From Casetext: Smarter Legal Research

BG National Plumbing & Heating, Inc. v. New York City School Construction Authority

Supreme Court of New York, Appellate Division, Second Department
Jun 2, 2021
No. 2021-03435 (N.Y. App. Div. Jun. 2, 2021)

Opinion

2021-03435 Index 706681/14

06-02-2021

BG National Plumbing & Heating, Inc., appellant v. New York City School Construction Authority, respondent.

Mark L. Cortegiano, Middle Village, NY (Derek Piersiak and Diana J. Demirdjan of counsel), for appellant. James E. Johnson, Corporation Counsel, New York, NY (Jeremy W. Shweder and Barbara Graves-Poller of counsel), for respondent.


Mark L. Cortegiano, Middle Village, NY (Derek Piersiak and Diana J. Demirdjan of counsel), for appellant.

James E. Johnson, Corporation Counsel, New York, NY (Jeremy W. Shweder and Barbara Graves-Poller of counsel), for respondent.

REINALDO E. RIVERA, J.P. MARK C. DILLON COLLEEN D. DUFFY VALERIE BRATHWAITE NELSON, JJ.

DECISION & ORDER

In an action, inter alia, to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Queens County (Joseph Risi, J.), entered February 21, 2019. The order granted the defendant's motion to dismiss the complaint and denied the plaintiff's cross motion for leave to amend the notice of claim and the complaint.

ORDERED that the order is affirmed, with costs.

In May 2012, the plaintiff was the successful bidder on a project to perform accessibility and electrical upgrades for the defendant. Pursuant to the subject bid and contract agreement, the plaintiff was to substantially complete the work on the project on or before "730 continuous calendar days," commencing from the "Notice to Proceed" date of June 18, 2012. On December 19, 2013, the plaintiff filed a notice of claim (hereinafter the original notice of claim) upon the defendant, alleging that it was entitled to an extension of the substantial completion date of 243 consecutive calendar days because of certain delays and impacts on the project. Notably, the original notice of claim did not include any claim for monetary damages.

In September 2014, the plaintiff commenced the instant action by filing a summons with notice. In October 2017, the plaintiff served a complaint seeking monetary damages in "an amount to be determined at trial but not less than $2,455,740.63 plus statutory interest."

On or about June 1, 2018, the defendant moved to dismiss the complaint, inter alia, on the ground that the notice of claim failed to comply with Public Authorities Law § 1744. On or about July 17, 2018, the plaintiff cross-moved pursuant to General Municipal Law § 50-e for leave to amend the original notice of claim to include damages in the total principal sum of $2,455,740.63 and to claim a net 540 consecutive calendar day extension of the substantial completion date, and pursuant to CPLR 3025 for leave to amend the complaint. The Supreme Court granted the defendant's motion and denied the plaintiff's cross motion. The plaintiff appeals.

Public Authorities Law § 1744(2) requires the plaintiff to serve a notice of claim upon the defendant within three months after the accrual of such claim (see AMCC Corp. v New York City Sch. Constr. Auth., 154 A.D.3d 673, 675; Kafka Constr., Inc. v New York City Sch. Constr. Auth., 125 A.D.3d 933, 935). Under Public Authorities Law § 1744(3), a notice of claim "must set forth in detail... (i) the amount of the claim; (ii) a specific and detailed description of the grounds for the claim, relating the dollar amount claimed to the event purportedly giving rise to the claim and indicating how the dollar amount is arrived at; and (iii) the date of the event allegedly underlying the claim." Here, the original notice of claim filed by the plaintiff failed to comply with Public Authorities Law § 1744(3) (see AMCC Corp. v New York City Sch. Constr. Auth., 154 A.D.3d at 675; see also C.S.A. Contr. Corp. v New York City School Constr. Auth., 5 N.Y.3d 189, 192; Bri-Den Constr. Co., Inc. v New York City Sch. Constr. Auth., 55 A.D.3d 649).

The Supreme Court properly denied that branch of the plaintiff's motion which was for leave to amend the original notice of claim, inter alia, to include damages in the total principal sum of $2,455,740.63. "A notice of claim may be amended only to correct good faith and nonprejudicial technical mistakes, omissions, or defects, not to substantively change the nature of the claim or the theory of liability" (Castillo v Kings County Hosp. Ctr., 149 A.D.3d 896, 897; see Matter of Johnson v County of Suffolk, 167 A.D.3d 742, 743). Here, the proposed amendments to the original notice of claim were not technical in nature, and thus, are not permitted as late-filed amendments to a notice of claim (see C.D. v Goshen Cent. Sch. Dist., 186 A.D.3d 1316, 1318; Robinson v City of New York, 138 A.D.3d 1093, 1094). In addition, the plaintiff failed to explain the inordinate delay in seeking leave to amend the original notice of claim.

The parties' remaining contentions either are without merit or need not be reached in light of our determination.

RIVERA, J.P., DILLON, DUFFY and BRATHWAITE NELSON, JJ., concur.


Summaries of

BG National Plumbing & Heating, Inc. v. New York City School Construction Authority

Supreme Court of New York, Appellate Division, Second Department
Jun 2, 2021
No. 2021-03435 (N.Y. App. Div. Jun. 2, 2021)
Case details for

BG National Plumbing & Heating, Inc. v. New York City School Construction Authority

Case Details

Full title:BG National Plumbing & Heating, Inc., appellant v. New York City School…

Court:Supreme Court of New York, Appellate Division, Second Department

Date published: Jun 2, 2021

Citations

No. 2021-03435 (N.Y. App. Div. Jun. 2, 2021)