From Casetext: Smarter Legal Research

Acs Sys. Assocs., Inc. v. Safeco Ins. Co. of Am.

Supreme Court, Appellate Division, First Department, New York.
Dec 1, 2015
134 A.D.3d 413 (N.Y. App. Div. 2015)

Opinion

16252 150625/11.

12-01-2015

ACS SYSTEMS ASSOCIATES, INC., Plaintiff–Respondent, v. SAFECO INSURANCE COMPANY OF AMERICA, Defendant–Appellant.

Jaspan Schlesinger LLP, Garden City (Ryan E. Cronin and Charles W. Segal of counsel), for appellant. Cohen Seglias Pallas Greenhill & Furman P.C., New York (Shawn R. Farrell of counsel), for respondent.


Jaspan Schlesinger LLP, Garden City (Ryan E. Cronin and Charles W. Segal of counsel), for appellant.

Cohen Seglias Pallas Greenhill & Furman P.C., New York (Shawn R. Farrell of counsel), for respondent.

Opinion

Order, Supreme Court, New York County (O. Peter Sherwood, J.), entered on or about July 10, 2014, which, insofar as appealed from as limited by the briefs, granted plaintiff's motion for summary judgment on its payment bond claim, awarding it damages in the amount of $1,502,964, plus interest in the amount of $362.30 per day until entry of judgment and thereafter at the statutory rate, unanimously modified, on the facts, to delete the amount of damages awarded and substitute $1,501,310.77 therefor, and to delete the amount of interest per day until entry of judgment and substitute $362.26 therefor and otherwise affirmed, without costs.

The general contractor hired by the School Construction Authority (SCA) for a school renovation project obtained a payment bond from defendant to guarantee payment to its subcontractors and material suppliers. It is undisputed that SCA paid the general contractor in full for the work performed by plaintiff subcontractor on the project and that the general contractor failed to remit payment to plaintiff (see General Municipal Law § 106–b2 ). General Municipal Law § 106–b(2) requires a contractor who receives any payment from a public owner to make prompt payment to its subcontractors for their work “less an amount necessary to satisfy any claims, liens or judgments against the subcontractor ... which have not been suitably discharged.” Contrary to defendant's contention, an unrealized, admittedly “potential” claim for liquidated damages that the SCA may or may not assert against the general contractor does not constitute a claim for liquidated damages against plaintiff by which defendant or the general contractor may offset its payment to plaintiff (see NRS Constr. Corp. v. City of New York, 134 A.D.2d 219, 521 N.Y.S.2d 240 1st Dept.1987 ).

The parties dispute the number of days for which interest was awarded. We find that interest on amounts due to plaintiff on requisition 18 began to accrue on May 10, 2011, and accrued for 1148 days, until the date of the order appealed from, for a total of $287,348.49, and that interest on amounts due to plaintiff on requisition 19 began to accrue on October 4, 2011, and accrued for 1001 days, until the date of the order, for a total of $112,073.28. Accordingly, we modify the damages award as indicated.

We have considered defendant's remaining contentions and find them unavailing.


Summaries of

Acs Sys. Assocs., Inc. v. Safeco Ins. Co. of Am.

Supreme Court, Appellate Division, First Department, New York.
Dec 1, 2015
134 A.D.3d 413 (N.Y. App. Div. 2015)
Case details for

Acs Sys. Assocs., Inc. v. Safeco Ins. Co. of Am.

Case Details

Full title:ACS Systems Associates, Inc., Plaintiff-Respondent, v. Safeco Insurance…

Court:Supreme Court, Appellate Division, First Department, New York.

Date published: Dec 1, 2015

Citations

134 A.D.3d 413 (N.Y. App. Div. 2015)
20 N.Y.S.3d 72
2015 N.Y. Slip Op. 8784

Citing Cases

V.C. Vitanza Sons, Inc. v. Liberty Mut. Ins. Co.

There is little evidence that plaintiff was told that it was inadequately staffing the project or otherwise…

Summit Dev. Corp. v. Hudson Meridian Constr. Grp. LLC

First Hudson claims that it withheld to offset liquidated damages that the Owner may assess, however, at the…