From Casetext: Smarter Legal Research

A. L. Young Machinery Co. v. Cupps

Supreme Court of California
Mar 25, 1931
297 P. 538 (Cal. 1931)

Opinion

          Rehearing Granted April 23, 1931.

          In Bank.

          Action by the A. L. Young Machinery Company against I. H. Cupps and others, including the Indemnity Insurance Company of North America. From a judgment of dismissal in favoe of Indemnity Insurance Company of North America, plaintiff appeals.

          Reversed and remanded with directions.

          Appeal from Superior Court, San Joaquin County; C. W. Miller, Judge.

         COUNSEL

          Kirkbride & Gordon and Kirkbride, Wilson & Brooks, all of San Mateo, for appellant.

          Hartley F. Peart and Gus L. Baraty, both of San Francisco, for respondent Indemnity Ins. Co. of North America.


         OPINION

          PER CURIAM.

          Plaintiff appeals from a judgment of dismissal in favor of defendant insurance company entered after the trial court had sustained a demurrer to plaintiff’s second amended complaint without leave to amend. The facts as set forth in plaintiff’s complaint, so far as necessary to be considered on this appeal, are as follows:

          On November 26, 1924, defendant Cupps entered into a contract with the county of San Joaquin for the construction of a designated public highway in that county for the total sum of $10,459.50. On December 4, 1924, Cupps filed with the board of supervisors of the county of San Joaquin a bond in the sum of one-half the contract price, naming the defendant insurance company as surety. The bond specifically recited that it was given and executed pursuant to the Public Works Act of 1919 (St. 1919, p. 487). It is then alleged that during the performance of the work under this contract. and between January 13 and February 16, 1926, the plaintiff sold, delivered, and furnished to the contractor certain materials, supplies, implements, and machinery, consisting of one 30-foot steel frame bucket elevator complete; one 36 by 12 inch screen; a one-yard drag scraper; and certain pulleys, belts, lanterns, hose, and extension for the elevator; that there still remains due and unpaid on the above articles the sum of $1,405.75. It is then specifically alleged that the above equipment was ‘furnished for use under the contract above mentioned and were used in, upon, for and about the work contracted to be executed and performed under said contract, and were totally used up, consumed, destroyed and worn in, upon, for and about the performance of said work under said contract, and at the completion of said work had no further use or value for the purpose for which they were constructed, and were without salvage value.’ The date of completion of the work and the filing of the verified claim and withhold notice required by the statute are then alleged, it appearing from such allegations that these steps were all taken within the time and in the manner provided by law. Plaintiff asks judgment against the surety on its bond for the amount of the unpaid balance on the purchase price of the above equipment.

          The trial court, holding the view that the purchase price of such equipment was not covered by the bond, sustained a demurrer without leave to amend. Respondent surety company contended on the demurrer, and contends now, that it is not liable on the bond for the purchase price of such equipment, on the theory that the bond required by the public works statute allows recovery only for the reasonable rental value of such equipment, when such equipment is in fact rented, and allows no recovery for the purchase price thereof.

         As stated above, the bond in question was a statutory bond given and executed under the 1919 act, as it then read. That act provides that on public work the contractor must give a bond for at least one-half of the contract price of the work, which bond must guarantee that if the contractor ‘fails to pay for any materials, provisions, provender or other supplies, or teams, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, that the surety or sureties will pay the same. * * *’ The bond issued by respondent is broader in many respects than the bond required by the statute. Both appellant and respondent devote the major portion of their briefs to the question as to whether those provisions in the bond more onerous than those required by the statute can be enforced against the surety. It is not necessary to determine that point on this appeal. It is our opinion that the expressions ‘materials’ and ‘supplies’ found in the statute are sufficiently broad to include equipment of the nature involved herein, when such equipment is purchased for the particular job, and is entirely consumed thereon, except for normal salvage value. It is true, of course, that the purchase price of equipment capable of being used on more than one job, and which becomes part of the contractor’s general equipment, is not covered by the statute, but when the equipment is of such a nature that in the usual course of events it will be entirely used and consumed on the particular job for which it was purchased, it is our opinion that such equipment is included within the meaning of ‘materials’ and ‘supplies,’ as used by the statute. Respondent cites several mechanics’ lien cases which indicate that in those cases the lien extends only to those articles which physically go into the structure against which the lien is sought to be exerted. Those cases are not in point. It has repeatedly been held in reference to the 1919 act, and its predecessors, that such acts are to be more liberally construed than the mechanic’s lien statutes, and that the reasons for giving a limited construction to the latter are not applicable to the former. Pacific Wood & Coal Co. v. Oswald, 179 Cal. 712, 178 P. 854; Sherman v. Amer. Surety Co., 178 Cal. 286, 173 P. 161; French v. Powell, 135 Cal. 636, 68 P. 92; Associated Oil Co. v. Commary-Peterson Co., 32 Cal.App. 582, 163 P. 702. It has been held under the 1919 act and similar public work statutes, that rental of machinery, money, expended on the hiring of mule teams, money spent for provisions, harness, and other equipment, including scrapers, freight on mules and equipment, etc., are all recoverable against the surety. Williamson v. Egan (Cal. Sup.) 287 P. 503; Pacific Wood & Coal Co. v. Oswald, supra; Bricker v. Rollins & Jarecki, 178 Cal. 347, 173 P. 592, 594; Sherman v. Amer. Surety Co., supra; People’s Nat. Bank v. Southern Surety Co. (Cal.App.) 288 P. 827. The theory of these cases is that the statute was intended to cover all those things which have contributed to the improvement, whether directly by physically going into the construction, or indirectly, by being entirely consumed or used in the construction. In discussing the word ‘supplies,’ as used in a previous statute, the court in Bricker v. Rollins & Jarecki, supra, stated: ‘The ordinary meaning of this term in its general and accepted use is such as to include goods, wares, and merchandise of almost every kind and nature, whether used in the household or on the farm, or in any sort of productive or constructive work requiring the labor or service of men or animals or machinery. In the instant case they were furnished to be used and were actually used in advancing the work to be done under this contract, and in that sense entered into and became a component part of it and of the thing produced by it. This being so, we are of the opinion that as to the above classes of claims the trial court was correct in their allowance.’

          The true test in such cases was indicated by the Supreme Court of South Dakota in the recent case of Dennis v. Enke, 224 N.W. 925. In that case the question involved was whether the seller of a $3,000 tractor could recover from the surety the balance of the purchase price on a bond somewhat similar to the one here involved. We take the liberty of quoting from that case at some length. At page 927 of 224 N. W., that court, after analyzing certain earlier cases, stated:

          ‘This court has indicated in those cases that absolute and entire consumption in the work is not essential to liability, and liability is not necessarily prevented by the fact that there may be some salvage value in the materials or other supplies. It is enough if they were purchased directly and particularly for the work, were proper for the work, and were used therein, and consumed therein to such an extent that their residual value is a salvage value only as distinguished from a new value, as illustrated by pipe cut and threaded in certain lengths, lumber cut up and nailed in place to make a tool shed or a form for cement, etc. That these items have some residual value is of course true, but it is a very different value both in kind and amount from that of new lumber or new pipe in standard lengths and dimensions, and this court has held, under the circumstances of the cases heretofore considered, that the existence of some such residual salvage value did not necessarily prevent liability on the part of the surety.

         ‘The same rule was applied to the matter of minor tools and appliances in the Dennis Case [53 S.D. 646], 222 N.W. 269, where the items involved were two scrapers at $25.50 each, and certain repair items, and where the court below found as a fact (the appeal being from the judgment only) that all of the items were purchased for the purposes of the contract and were practically worn out in carrying out the provisions of the contract.’

         Again, at page 927 of 224 N. W., it is stated:

          ‘It is a matter of common knowledge that the performance of contracts of this kind requires a plant and equipment suitable therefor, many items of which are expensive and the purchase of which could not be justified by any single contract unless it was extremely large. It is further a matter of common knowledge that this kind of work is generally performed by persons who engage therein as a business and who maintain, for the purpose of the general contracting business, a very considerable amount of equipment intended and designed to be used in that business over a period of several years and in the performance of a number of contracts. We do not think it can be said to be within the contemplation of the parties that the surety on such a bond as this should be liable for the purchase price of tools and appliances which constitute and create, or become a part of, the general plant and equipment of the contractor, as distinguished from those minor tools and appliances which are consumed or practically consumed in the performance of a particular contract. The underlying principle which distinguishes between liability and nonliability is comparatively easy to perceive and grasp, difficult to phrase accurately, and still more difficult to apply precisely in border line cases. There must always be somewhat what of a twilight zone in these cases between liability and nonliability dependent upon the facts in particular cases. The problem is similar to that faced by the cost accountant of a manufacturing plant in determining whether a certain tool or appliance should be charged as a direct expense item to a particular job, or should be charged to plant and equipment; the established cost of its use in the particular job being ultimately taken into account by being embraced in the percentage of general overhead expense of plant equipment and factory charged to the particular job.

          ‘In order to create liability on the part of the surety for the purchase price of tools and appliances under these contract bonds, at least the following elements we think must be present: First, the tool or appliance must be purchased specifically and particularly for use in the performance of the particular contract; second, the use of such tool or appliance must be at least proper, if not reasonably necessary, in connection with and about the carrying out of the contract; third, the tool or appliance must be used in or about the performance of the contract; fourth, the tool or appliance must be such that it is reasonably to be expected in the natural course of events that its normal life for the purpose for which it was designed will be practically consumed by its use in and about the performance of the contract, and in this connection the facts of each particular case must be taken into consideration. For example, general experience indicates that a crew of men engaged in the performance of a contract of this kind lose and break numerous small tools and items of equipment, such as shovels, spades, hammers, etc., by reason of which they are for all practical purposes really consumed in the performance of the contract, notwithstanding the fact that such tools, if carefully handled and not lost, would be far from worn out by the actual amount of work for which they are used in the performance of a particular contract. If such small tools are purchased for the performance of the contract, are proper or reasonably necessary therefor, are used in such performance, and in such performance are lost or broken, and such loss or breakage is reasonably to be anticipated, it is entirely possible that the surety on the bond might be liable.’

          The articles herein involved fully comply with all the requirements suggested by the above case. It is our opinion that if the articles in question were totally used up in the usual and ordinary performance of the contract, so that nothing remained in excess of normal salvage, they then lost their identity as tools, appliances, implements, and machinery, and are included within the broader definition of the words ‘materials’ and ‘supplies.’ In such a case, in effect, they entered into and became a component part of the construction work. Certainly it is true that their full usefulness has entered into the work to the same extent as has hay for the horses or food for the men. Each case must be determined on its own facts. In the case at bar, the plaintiff has alleged the articles were purchased for the particular job and were entirely used up and consumed thereon. The truth of these allegations is admitted on demurrer. We are of the opinion that it was error to sustain the general demurrer without leave to amend. It is our opinion that plaintiff not only can, but has stated a cause of action. We do not mean by this to forecast the result of the action which, of course, must await upon the character of the evidence adduced at the trial.

          Defendant surety, in addition to the general demurrer, also demurred specially to the complaint. It may be that several of these specifications are meritorious. It is therefore ordered that the judgment be reversed, and the case remanded to the trial court, with instructions to overrule the general demurrer and to pass upon the various specifications of special demurrer.


Summaries of

A. L. Young Machinery Co. v. Cupps

Supreme Court of California
Mar 25, 1931
297 P. 538 (Cal. 1931)
Case details for

A. L. Young Machinery Co. v. Cupps

Case Details

Full title:A. L. YOUNG MACHINERY CO. v. CUPPS et al.[*]

Court:Supreme Court of California

Date published: Mar 25, 1931

Citations

297 P. 538 (Cal. 1931)

Citing Cases

Walter J. Bryson Paving Co., et al. v. State

So, the question for us to determine is whether or not merchandise of this character furnished to the…