From Casetext: Smarter Legal Research

Burrstone Energy Ctr., LLC v. Faxton-St. Luke's Healthcare

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department
Jun 8, 2018
162 A.D.3d 1554 (N.Y. App. Div. 2018)

Opinion

655 CA 18–00006

06-08-2018

BURRSTONE ENERGY CENTER, LLC, Plaintiff–Appellant–Respondent, v. FAXTON–ST. LUKE'S HEALTHCARE, Defendant–Respondent–Appellant.

HINCKLEY, ALLEN & SNYDER LLP, ALBANY (JAMES J. BARRIERE OF COUNSEL), FOR PLAINTIFF–APPELLANT–RESPONDENT. BOND, SCHOENECK & KING, PLLC, ALBANY (STUART F. KLEIN OF COUNSEL), FOR DEFENDANT–RESPONDENT–APPELLANT.


HINCKLEY, ALLEN & SNYDER LLP, ALBANY (JAMES J. BARRIERE OF COUNSEL), FOR PLAINTIFF–APPELLANT–RESPONDENT.

BOND, SCHOENECK & KING, PLLC, ALBANY (STUART F. KLEIN OF COUNSEL), FOR DEFENDANT–RESPONDENT–APPELLANT.

PRESENT: WHALEN, P.J., CENTRA, PERADOTTO, TROUTMAN, AND WINSLOW, JJ.

MEMORANDUM AND ORDER

It is hereby ORDERED that the order so appealed from is unanimously affirmed without costs.

Memorandum: The parties entered into an "Energy Services Agreement" (Agreement) pursuant to which plaintiff would finance and construct a combined heat and power facility (CHPF) on defendant's property in exchange for defendant's promise to purchase all of its thermal energy requirements from plaintiff unless, "when operating at full capacity, the CHPF [did] not produce sufficient Thermal Energy to meet all [of defendant's energy] requirements." In the event that the CHPF did not produce sufficient Thermal Energy, defendant would be permitted to use its own boilers "to supplement the production and delivery of Thermal Energy so as to meet the one hundred percent (100%) Thermal Energy requirement." Several years after the CHPF began operating, plaintiff commenced the instant action for breach of contract and judgment declaring that defendant is obligated under the Agreement to purchase 100% of its thermal energy requirements from plaintiff. Plaintiff moved for partial summary judgment on its fifth cause of action, seeking a declaration, and defendant cross-moved for partial summary judgment on that cause of action. Supreme Court denied the motion and cross motion, and we affirm.

Initially, we agree with plaintiff that the court erred in determining that it was precluded from issuing a declaration. The mere existence of another adequate remedy does not preclude a court from issuing a declaration (see Matter of Morgenthau v. Erlbaum , 59 N.Y.2d 143, 148, 464 N.Y.S.2d 392, 451 N.E.2d 150 [1983], cert denied 464 U.S. 993, 104 S.Ct. 486, 78 L.Ed.2d 682 [1983] ; County of Monroe v. Clough Harbour & Assoc., LLP , 154 A.D.3d 1281, 1282, 62 N.Y.S.3d 677 [4th Dept. 2017] ; see generally CPLR 3001 ). Where, as here, the parties have differing interpretations of their obligations under a contract and the contract does not "delineate[ ] the agreed procedure to be followed for resolving disputes arising [between the parties]" ( Kalisch–Jarcho, Inc. v. City of New York , 72 N.Y.2d 727, 732, 536 N.Y.S.2d 419, 533 N.E.2d 258 [1988] ), a cause of action for declaratory relief "may be an appropriate vehicle for settling justiciable disputes as to contract rights and obligations" ( id. at 731, 536 N.Y.S.2d 419, 533 N.E.2d 258 ).

We nonetheless conclude that the court properly denied the motion and cross motion because the parties' Agreement is not clear and unambiguous (see generally MHR Capital Partners LP v. Presstek, Inc. , 12 N.Y.3d 640, 645, 884 N.Y.S.2d 211, 912 N.E.2d 43 [2009] ; Colella v. Colella , 129 A.D.3d 1650, 1651, 12 N.Y.S.3d 459 [4th Dept. 2015] ). The Agreement provides that "[t]he Parties acknowledge and understand that when operating at full capacity, the CHPF may nevertheless not produce sufficient Thermal Energy to meet all requirements." That provision may be interpreted, as plaintiff contends, as requiring defendant to purchase all of the thermal energy produced by the CHPF, regardless of whether defendant can distribute that energy. The provision also may be interpreted, as defendant contends, as permitting defendant to use its own boilers when the CHPF is incapable of meeting 100% of its thermal energy requirements, which is often because defendant's thermal energy distribution system cannot accommodate all forms of thermal energy produced by the CHPF. Inasmuch as it is not clear whether the parties were aware of the limitations of defendant's hot water thermal energy distribution capabilities when they entered the Agreement "for the sale [from plaintiff] to [defendant] of all the [hospital's] ... Thermal Energy requirements," both the motion and cross motion were properly denied.


Summaries of

Burrstone Energy Ctr., LLC v. Faxton-St. Luke's Healthcare

SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department
Jun 8, 2018
162 A.D.3d 1554 (N.Y. App. Div. 2018)
Case details for

Burrstone Energy Ctr., LLC v. Faxton-St. Luke's Healthcare

Case Details

Full title:BURRSTONE ENERGY CENTER, LLC, PLAINTIFF-APPELLANT-RESPONDENT, v…

Court:SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department

Date published: Jun 8, 2018

Citations

162 A.D.3d 1554 (N.Y. App. Div. 2018)
162 A.D.3d 1554
2018 N.Y. Slip Op. 4182

Citing Cases

Columbus Monument Corp. v. City of Syracuse

As noted, this is a hybrid action consisting of both an Article 78 and a declaratory judgment action. "Where,…

Columbus Monument Corp. v. City of Syracuse

The remaining claims for declaratory relief granted by the court, i.e., that "the Monument has not exceeded…