Summary
affirming denial of motion for summary judgment against promissory estoppel claim because "questions of fact existed as to what transpired during the contract negotiations"
Summary of this case from Vinifera Imports Ltd. v. Societa Agricola Castello Romitorio SRLOpinion
526458
05-16-2019
Rossi & Rossi, New York Mills (Vincent J. Rossi Jr. of counsel), for appellant. Hinman, Howard & Kattell, LLP, Binghamton (Daniel R. Norton of counsel), for respondent.
Rossi & Rossi, New York Mills (Vincent J. Rossi Jr. of counsel), for appellant.
Hinman, Howard & Kattell, LLP, Binghamton (Daniel R. Norton of counsel), for respondent.
Before: Garry, P.J., Lynch, Clark, Mulvey and Rumsey, JJ.
MEMORANDUM AND ORDER
Clark, J. In December 2016, in preparation for submitting a bid to serve as the general contractor on a reconstruction project, plaintiff solicited quotes from subcontractors to perform excavation and landscaping work on the project. Defendant submitted a quote, which plaintiff incorporated into its bid after purportedly confirming with defendant the scope of work and price quoted. In January 2017, plaintiff informed defendant that it had won the contract to serve as general contractor on the project. The parties thereafter engaged in discussions regarding the scope of defendant's work and, upon plaintiff's request, defendant provided a revised quote that included the construction of a temporary access road. The parties' ensuing attempt to negotiate and enter into a written subcontract was unsuccessful and ultimately terminated upon defendant's notification to plaintiff that, due to allegedly "unreasonable" terms and conditions in the proposed subcontract, it would not enter into any agreement with plaintiff. As a result, plaintiff sought the desired excavating and landscaping services from a different subcontractor at a higher price.
In April 2017, plaintiff commenced this action, asserting a claim for breach of contract and seeking to recoup the difference between the amount it ultimately paid for excavation and landscaping work and the price quoted by defendant. In lieu of answering, defendant moved for, among other things, dismissal of the complaint (see CPLR 3211[a][1], [7] ). Plaintiff cross-moved for leave to file and serve an amended complaint substituting its breach of contract claim with a claim for promissory estoppel. After oral argument on the motions, Supreme Court advised the parties that it was converting defendant's motion to dismiss into a motion for summary judgment dismissing the complaint (see CPLR 3211[c] ) and afforded the parties an opportunity to submit additional proof. Following further oral argument, Supreme Court, among other things, granted plaintiff's cross motion for leave to file and serve an amended complaint and, finding that plaintiff had stated a viable claim for promissory estoppel and that questions of fact existed as to "what transpired during the contract negotiations," denied defendant's motion for summary judgment dismissing the complaint. Defendant appeals, and we affirm. To state a valid claim for promissory estoppel, a plaintiff must allege that the defendant " ‘made a clear and unambiguous promise’ " to the plaintiff and that the plaintiff reasonably relied on that promise to its detriment ( Bunkoff Gen. Contrs. v. Dunham Elec. , 300 A.D.2d 976, 978, 753 N.Y.S.2d 156 [2002], quoting R. Freedman & Son v. A.I. Credit Corp. , 226 A.D.2d 1002, 1003, 641 N.Y.S.2d 429 [1996] ; see Clifford R. Gray, Inc. v. LeChase Constr. Servs. , 51 A.D.3d 1169, 1170, 857 N.Y.S.2d 347 [2008] ). We agree with Supreme Court that plaintiff stated a viable cause of action for promissory estoppel here and that triable issues of fact – including, but not limited to, the parties' negotiation of the subcontract – preclude an award of summary judgment dismissing the complaint (see Bunkoff Gen. Contrs. v. Dunham Elec. , 300 A.D.2d at 976 n 2, 978, 753 N.Y.S.2d 156 ; cf. LAHR Constr. Corp. v. Kozel & Son , 168 Misc.2d 759, 765–766, 640 N.Y.S.2d 957 [S. Ct., Monroe County 1996] ). Accordingly, there is no basis upon which to disturb Supreme Court's order.
Garry, P.J., Lynch, Mulvey and Rumsey, JJ., concur.
ORDERED that the order is affirmed, with costs.