof; First year, 55 percent, Second year, 70 percent, Third year, 85 percent, Fourth year and all subsequent years, 100 percent.

"The privileges extended by this Article shall be deemed to have been in effect as of October 30, 1934, the date on which similar privileges were granted to certain other allottees."

The contract of July 6, 1938, further provided that the generation of energy allocated to Los Angeles Gas and Electric Corporation and assigned to the City of Los Angeles might be effected by the City, at its option, as though so provided in Article (10) (d) of the lease of April 26, 1930, that is, in the machinery provided for the City instead of that provided for Los Angeles Gas and Electric Corporation.

The Third Circuit Contract of the City of Los Angeles, dated July 6, 1938, provided that, if the United States made available to the City, in accordance with the lease of April 26, 1930, and that contract, the necessary water, the City would take and pay for, in accordance with its optional rights under said lease, a quantity of electric energy in excess of 3,000,000,000 kilowatt-hours, during the period ending May 31, 1945, all such energy to be paid for at the rate for secondary energy, and the contract further provided:

"Water will be delivered by the United States for the generation of energy hereunder in accordance with Article (21) of the Lease. The term "load requirements" as used therein with reference to the City shall include, after the City has constructed its third circuit under this agreement and throughout the remaining life of the Lease, the requirements of the City for temporary increases in the delivery of water for generation of firm energy during periods when another source of power is out of service by reason of an emergency. If, in consequence thereof, the City uses water for the generation of firm energy in excess of its allocation during any year of operation, the Secretary may, in his discretion diminish delivery of water to the City for the generation of firm energy during the following year of operation by an equivalent quantity."

Article (21) of the lease thus referred to provided that:

"The United States will deliver water continuously to each lessee in the quantity, in the manner, and at the times necessary for the generation of the energy which each of said lessees has the right and/or obligation to generate under this contract in accordance with the load requirements of each of said lessees and of allottees for which the respective lessees are generating agencies."

The City of Los Angeles lease of April 26, 1930, contained a formula for determining the rate for firm energy in the advent of periodic rate adjustments which were provided for under said lease, but it contained no formula for determining the rate for secondary energy. The Third Circuit Contract of said City, dated July 6, 1938, provided that, in all future adjustments of rates for secondary energy (which should be uniform for all contractors having rights to secondary energy), the rate for secondary energy should be the price for firm energy plus fixed and operating costs of generation and transmission of such energy, less all or such portion of all reasonable fixed and operating costs as are chargeable specifically and solely to generating and transmitting secondary energy and providing, maintaining and intermittently operating such standby plants as are necessary to make such secondary energy equally as reliable and continuously available as firm energy.

20. On October 14, 1938, an interim contract was entered into between the United States and Southern California Edison Company, Ltd., giving the latter the right to take, until June 1, 1940, large quantities of Metropolitan Water District's unused firm energy and to pay for it at only the secondary energy rate of one-half mill. (Plaintiff's Ex. 34.)

The plaintiff's contract of November 5, 1931, provided that no disposition of firm energy allocated to but not used by Metropolitan Water District should be made by the Secretary without first giving to the plaintiff the right to contract for such energy on equal terms and conditions, but no such right to contract for the Metropolitan Water District's unused firm energy at the secondary energy rate or at any rate less than the firm energy rate was ever given by the Secretary to the plaintiff, and no notice was given to the plaintiff by the Secretary of his proposal or intention to make the contract of October 14, 1938, with Southern California Edison Company, Ltd., although the Secretary did, in September 1937, give plaintiff the opportunity to contract for such Metropolitan Water District's unused firm energy at the rate of 1.63 mills per kilowatt-hour.

21. Because of the large amount of energy taken, the load-building or absorption period provisos operated as to the City of Los Angeles, both in its own right and as assignee of Los Angeles Gas Electric Corporation, and as to Southern California Edison Company, Ltd., and the municipal corporations of Pasadena, Glendale and Burbank, mainly as mere rate reductions and they received the benefits intended thereby. This, however, was not true as to Metropolitan Water District as it did not take a large part of the firm energy it was obligated to take and/or pay for.

22. In addition to the original request, Southern Sierras Power Company, or Nevada-California Electric Corporation, or plaintiff, on July 8, 1940, September 17, 1940, and February 4, 1941, made written requests upon the Secretary to be accorded a load-building or absorption period proviso or concession against firm energy under the original contract of November 5, 1931 with Southern Sierras Power Company, but the Secretary denied such requests. On May 2, 1940, February 4, 1941, and June 20, 1941, plaintiff applied to the Secretary for a reduction to one-half mill per kilowatt-hour on the interim "firm" energy taken under the supplemental contract of July 22, 1937, with Nevada-California Electric Corporation, but the Secretary also denied these requests.

23. In the sale and distribution of energy there was some competition between plaintiff and Southern California Edison Company, Ltd., between plaintiff and the City of Los Angeles, and between Southern California Edison Company, Ltd. and the City of Los Angeles.

24. Pursuant to the act of Congress approved July 19, 1940, 54 Stat. 774, 43 U.S.C.A. § 618 et seq., known as "Boulder Canyon Project Adjustment Act," the Secretary on May 20, 1941, promulgated new regulations applicable to the generation and disposal of electrical energy, and pursuant to said Act and prior Acts, entered into a certain "Contract for Operation of Power Plant," dated May 29, 1941, with the City of Los Angeles and Southern California Edison Company, Ltd., terminated the "Contract for Lease of Power Privileges" dated April 26, 1930, and on or about May 29, 1941, made certain contracts herein called "Adjustment Contracts," effective for the period ending May 31, 1987, with each and all allottees hereinbefore mentioned, whereby all prior existing leases and contracts of the lessees and allottees were terminated, and whereby the allotment of firm and secondary energy and the minimum obligation to take and pay for firm energy of each of the lessees and allottees as provided in prior existing leases and contracts were unchanged, but the rate for falling water for the generation of firm energy was reduced from 1.63 to 1.163 mills per kilowatt-hour and for secondary energy from .5 mills to .34 mills per kilowatt-hour, both rates retroactive to June 1, 1937, the necessary refunds to be made on future bills. In each of those adjustment contracts provision was made whereby the then unexpired and unenjoyed portion, if any, of the absorption period provided for in the prior leases and contracts respectively was carried over into each of the adjustment contracts. (Plaintiff's Exhibits 17, 18, 19, and 20.)

25. In the adjustment contract of May 29, 1941, with the City of Los Angeles, the City's obligation to take and/or pay for energy for the period ending May 31, 1945, as set forth in the City's Third Circuit Contract of July 6, 1938, was carried over into the adjustment contract, such energy to be paid for at the adjusted rate for secondary energy, and it was further provided that the United States would deliver water to the City in the quantity, in the manner, and at the times necessary for the generation of that energy.

26. It was provided in Article 15 of plaintiff's adjustment contract that it was understood that plaintiff claimed that (1) it is entitled to an absorption period for the three years commencing June 1, 1940, and that (2) it was obligated to pay only at the rate for secondary energy for all energy taken by it under the contract of July 22, 1937; also, that it was agreed that neither the termination of the original contract between the parties nor the termination of the contract dated November 12, 1931, between the United States and Los Angeles Gas and Electric Corporation and assigned to the City, nor the termination of the lease, nor anything contained in the contract or in the contract for the operation of the Boulder Power plant or in the General Regulations, should terminate, modify or otherwise affect the relative rights and obligations of the parties as they existed on May 19, 1941; also, that the rights and obligations of the parties should be conformed to said relative rights and obligations as finally determined, provided that, pending such determination, payments should be made by plaintiff in accordance with departmental determination and the provisions of the adjustment contract, but without prejudice to the rights of plaintiff, and provided that plaintiff should be estopped from asserting the claim referred to in "(1)" above, and the denial thereof by the defendant should be final conclusive and binding if court proceedings with respect to it should not be commenced on or before May 31, 1942, and provided further that plaintiff should be estopped from asserting the claim referred to in "(2)" above, and the departmental decision thereon should be final, conclusive and binding if (in the event said departmental decision be adverse to plaintiff) arbitration or court proceedings with respect to it should not be commenced within one year from the date of the departmental decision.

These suits were instituted within the periods stated and in due time.

27. All of the contracts mentioned in the foregoing findings of fact are in evidence and are by reference made a part of these findings.

28. If plaintiff is entitled to a load-building or absorption period proviso or concession, sued for in No. 45688, the amounts due it are $41,369.78 for the operating year June 1, 1940 to May 31, 1941, inclusive; $27,307.36 for the operating year June 1, 1941 to May 31, 1942, inclusive; and $13,495.40 for the operating year June 1, 1942 to May 31, 1943, inclusive, a total of $82,172.54.

29. Plaintiff, under the supplemental contract of July 22, 1937, paid for 223,671,094 kilowatt-hours of energy at the firm energy rate of 1.63 mills per kilowatt-hour and 117,205,196 kilowatt-hours at the secondary energy rate of one-half mill per kilowatt-hour. If plaintiff had been required to pay for the 223,671,094 kilowatt-hours at only the secondary energy rate, it would have paid only $180,502.55, and the difference, $184,081.31, is the amount sued for in No. 45916.


In these two cases we have written one set of findings of fact and one opinion. In case No. 45688 the plaintiff sues for $82,172.54, claiming that it was overcharged this amount by the Government for electric power taken by the plaintiff from a generating plant at Boulder Dam, in that it was denied a "load-building" or "load-absorption" period which, if granted, would have reduced its charges by the amount stated. In case No. 45916 the plaintiff sues for $184,081.31 which, it claims, it was overcharged for Boulder Dam electric power under an "interim" contract with the Government, in that it was required to pay 1.63 mills per kilowatt-hour for secondary power when the lawful price for such power was only .5 mill. References to the plaintiff apply, depending on the time of the action referred to, to the plaintiff's former wholly owned subsidiary, the Southern Sierras Power Company, or to the plaintiff itself, either under its former name, the Nevada California Electric Corporation, or under its present name.

The Boulder Canyon Project Act of December 21, 1928, 45 Stat. 1057, 43 U.S.C.A. § 617 et seq., required the Secretary of the Interior to obtain contracts, from future purchasers of power to be generated at the dam, adequate in his judgment to insure the payment of all costs of operation and maintenance and the repayment within 50 years from the date of completion of the project of the cost of building it, with interest. Unless and until such contracts were obtained, no money was to be spent in constructing the dam. The Secretary, on April 26, 1930, made a contract for the lease of the power privileges at the dam to the City of Los Angeles and the Southern California Edison Company. The City agreed to operate a part of the power plant machinery of the dam and to generate electricity at cost for itself, the Metropolitan Water District, the States of Nevada and Arizona if and when they should elect to take power, and certain other municipal corporations which were, by contracts to be made, to receive allotments of power. Edison similarly agreed to operate the rest of the generating equipment to supply power to itself and to the plaintiff and the Los Angeles Gas and Electric Corporation. The lease contract provided that the City and the other municipalities should be entitled and obligated to take power when the Secretary should announce that 1,250,000,000 kilowatt-hours per year of energy were ready for delivery; that the Metropolitan Water District, with which the Secretary on the same day made a contract for a large allotment of power, was to become entitled and obligated to take power when the Secretary should announce that 2,000,000,000 k.w.h. were available, but not sooner than 1 year after the commencement of delivery to the city; and that Edison and the other private allottees were to become entitled and obligated to take power when water capable of generating 4,240,000,000 k.w.h. was available, but not sooner than 3 years after commencement of delivery to the City. The lease was to run for 50 years from the date when delivery of power to the City should begin.

In the autumn of 1931, the Secretary made separate contracts with the cities of Pasadena, Glendale, and Burbank, California, the Los Angeles Gas and Electric Corporation and the plaintiff. The plaintiff's contract was dated November 5, 1931. In each of these contracts the allottee agreed to take and/or pay for the percentage named in the contract of the whole amount of firm energy to be generated at the dam, at the price of 1.63 mills per k.w.h.

The lease and the several contracts allotted, by percentages, the entire 4,240,000,000 k.w.h. per year among the several allottees as firm power, i.e., as power which the Government bound itself to deliver and the allottees bound themselves to pay for. The rate to each allottee for firm power was 1.63 mills per k.w.h., except as that rate was affected by the load-building or absorption period discussed hereinafter. It was contemplated that there would actually be more than 4,240,000,000 k.w.h. of power available, and the possible excess was secondary power. Rights in secondary power were specified in the lease and the contracts, and the rate for it was set at .5 mill per k.w.h. The table in finding 8 shows the rights of the parties to firm and secondary power.

In the lease a concession was made to the City of Los Angeles and to Edison, that they would not, for the first three years that each was bound to pay for power, be obliged to take or pay for their full ultimate allotments at the firm power rate. It was provided that, for the first, second, and third years only 55, 70, and 85 percent, respectively, need be taken, and that if more than those percentages were in fact taken, the excess would be charged for only at the .5 mill secondary power rate. This was the "load-building period" privilege, which, as we shall see, the plaintiff claims it did not get, which claim is the basis for the suit in case No. 45688. This privilege was given to the Metropolitan Water District in its contract of April 26, 1930, which was also the date of the lease. It was not given to the 3 smaller cities, nor to the Gas Company, nor to the plaintiff, in their contracts made in the autumn of 1931. As we shall see, it was later given to all of the municipalities, and to the city of Los Angeles, as the successor to the Gas Company, but not, at least in the same form, to the plaintiff, though the Government urges that it was given to the plaintiff in substance.

Contracts adequate to reimburse the Government having been made, the Government proceeded with the building of the dam. As building progressed, the prospect was that the Secretary would announce the availability of 1,250,000,000 k.w.h. per year of power, which announcement would put into effect the obligation of the City of Los Angeles to begin to pay for its percentage of power, about June 1, 1937. The dam was expected to be completed in 1936. But all the water in the river could not be impounded while the depth necessary to generate 1,250,000,000 k.w.h. was built up, since persons downstream had the right to a flow of some of the water for irrigation and other uses. Hence, some water would have to be released, and if it was put through the generating equipment, power not contracted for would be available. It was also expected that in the interval between each announcement and the succeeding one, water would be available to generate more power than the amount covered by the original contracts. As early as 1934 the City of Los Angeles, Edison, and the plaintiff applied to the Secretary for "interim" contracts to buy this power, when it should become available, at the .5 mill secondary power rate. The City objected to the plaintiff's getting any of it at that rate, because the plaintiff's "interim" would continue for some three years after the City began to pay the firm power rate of 1.63, and, the City claimed, the plaintiff was in competition with it at various points. A conference was held in Washington at which representatives of the City, the plaintiff, the United States Bureau of Reclamation and the Department of the Interior prepared and signed, on October 3, 1934, a "Memorandum of Understanding." See finding 10. This memorandum provided that the City should have an interim contract at the secondary rate until it became bound, under the lease, to take power at the firm rate; that the plaintiff should have a similar interim contract until it, in its turn, became so bound; and that the cities of Pasadena, Glendale, and Burbank should have load-building privileges. In the memorandum the City withdrew its objection to the plaintiff's receiving an interim contract. The Secretary never approved the agreement embodied in the memorandum, however, and the plaintiff never received an interim contract on the terms provided in the memorandum. On October 22, 1934, the City was given an interim contract to take power at the .5 mill rate from the time sufficient water became available until the time when it became bound to pay the firm power rate under the 1930 lease. On October 30, 1934, Pasadena and Burbank, and on November 1, Glendale, were given supplemental contracts giving them 3 year load-building periods similar to those given in 1930 to the City, Edison, and Metropolitan. These municipalities were, as we have seen, to begin to take firm power at the same time as the City, so their load-building periods were to be concurrent with that of the City. The Secretary in 1934, 1935, and 1936, refused, though requested, to give the plaintiff either a load-building period, or an interim contract at the .5 mill rate.

In May 1937 the Secretary announced that 1,250,000,000 k.w.h. per year would be available June 1, 1937, thereby obligating the City of Los Angeles and the three smaller cities to begin to take power at the firm rate, as modified by the load-building privilege, from the latter date. The City's interim contract thus came to an end on May 31, 1937. On July 22, 1937, the plaintiff was given a supplemental or interim contract to be operative for the period of approximately 3 years which would elapse before the availability of the full 4,240,000,000 k.w.h. would be announced and the plaintiff's permanent contract would go into effect. This interim contract provided that the plaintiff should receive 114,280,000 k.w.h. the first year, and specified amounts slightly less than that for the second and third years, of "firm" energy at the 1.63 mills rate, and additional energy at the .5 mill rate. The contract designated the named amounts of energy as "firm" energy, but the energy was not "firm" within the meaning of that term as used in the lease, the other contracts and the regulations. It was completely subordinate to the rights of the City, though the prospect was that it would in fact be available and it turned out to be available for the three-year period. It was also subject in various ways to the will of the Secretary. This interim contract gave the plaintiff, for the interim period, the load-building concession which meant that only 55, 70, and 85 percent of the specified amounts of "firm" energy had to be taken and paid for at the 1.63 mills rate during the first, second, and third years, respectively, of the interim contract, amounts taken in excess of those percentages carrying only the .5 mill rate. The refusal to give the plaintiff a .5 mill rate for all power taken under its interim contract is, as we have said, the basis for its suit in No. 45916.

In No. 45688 the plaintiff's claim is based on the fact that it was not given a load-building period which would have reduced the price of its power from 1.63 mills to .5 mill per k.w.h. for 45, 30, and 15 percent of the firm power which it took during the first, second, and third years of the period of its permanent contract, i.e., from June 1, 1940 to May 31, 1943. As appears above, all other parties to the lease and the contracts made in 1931 were given such a period. In support of its claim for equal treatment in this regard, the plaintiff cites the Boulder Canyon Act, 45 Stat. 1057, 43 U.S.C.A. § 617, the Regulations issued by the Secretary of the Interior, the basic lease to the City and Edison, and the contracts with the plaintiff and others. Section 5 of the Act provided, in part:

"That the Secretary of the Interior is hereby authorized, under such general regulations as he may prescribe, to contract for the * * * generation of electrical energy and delivery at the switchboard to States, municipal corporations, political subdivisions, and private corporations of electrical energy generated at said dam, upon charges that will provide revenue which, in addition to other revenue accruing under the reclamation law and under this act, will in his judgment cover all expenses of operation and maintenance incurred by the United States on account of works constructed under this act and the payment to the United States under subdivision (b) of Section 4. * * *

"General and Uniform regulations shall be prescribed by the said Secretary for the awarding of contracts for the sale and delivery of electrical energy. * * *"

The Secretary's General Regulations, promulgated on April 25, 1930, after conferences with the municipalities and companies which were to take the power, provided for the making of the lease to the City and Edison; defined firm and secondary energy; fixed the rate per k.w.h. for each class of energy; allocated the energy among the lessees and allottees, and fixed the minimum annual obligations of each lessee and allottee. The lease, as we have seen, was dated April 26, 1930, and leased the generating machinery at the dam, some to the City of Los Angeles and some to Edison. It also, by its terms, made allotment contracts with the City and Edison, which incorporated the terms set out in the regulations. It provided in Article 14(D) for the allocation of 6% of the power to a list of municipalities, including Burbank, Glendale, and Pasadena, and in Article 14(F) (ii) it required the City of Los Angeles to take and pay for so much of the energy allocated to the municipalities as they did not take and pay for. It provided in Article 14(F) for the allocation of power to the plaintiff. The other contracts, including the one made with the plaintiff, also covered the subjects of allotments and rates, and a copy of the lease was attached to and made a part of each contract. Article 37 of the lease said:

"Any modification, extension, or waiver by the Secretary of any of the terms, provisions, or requirements of this contract for the benefit of any one or more of the allottees (including the lessees) shall not be denied to any other."

As we have seen, the lease granted the load-building period to the City and Edison, whereby each was, for the first, second, and third years of its contract excused from taking more than 55, 70, and 85 per cent of the agreed amount of firm energy at the 1.63 mill rate, and, if it took more than those percentages, got the excess at the .5 mill rate. The municipalities of Burbank, Glendale, and Pasadena, as well as the plaintiff and the Gas Company, were not given this concession in their original contracts made in the autumn of 1931. But, as we have seen, in the autumn of 1934, following the signing of the "Memorandum of Understanding," the Secretary made supplemental contracts with the three municipalities in which it granted load-building periods to them on the basis of the same percentages as those granted to the City and Edison. On October 22, 1934, as shown in finding 11, the Secretary made a contract with the City, excusing the City from its guaranty that the municipalities would pay for their allotments of power, to the extent that their allotments were to be reduced by the load-building period which they were to be given.

The plaintiff claims that it was entitled to a load-building period because that concession was made to the municipalities. It points to Article 37 of the lease, quoted above. It says that the supplemental contracts with the municipalities were modifications of the lease (1) because the lease was incorporated in and made a part of each of the original contracts which were later modified, and (2) because the term of the lease itself, by which the City guaranteed to pay for the allotments of the municipalities at firm energy rates, if the municipalities did not pay, was modified by the contract of October 22, 1934, with the City. It also points to the fact that when, in 1938, the City became the assignee of the property and rights of the Gas Company, it on July 6, 1938, obtained a contract with the Secretary whereby, as such assignee of the Gas Company's contract with the Secretary, it was given a load-building period. The contract of July 6, 1938, which is quoted in finding 19, said that it was made to give the City, as assignee of the Gas Company, the same privileges given to other allottees on October 30, 1934, evidently referring to the supplemental contracts with the municipalities.

We think the plaintiff became entitled to a load-building period, when that concession was made to the municipalities and to the City as guarantor, and as assignee of the Gas Company. We think the lease and the contracts made with the allottees other than the lessees were intended to provide for equal treatment of the allottees, including the lessees, except as the lease and the original contracts which were contemplated by the lease, and into which the lease was incorporated, provided. The lease was modified when the requirement of its Article 14(D) that the municipalities take 6% of firm power was reduced by the percentages of the load-building period, and when the requirement of its Article 14(F) relating to the Gas Company was similarly reduced, for the benefit of the City as assignee. Its Article 14 (F) (ii) was modified when the City's guaranty to take or pay for the municipalities' allotment if they did not do so was reduced by the same percentages.

The government argues that the lease was not modified by these concessions to other allottees, but, as we have indicated, we do not agree. The Government also urges that, whether or not the plaintiff became entitled to a load-building period, it received that concession, in its interim contract given it by the supplemental lease of July 22, 1937, shown in finding 17. By this lease it agreed to take specified quantities of power, during the interval of about two years and ten months before the time when its original contract of 1931 would have required it to take power, and to pay the firm power rate of 1.63 mills for this interim power, except that any power taken by it in excess of 55, 70, and 85 per cent of the specified quantities, during the first, second, and third years, respectively, of the interim contract, would carry only the .5 mill rate. We think that the acceptance of this interim contract by the plaintiff did not destroy its right, under the lease and its original contract, to have a load-building period of three years from June 1, 1940, the date when it became obligated under its original contract to begin to take and pay for power. The contracts of the municipalities, and of the City as assignee of the Gas Company, were modified so as to give them load-building periods from the corresponding times in their contracts. We think that the Government has no right to set up, as to the plaintiff, something which, it claims, is the equivalent of, or practically as good as, the thing which it had expressly agreed that the plaintiff should have. The load-building period given to the plaintiff in its interim contract was not, we think, intended to be given as a substitute for one to which the plaintiff was entitled under Article 37 of the lease. As will appear from the discussion of No. 45916, a complicated set of circumstances led to the making of the interim contract. The right, which the plaintiff claims, accrued to it as a result of a statute, regulations of general effect, and contracts made by an authorized public officer. The effect of these acts and contracts was to fix schedules of rates and terms on which those entitled to power from the dam would get it. The Government, as the vendor of power, should not be permitted to change those schedules to the prejudice of the purchaser. We conclude, therefore, that in No. 45688 the plaintiff's claim to the benefits of a load-building period for the three years beginning June 1, 1940, is well founded.

No. 45916 is, as we have said, based upon the claim that all of the power which the plaintiff took under its interim contract of July 22, 1937, and for which it paid 1.63 mills, except for the percentages covered by the load-building period, for which percentages it paid .5 mill, should have carried the .5 mill rate because it was secondary power. The plaintiff relies upon the Boulder Canyon Act, which, it contends, required that the power be disposed of under uniform regulations; the Regulations of the Secretary of the Interior, which set the rate of .5 mill for secondary power; the "Memorandum of Understanding" with the plaintiff and others, of October 3, 1934; the interim contract with the City of Los Angeles, of October 22, 1934, selling to it power which had express priority over the plaintiff's interim power, at the .5 mill rate; the "third circuit" contract with the City, of July 6, 1938, whereby the City was assured a specified amount of power, in addition to the firm power agreed to in its original lease, at the .5 mill rate; and the contract of October 14, 1938 with Edison whereby, without notice to the plaintiff, Edison was given a contract for unused firm power of the Metropolitan Water District at the .5 mill rate.

The Government's defense to this claim is, in substance, that the power available before the date of the first announcement which put the City's permanent contract into effect, and after each announcement but before the succeeding one, until the ultimate announcement of 4,240,000,000 k.w.h. of available power was made, putting the last of the contracts into effect, was power not covered by the Regulations or contracts, which the Secretary could refuse to sell at all, or sell on any terms he saw fit, and that the plaintiff is therefore bound by its contract to pay the agreed rates. As we have shown, the City and the plaintiff each applied for interim power. The conference of the interested parties with the agents of the Government produced the Memorandum of Understanding of October 3, 1934. That memorandum was intended as an agreement that various formal contracts would be made. All the contemplated contracts were made, except the one giving the plaintiff an interim contract, at the .5 mill rate. The City was given such a contract, and began to take power under it in October 1936, and ceased doing so on June 1, 1937, when its permanent contract began to operate.

The Secretary refused to approve an interim contract with the plaintiff on the terms provided in the Memorandum of Understanding. Further negotiations occurred in the succeeding years, and on July 22, 1937, an interim contract was made with the plaintiff. It leased to the plaintiff the generator which had been ordered by the Government in 1934, pursuant to the Memorandum of Understanding, and installed at a cost of $1,000,000, and required the plaintiff to pay its amortization and operating charges. It bound the plaintiff to take some 114,000,000 k.w.h. of power per year, designated the power to be taken as "firm" power, and fixed the firm power rate of 1.63 mills as the applicable rate. It granted the plaintiff a load-building period, for the interim, which meant that for power taken in excess of 55, 70, and 85 percent of the agreed amounts for the three successive years, the .5 mill rate would apply. The contract made the plaintiff's right to the release of any water for generating power subject to the conclusive determination of the Secretary that there was water available above what was needed for the fullest operation of equipment already or subsequently installed to serve the City of Los Angeles, or others having contracts for power. It provided that interim contracts might be made with others having contracts which did not yet entitle them to take power. Article 33 of the contract, quoted in finding 17, provided that if more favorable rates should be granted to any allottee or contractor, then the plaintiff should not thereafter be required to pay more than those rates. Article 33 was not, however, to apply to rates for the temporary resale of power allotted to the Metropolitan Water District.

The interim power which the plaintiff was entitled to under its contract was not "firm" power, as that term was used in the Regulations, lease, and contracts other than the interim contract. Firm power as defined was power which the Government agreed to deliver and the taker had the right to demand. The amount of firm power to be ultimately available had been conservatively estimated, so that the financing of the project would be sound, and it was always anticipated that there would be, in fact, a good deal more power than that which had been contracted for as "firm." The mere prospect or likelihood that power would be available was not, therefore, the basis of distinction between firm and secondary power. Yet the interim contract attached the label "firm" to the plaintiff's power, in contradiction of the use of the term in all other connections. The obvious purpose of the label was to justify the rate. The reason for the imposition of the rate was that the Secretary thought it would be unfair for the plaintiff to have the .5 mill rate for the three years before its permanent contract went into effect, while the City would be paying the full rate for a considerable percentage of its power.

The regulations, the lease, and the original contracts fixed the rates for firm and secondary power. We think they bound the Secretary, if he desired to market the power here in question, to charge the price for it which was applicable to its true nature. It was secondary power, because it was not agreed to be delivered, and was expressly made subject to the priorities of the City, and to being shared, if necessary, with others. The rate, set by public regulation and by agreement, applicable to secondary power, should have been applied to it.

The plaintiff asserts that, by Article V of the Regulations, Article (14) of the lease, and Article (7) of the plaintiff's original contract, which provided for the allotment of energy, it was entitled to a portion of the secondary energy at any time that such energy was available and was not taken by Metropolitan. If so, it was entitled to get it at the .5 mill rate set in the Regulations, lease, and contract for secondary energy. We think it was so entitled. A practical impediment to its getting it was, originally, that it would have no facilities for generating it until Edison took possession under its lease after 4,240,000,000 k.w.h. of energy were available. In fact the Secretary, by the plaintiff's interim contract of July 22, 1937, leased generating equipment to the plaintiff, thus making secondary energy available to it. But in the same contract, he labeled the secondary energy as "firm" and charged 1.63 mills for most of it. We think that, having made it available, he could not depart from the rate set in the Regulations, lease, and contract.

The so-called "third circuit" contract made by the Government with the City on July 6, 1938 is relied on by the plaintiff as bringing into play from that date the provision of Article 33 of the plaintiff's interim contract promising to it the benefit of any more favorable contract made thereafter. The City was proposing to build an additional transmission line, and desired to obtain additional power. By this contract the Government agreed to supply 3,000,000,000 k.w.h. of additional power at the .5 mill rate during the period ending May 31, 1945. It also agreed to a formula for adjusting future rates for secondary power, the regulations, lease, and original contracts not having contained any provision for those rates.

We think that the third circuit contract, which gave the City a .5 mill rate for power, including interim power, which power, if secondary, yet had priority of right over the plaintiff's interim power, entitled the plaintiff under Article 33 to the .5 mill rate from July 6, 1938.

Edison's contract for firm power did not go into effect until June 1, 1940. The Metropolitan Water District had, in the original contracts, obligated itself to pay for 36% of the firm power generated at the dam. Its obligation was to begin when the Secretary announced the availability of 2,000,000,000 k.w.h., one year after the City's obligation became effective. In 1937 it was apparent that the 2,000,000,000 k.w.h. announcement would be made June 1, 1938. It had been expected from the beginning that Metropolitan would not, in fact, have use at least in the early years for its 36% of firm power, and the lease and contracts had provided that the Secretary might resell, for Metropolitan's account, what it did not use; that the City and Edison should each have an option to buy one-half of such power; that the plaintiff should have an option to buy 10% of Edison's one-half, and that if the Secretary proposed to sell such power he would notify the several parties having options. In 1937 the Secretary notified the parties, including the plaintiff, that he proposed to sell Metropolitan unused power, to begin June 30, 1938, at the 1.63 mills firm power rate. None of the parties exercised their options. On October 14, 1938, after the plaintiff had made its interim contract on July 22, 1937, the Secretary, without notice to the plaintiff, made a contract to sell Edison Metropolitan unused firm power at .5 mill. Failure to notify the plaintiff was a breach of the Government's contract giving the plaintiff an option to buy such power, and a right to notice when it was for sale. The Government urges that the plaintiff was not hurt by this alleged breach, since it had, by its interim contract, obligated itself to pay 1.63 mills for a specified amount of power, subject to the load-building concession of a rate of .5 mill for all above 55, 70, and 85% of the specified amount in the first, second, and third years, hence would be getting at .5 mill all the power it was free to buy at a rate other than 1.63 mills. The plaintiff replies that what it was getting under its interim contract at .5 mill was secondary power, subject to the priority of the City and the will of the Secretary, while what it was entitled to buy of the unused Metropolitan power was firm power, subject to no prior right in anyone. The plaintiff suggests that the reason it was not notified of the proposed sale of unused Metropolitan power was that if it had entered into the negotiations to buy firm power at .5 mill the absurdity of its having been charged 1.63 mills, in its interim contract, for secondary power, would have been so apparent as to demand a revision of that contract. We think there is probable merit in the suggestion. The provision of Article 33 of the plaintiff's interim contract would certainly have been called into play by the sale to Edison, except that Article 33 expressly provided that it should "not be construed to apply to rates and charges fixed in contracts covering the temporary resale of electrical energy allotted to" Metropolitan. The plaintiff claims that because of the Government's breach of its contract to notify it of the sale of Metropolitan unused power, the Government lost its right to insist upon the proviso in Article 33. We do not see the force of this argument, and, since we have concluded above that the plaintiff was entitled to the .5 mill rate, it is not necessary to determine what effect, if any, the Edison transaction may have had upon the plaintiff's rights.

The Government urges, with regard to both suits, that whatever rights the plaintiff may have had to a load-building privilege or to a .5 mill rate for its secondary power, it lost those rights by voluntarily entering into its interim agreement. The plaintiff says that it did not make the agreement voluntarily, but made it as a result of economic duress. We agree with the plaintiff. We have found that it did all that it could to obtain an interim contract along the lines of the 1934 Memorandum of Understanding. It was apparent in 1937 that this could not be accomplished. It would not have been prudent, even if it had been possible, for it in 1937 to have obtained other sources of needed power, since it was to become bound in 1940 to take power under its contract, hence other arrangements would have had to be temporary. The 1.63 mills rate of its interim contract was probably less than it would have had to pay elsewhere. The fact that the Gas Company, with which it had had exchange arrangements, was being taken over by the City, which was not friendly and was questioning the validity of the exchange arrangements, made it imprudent for it to depend greatly on that source of power. One who has a right to obtain a service from a public utility, for which service there is a charge fixed by law, cannot estop himself from challenging a higher charge by an agreement to pay it. To a degree, the extent of which it is not necessary to determine, the same doctrine is, we think, operative in this case, and coupled with the economic duress to which the plaintiff was subject, it is sufficient to relieve the plaintiff of any waiver which might otherwise have resulted from its making of its interim contract. The Regulations, lease, and contracts made by the Secretary created a situation which contemplated and called for treatment of all parties on the basis of uniform definitions and rules. For him to change the defined meaning of terms, and make special applications of the rules to particular situations because he thought they called for special treatment, was, we think, a denial to the plaintiff of its rights under the Regulations and the contracts.

The plaintiff is entitled to recover in both cases. Judgment will therefore be entered for plaintiff in case No. 45688 in the sum of $82,172.54, and in case No. 45916 in the sum of $184,081.31. It is so ordered.

WHALEY, Chief Justice, and LITTLETON, Judge, concur.


I do not think plaintiff is entitled to recover in either case. Under the original leases and contracts the plaintiff was not entitled to any power until 1940, when it was to take a part of that to be generated by the Edison Company beginning in that year. It wanted it earlier and induced the defendant to lease to it generating equipment so it could generate its own current and so get it earlier than it could under its arrangement with the Edison Company. Defendant was under no obligation to do this; nor was plaintiff under any compulsion to take the power. The parties were free contracting agents.

They entered into a contract for power on precisely the same terms as the city's contract. The only difference was the city was entitled to get its power first; but this was immaterial because there was plenty for both parties.

No more has been charged plaintiff than it agreed to pay. There has been no discrimination, and, so, I do not think plaintiff is entitled to recover.

JONES, Judge, took no part in the decision of this case.


Summaries of

California Electric Power Co. v. United States, (1945)

United States Court of Federal Claims
May 7, 1945
60 F. Supp. 344 (Fed. Cl. 1945)
Case details for

California Electric Power Co. v. United States, (1945)

Case Details

Full title:CALIFORNIA ELECTRIC POWER CO. v. UNITED STATES

Court:United States Court of Federal Claims

Date published: May 7, 1945

Citations

60 F. Supp. 344 (Fed. Cl. 1945)

Citing Cases

Westinghouse Elec. Corp. v. Garrett Corp.

"[Westinghouse] has no right to set up, as to [Garrett], something which, it claims is the equivalent of, or…

Reynolds Metals Company v. United States

A most favored nation clause is neither an unnecessary extension of the limitations period nor a refuge for…